Document zz2e72yrnQNLraJnEjQB1n1R6

Koppers Roof Systems 1977 preface This manual contains recommended roofing specifications and proce dures which are based on the many years of Koppers experience and ac cepted good roofing practice. They are intended to provide the architect, engineer, general contractor, and roofer with the proper information to plan and construct the best roof sys tems with the most time-proven ma terials availabie today. The availability of a Koppers surety bond or guarantee for roofing and flashing constructed according to the information contained in this manual under Koppers bond and guarantee procedure, and the publishing of these specifications and information shall not be construed as creating any warranty, expressed or implied, with regard to any roofing or flashing for which a bond or guarantee has not been issued. This roofing manual supersedes all previous roofing manuals and litera ture published by Koppers. The specifications and details con tained in this manual have been de termined to cover the proper proce dure for long lasting roofing systems for most areas of our country. In certain locations, minor variations in details and specifications may be appropriate due to unusual local con ditions. such as wind, temperature, humidity, etc. To assure the best ap plication of the proper specifications and details for your area we recom mend you consult your Koppers rep resentative. Notice: This reefing specification manual centaina the latest and best svailabie information as derived from Koppers tong experience in the roofing industry. The design criteria and details contained herein have been compiled and are offered as a guide for consideration to assist the architect, owner and roofer in an attempt to provide the best roof possible for long, troubiefree service. Responsibility, however, for design of any roofing system, remains with the architect or engineer and build ing owner. The contents of this manual are subject to change at the discretion of Koppers Company as future developments and experience are achieved. INDEX Coal Tar Diacuaaion Coal Tar Bitumen - Discussion Koppers Built-Up Roofing Material & System Diacuaaion General Requirements A Special Conditions Application: Roofing Built-up Roof Specifications deck construction Wood Plank/Plywood Poured Portland Cemegt Conorsts Precast Structural Concrete Sections Gypsum (Poured and Plank) and Lightweight Insulating Concrete Metal Decks (Insulated) Water Cooled Roofs and Water Retaining Roof* Wood Fiber no. of plies 5 4 4 3 4 3 S 4 4 3 4 3 4 3 Roof Application over Dycon Concrete*1) deck substrate Steel Centering Structural Concrete Formboard & Bulb Teas Koppers Multipurpose Membrane (KMM) Flashing Specifications Flashing Details Bonded A Guaranteed Roofing Program 4 3 4 3 4 3 (1) Also see Sweet's 3.4/Kop (2) Also see Sweet's 7.1 / Kop PAGE NO. 3 3 4 5-6 7 basic spec. no. 1 2 5 7 10 11 12 13 17 18 23 24 27 28 8 10 11 12 13 14 50 15-16 51 60 15-16 61 70 15-16 71 18-19 20-21 22-25 28-27 Coal Tar Tar is a vary familiar word, however, it has different meanings for different people. To many it is any black liquid adhesive or plastic substance; how ever, it is much more than this. It is a hydrocarbon, meaning it is composed primarily of carbon and hydogen and is therefore an organic compound. Tar is obtained from the "destructive dis tillation" of coal, primarily bituminous. This means when coal is heated to very high temperatures without con tact with air (thus not allowing the combustion of coal and its deriva tives) the coal molecules in effect are "cracked" into small molecules (gas), medium molecules (tar), and coke. We see, therefore that the more proper term is coal tar. Coal tar, through further distillation processes, is refined and separated into products of great commercial use fulness and value: PITCHES OR BITUMENS-of vari ous consistencies such as roofing material, waterproofing products, protective coatings for metals, masonry, etc. CREOSOTE--for wood preserving. CHEMICAL OILS--for use in the manufacture of drugs, dyea. paints, varnishes, cosmetics, plas tics, synthetic rubber, etc. Coal tar is indeed a vital and valuable product.that produces.materials for many industries in our world of today. KOPPERS 7.1/Ko __ . . Architectural and Coal Tar Bitumen A very valuable tar derivative used in the Roofing/Waterproofing industry is Coal Tar 8itumen. Its value is found in its superb water and corrosive re sistance qualities. Coal Tar Bitumen also performs as an excellent adhe sive when used in adhering tarred roofing felts together in built-up roof ing. These qualities are due to the unique properties that are endowed to Coal Tar Roofing Bitumen by nature. Without going into a highly technical chemical analysis, it can be most sim ply stated that Coal Tar Bitumen is a balanced organic compound using the Benzene Ring Molecule as its major building block. This molecule is illus trated at the right, the atoms of the Benzene Ring Molecule. Carbon (C) and Hydrogen (H) have a very strong molecular attraction or bond one to another which will not allow a water molecule to form and therefore be ab sorbed into the bitumen. Coal Tar Bitumen systems are inher ently resistant to molecular penetra tion by water. Coal Tar Bitumen Built-Up Roofing Systems are nature's own balanced answerto waterproofing and chemical resistance, especially to water and water-borne chemicals. 3 Koppers Coal Tar Bitumen Built-Up Roofing Materials and System Discussion Description Koppers Coal Tar Bitumen built-up roofing systems consist of alternate layers of Koppers Coal Tar Bitumen and Koppers tarred felt, surfaced with a heavy top pouring of Koppers Coal Tar Bitumen into which is embedded an aggregate. Koppers Cos) Tar Bitumen built-up roofing systems are used whenever a roof is exposed to water and/or cor rosion, and on all level or low sloped roofs where long, maintenance-free service is required. Features Coal Tar Bitumen built-up roofing pro vides one of the most durable roofing systems known due to its inherent superior waterproofing and weather ing characteristics. This is THE time proven roofing system for level and low sloped roofs. Coal Tar Bitumen provides numerous advantages to an owner, however, the superior performance of coal tar roof ing systems in the aress listed below make coal tar roofing systems unique in the roofing industry. 1. Coal Tar Bitumen has natural re sistance to water, air and water vapor penetration. A tight molecular structure enables Coal Tar Bitumen to withstand water penetration and resist oxidation of the roof surface. 2. Another unique feature of ooai tar roofing is its self-healing ability. Alligatoring and hairline cracks com mon to most materials, eventually cause damage to the roofing mem brane. Coal Tar Bitumen has a prop erty known as "cold flow1' which automatically corrects these condi tions before serious damage takes place. This "cold flow" feature heals small mechanical fractures at normal temperatures. 3. Application improvements. Because Koppers has expertise in the chemistry of aromatic coal tars. Coal Tar Bitumen was developed with the beneficial features of low fume evo lution at application temperatures, thus reducing potential irritation dur ing application. These features represent significant improvements which are in consort with the aims of government, labor, and industry in the areas of reduced air pollution and improved worker conditions. Uses 1. All 'dead' level roofs. 2. All water cooled roofs. 3. Low sloped roofs with occasional ponding. 4. Low sloped roofs with retarded drainage. 5. All buildings with level or low sloped roofs that are built for long service life. Slopes Koppers recommends that the maxi mum roof slope be one-half (ft) inch per foot for all built-up Coal Tar Bitu men roof systems. Koppers does, however, permit slopes up to two (2) inches per foot at flashings that in corporate tapered cants and for short run crickets or saddles for drainage, provided there Is adequate back nail ing, and these crickets or saddles do not cover more than 15% of the roof area. All felts must be backnailed on slopes one-half (16). inch per foot or more. For recommendations on roofing pro cedures for slopes over Vi inch per foot consult your Koppers represen tative. Underwriters Laboratories Underwriters Laboratories, Inc. Build ing Materials Directory, Guide No. (360018) TFJK-Bullt-Up Roof Covering Materials Lists Koppers Coal Tar Bitu men and tarred felts for use in con struction of Class A and B built-up roof coverings. Additional References: Roof Deck Constructions are listed under U. L Guide No. (380 RO) TGKX. Roof deck construction materials, such as vapor barriers, insulations, and adhesives are listed under U. L Guide No. (360 R13) TGYV. Bonds/Guarantees Koppers Bonds/Guarantees are avail able for 5, 10, 15, and 20 year terms. Roof bonds/guarantees cover ONLY the built-up roofing and flashing mem brane. For further details, please refer to Page 26 and 27 of this manual. Coal Tar Bitumen Property Water Specific Gravity 77/77 F (25/25C) Softening Point (Cube-in-Water Method) Rash Point (Cleveland Open Cup) Total Bitumen Soluble In Carbon Disulfide, percent Distillation Test Total Distillate by weight, given in percent: -- 0 to 315C (32 to 599F) -- 0 to 360C (32 to 680F) Method of Test ASTMD-95 ASTM D-70 ASTM D-61 ASTM D-92 ASTMD-4 ASTM D-20 Physical Properties Requirements -01.22 Min. 1.34 Max. 147F-162F 248F Min. (120C) 72 Min. 85 Max. 0.0 Max. 5.0 Max. 4 General Requirements and Special Conditions KOPPERS 7 : ko Architectural and Construction Materials Roof Structure System attachments vertically and laterally, and Precast Decks: (concrete, gypsum, wood In any building the performance of the Built-Up Roofing will- be affected to some degree by all of the parts of the roof struc ture system as well as the Inside and out side atmospheric environment. Each com ponent should be investigated for its com patibility with each of the others. The roof structure system may include any or all of the following: Outside Air Conditions Roofing System Peripheral Details (Bashings) Insulation (if present) Vapor Barrier (it present) Structural Deck including sub purlins (supports) Structural Framing the selection of the deck material and construction details including their ability to contain bitumens. (KOPPERS WILL NOTASSUME RESPONSI BILITY FOR DECK DEFECTS ON KOPPERS ROOFS. OR BITUMEN SEEPAGE.) The placing of conduits, bolt heads, etc., above the roof deck and below the roofing membrane is not recommended. All projections or openings in the deck should be completed prior to the applica tion of the roofing. Optimum adhesion to the deck is neces sary for good roof performance. Where Koppers Bitumen or steep asphalt is used for'adhssion, questionable decks may be fiber) Decks of these types, whether grouted or not, shall be caulked with Koppers Bashing Cement*which shall be applied so that the top surface is level and smooth. Felt stripping tour (4) to six (6) inches wide set in a troweling of the cement Is recommended to assist In level ing uneven joints and bridge the joint openings thus providing a better surface for the roofing materials. Wood Plank/Plywood: Wood shall be well seasoned, dry and preferably treated. End joints shall have adequate bearing. Loose or void knot holes, large cracks, etc., shall be covered with sheet metal. Lumber shall be a minimum of 1" nominal thickness. Air Space (If present) tested for dryness and adhesion by pouring Plywood shall be a minimum of V4* thick-. Ceiling (if present) one pint of the bitumen, heated to applica ness. Interior Air Conditions tion temperature, over a representative Lightweight Insulating Decks You will find information in this manual pertaining to materials and application methods other than tor built-up roofing. They are offered to assist the designer in area or areas of the deck. The deck is not satisfactory if the bitumen foams or bub bles, or upon coaling to ambient tempera ture may be stripped clean of the deck. Lightweight Insulating decks include light weight aggregate concrete (20 to 40 lbs. per cu. ft. oven dry density); foamed con crete, gypsum and thermosetting asphal r~ establishing their normal position in the tic decks. Except for Dycon Concrete, roof structure system. They should not be construed as part of the built-up roofing system, as endorsement, nor as part of the designated specifications other than to establish a suitable roofing base in the roof structure system. The proper design, specification and posi CondKIofta of surface to Receive Roofing All surfaces must be dry, reasonably smooth, clean, rigid and free from debris, loose materials, projections and holes which might cause rupture of the mem branes. lightweight insulating deck systems must be capable of venting excess water vapor to the underside. Koppers will not accept these lightweight insulating decks to be placed over vapor barriers, poured con crete substrates, unvented metals, or any type of base which will not permit these tioning of the various components of the materials to vent from the underside. It is roof structure system is the responsibility Metal Decks: Decks of this type must also necessary to prevent a water vapor pres of the building owner or his designer. Any be free from loose rust and oily sub sure build-up under the built-up rooting. subsequent failures, due to either the in stances. Deflection should not exceed Occasional, or spot vents through the roof stallation or lack of installation will not be 1/240 of the clear span and conform to ing as the only venting method are not Koppers responsibility. Factory Mutual requirements. satisfactory substitutes tor' underside or Decks Note: When applying insulation and roof ing over a perforated or acoustical type continuous vented systems. In addition, lightweight insulating decks The deck is the base over which the built- metal deck, it is recommended that a vapor shall have sufficient cohesive strength to up roofing, or insulation and built-up root barrier be installed prior to the application provide firm attachment of the roofing to ing Is applied. Where the term deck Is used of the Insulation or that a base sheet set in the deck and framing to prevent wind uplift in this manual without reference to insula steep asphalt be utilized as the first ply of damage or blow-offs. Nailable decks must tion, It shall designate the surface over Built-Up Roofing. This Is to reduce the be capable of developing at the very mini which roofing is to be applied. All decks possibility of Bitumen drippage. mum. a 40 pound nail pull-out or with shall be clean, smooth, dry, rigid and free drawal strength. If the materials do not of debris. Any deck defect shall be cor Poured Portland Cement Concrete, Pre achieve this value, additional fasteners rected before application of roofing. All decks shall be installed in accordance with the deck manufacturer's specifica tions and shall be in compliance with Koppers General Requirements. In approving any deck as satisfactory to receive a Koppers root, only the deck sur face is accepted. It is the responsibility of the building designer and the deck man cast Structural Concrete Sections, Poured Gypsum, Lightweight Insulating Concrete: Decks of these types with Inclines of onehalf (Vi) inch per foot or more shall permit nailing, or treated nailing strips must be set in the deck and installed prior to roof ing. Where insulation is specified, nailing strips may be secured to the deck surface of the insulation. Those strips should be will be required over and above those quantities described in the ensuing speci fication (standard is approximately 100 fasteners per square) to achieve a mini mum attachment, standard of 40 lb. per square foot. Koppers will not be responsi ble for failure of the Insulating deck to remain Integral or for disbonding of the roofing from the surface of the deck. ufacturer to provide for expansion and spaced not more than three (3) feet apart Provisions should be made wherever pos contraction in a manner that will provide and placed up and down and not across sible to provide additional venting such as a stable base for the rooting; for support the slope of the roof. Roof deck shall be notched wood perimeter nailers, etc., in of maximum anticipated loads; secure properly graded to outlets. conjunction with the venting from the 5 underside of th# dock. If board typa insula tion ia to ba appliad ovar a lightweight Insulating deck, provisions must bo mada batwaan tha All and tha board insula tion to pravant fill molstura from affacting tha Insulation and roofing. Malarial Protaction It is the responsibility of tha roofing con tractor to protect all roll roofing materials and roof insulation from ground or con struction moisture and weather before and during construction. Attachment Maximum adhesion or secure attachment of ail components in the roofing assembly is necessary for satisfactory long term per formance of tha roofing membrane. Ad hesive and/or fastaner quantities specified by tha manufacturer must be capable of passing a minimum uplift resistance of 40 pounds per square foot (pst). When Building Code requirements dictate a higher uplift resistance than our mini mum requirement, additional fasteners or adhesive will be required over and above the quantities described in the ensuing specifications. Solid mopping has been found to provide an uplift resistance in excess of 120 psf. Strip mopping, as suggested in the speci fications in this manual, has been found to provide an uplift resistance in excess of 60 psf. When nails or fasteners are used, they must be nailed through flat tin disks or have sufficiently large heads to prevent fracture or puncture through the roofing felts. The following are the names of some manufacturers who provide nail and/or fastening devices for use with built-up roofing: E/S Products, Inc. New Rochelle, NY Simplex Nail & Manufacturing Corp. Americas, GA Independent Nail Corp. Bridgewater. MA E. G. Building Fasteners Corp. New York. NY Koppers will not be responsible for any damage caused by or the result of unsatis factory attachment For further Information contact your Kop pers representative. Expansion Joints (BuiMng) Since all materials expand and contract due to temperature and/or moisture, the use, location, and design of-bufidlng ex pansion joints, especially in the roof struc ture system, should be taken into con sideration at the time of original building dasign. Although provisions for adequate expan sion joints are the responsibility of the building designer. Koppers offers the fol lowing recommendations foi'the protection of the rooting system against splits caused by expansion and contraction of the build ing. Building expansion joints should be installed. 1. On large roof areas at least 200 feet In each direction. 2. At all places where the structural sup ports and roof assembly change di rection. 6 3. Where type of adjoining deck materials change. Where control or expansion-contraction joints are provided in the structural steel, deck material, or dack system, provisions must be made for continuation of this re lief through the built-up roofing system. Koppers realizes that in a climate con- troled building there may be little or no expansion AFTER the building is in use, however, building expansion joints are still recommended baaed upon the following points: 1. During construction the building will not be under a steady state tempera ture/humidity condition so that thermal and moisture movement can be suffi cient to fracture the roofing. 2. If no building expansion joint is pro vided, the owner must keep the build ing at the steady state temperature and humidity condition at all times, as holi day shut-downs can fracture the roof ing due to the movement of the roof system resulting from temperature/hu midity variation. 3. If the occupancy Is fairly large, the sudden entrance on a rainy day of many rain-soaked employees may cause moisture movement in the roof structure system which can fracture the roofing. , Water Stops (Temporary Protection) Water stops consisting of two (2) plies of tarred felt and mopping of Coal Tar Bitu men for flat roofs or asphalt fbft and asphalt for steep roofs extending onto the deck at least 6' and 4' on top of the Insulation, shall be applied at the end of each day's work over exposed edges of insulation. These temporary protective measures must be removed cfeenty when stork is resumed to prevent blocking moisture vapor move ment to vented edge details. Cut Offs (Permanent Installation) Venting of roof insulation at trails, curbs, eaves, etc. is recommended for ail but a few special roof structures. Therefore, cut offs should not be installed at edges of insulation adjoining these areas for vent ing purposes. Cut-offs may be installed hotrever, pro vided they are constructed to run in one direction continuously to vented edges and provided no section of the roofing is Iso lated or blocked from venting. Koppers Steep Roofs For detailed specifications regarding KMM Aluminum Roofs, smooth surface asbestos roofs, or steep asphalt and gravsl. roofs, consult your Koppers representative or contact Koppers Company, Inc., Pitts burgh. PA. Vapor Barrier Vapor barriers are normally used where the heat flow direction and/or humidity within the building, during any climate or occupancy cycle, might cause the daw point or condensation to occur undar the built-up roofing within the insulation cham ber. It is important that the vapor barrier, when installed, provide a continuous seal, (including ventilators, skylights, peripheral walls, and other terminations) from the source of the watar vapor. Insulation Insulations come in varying thicknesses and sizes. Should the manner of attach ment as suggested conflict with that speci fied by tha individual insulation manufac turer, the insulation manufacturers spec ifications snaJI be followed and in addi tion, shall be in compliance with Koppers General Requirements. Good roofing practice dictates that the fol lowing points be considered when specify ing board type root insulation. 1. The roofing insulation must be kept dry at all times. It must be of a type ap proved by Koppers for use with a Kop pers built-up roof. It should only be applied over a deck complying with all of Koppers General Requirements. 2. If the deck slope is one-half (14) inch per foot or more the insulation must be able to retain nails or wood nailers must be installed perpendicular to the slope at each course of insulation. Spacing of nailers must be such that the insulation fits snugly with the nailers but must not be force fitted. 3. No more insulation shall be laid at any one time than can be protected by bitu men and felt in case of sudden weather changes. 4. Edges of insulation shall be brought closely together and shall not be forced into place. Where insulation joins ver tical surfaces, the Insulation shall be cut In a neat manner allowing approx imately one-half (Mr) inch clearance. 5. When more than one (1) layer of insula tion is used, joints in each layer shall not coincide. All layers shall be parallel to preceding layers. Wood Nailing Stripe All non-nailable decks require wood nail ing stripe at eaves, edges, wails, roof openings, etc. for proper secursment of metal flanges. Nailers must be securely and firmly attached to the deck or through to its supporting members. Nailers shall extend not less than 1" beyond the apron or flange. Rooting felts for all decks having a slope of'to" per foot or more must be back nailed and therefore non-nailable decks must be furnished with treated wood nail ing strips treated with a material com patible vdth bituminous roofing. Cold Storage and Freezer Buildings Koppers will not bond its built-up roofing over these structures if insulation or in sulation and vapor barrlar is installed over the deck unless there is an adequately ven tilated air space between the deck and insulated refrigerated area. For procedures on non-bonded built-up roofing applications or KMM installation, consult a Koppers representative or Kop pers Company, Inc., Pittsburgh, PA. Temporary Roofing Temporary roofing specifications are avail able for all Koppers Coal Tar Bitumen Built-Up Roofing Systems. Consult your Koppers representative for recommended specifications over various type decks for temporary roof construction. Application: Roofing r~\ Application of Bltunwna Recommended Weights par 100 sq. ft. (for estimating purposaa only) Koppers Coal Tar Bitumen Steep Asphalt Average Interpty Top Coating 25 lbs. 23 lbs. 75 lbs. 60 lbs. Avaraga intarpiy waighta ara based on long yaara of experience in good roofing practice, and taka Into account a reason* able variation in the amount of bitumen absorbed in different substrates, and the type of specification. Moppings of bitu men between tetts shall be continuous. Felt than not toeoh teK. The top pouring is most important it must be thorough and uniformly covered with specification aggregate embedded into the bitumen White the Bitumen Is SUB HOT. Recommended Temperature LimRationa: Koppers Coal Tar Bitumen Steep Asphalt Temp. *F Heated Application (max.) (min.) (recom.) 400 300 375 475 350 425 When rooting bitumens are overheated their waterproofing quantise are greatly reduced, and at the same time the volume of fuming is increased. In order to achieve the maximum benefits of low firming and unequafed waterproofing performance, it is imperative that Koppers Coal Tar Bitumen be heated within the temperature limita tions listed above. Close, supervision of heating is also good roofing practice for all bitumens. If heat is desired during a holding period at the jobsite while material ia not being drawn off and replenished as under nor mal usage, kettle temperature should be reduced and not permitted to exceed 350 F for Koppers Coal tar Bitumen or 425*F for steep asphalt. The kettle should be full lid closed. These temperatures ate applicable to job conditions and do not apply to holding or storage in kettles in excess of 4 hours. If bitumen la not to be used for periods over 4 hours, the kettle should be shut off. Koppers Coal Tar Bitumen may be con tained in 1000 gal. or gieatsr capacity heated and automatically controlled closed vessel tankers at 375*F for periods, not exceeding 96 hours. Application of Fett Plies of tstt must be Md shingle tasNoa. Where a water flow direction exists, felts should be applied so that the direction of flow is not against the laps.'Broom or press all piles of felt into the hot bitumen and lay without wrinkles, buckles or kinks, so that the finished root is free of pockets or blisters. Each felt ply shal{ be com pletely covered with a complete mopping of bitumen. The number of piles are controlled by varying widths of the edge laps. Fourply (4) roofing, for example, is achieved by lapping each ply approximately twentyseven and one-half (27Vi) inches or 14 of the width of the roll. Koppers felts are marked at the factory with lap linos for this purpose. Expept as specifically provided for in Koppers speci fications, application of felt lapping meth ods other than shingle fashion will not be permitted. When beginning a membrane roofing in stallation, appropriate width starting strips of felt shall be used at the starting point to achieve the specification ply build-up at that point so that successive felt appli cations will produce the pty requirements. Overlap ends of all connecting plies of felt (end tape) not leas than 10 Inches. End stripping or taping of these laps is not permitted. Koppers recommends that afi fails be becknaBed when the slope of the deck is one-hetf (V4) inch per foot or more. Application of Koppers Bitumen and Aggregate Surface The finsl application of Koppers Wbnfing is a triple weight application of Koppers Coal Tar Bitumen (approximately 79 lbs./ sq.) into which ia distributed an approved aggregate while the Bitumen is still hot. Benefits of aggregate surfacing 1. Protection from foot traffic of other trades during construction and after wards for routine root maintenance. 2. Weight as additional protection for wind uplift. 3. Reduced surface temperature. 4. Even flow of water to the drains. 5. Fire protection from burning brands. 6. Protect bitumen from the actinic rays of the sun. 7. Most important-by using an aggregate surface, an additional 75 Ib./sq. of Coal Tar Bitumen (the waterproofing agent) la included in the installation. The application of Koppers Coal Tar Bitu men and aggregate must be done et the time the felts are applied: except In pe riods of hot, dry weather when the top sur facing may be delayed overnight When the specifier desires glaze coating and/or all work to be completed the same working day, he shall be responsible to so state this requirement in his spKSlflestions. The aggregate surfacing must be applied Into the top pouring while the bitumen is still hot so that a uniform layer will be embedded and adhered. The completed roof assembly will have a uniform aggre gate surface. Depending on slag weights in certain parts of the country 400 lba. of slag per square may be required. Occa sionally on well applied roofs, small black globes known as "raspberries" or "black berries" will form In the roof surface. These are not detrimental to the roof. Aggregate Surfacing 4 The aggregate to be used should meet the ASTM Specification D1863-64. The basic KOPPERS 7.1/Ko Architectural and Construction Materials requirement for this aggregate are ea fol lows: Sieve Slia 14' Vt" %' No. 4 No. 8 Dust, max. pet. Moisture, max. % crushed stone and gravel Crocked roofing slag Unit weight (loose) mkt. lb. per cubic ft. Total Passing, Psrosnt 100 90-100 4-70 0-15 0-5 0.5 0.5 5.0 60 CoM Weather Application When roofing is applied at temperatures below 45*F, special precautions must be taken to insure the satisfactory perform ance of the finished roof. Before applying roofing, moisture, ice, snow, surface wa ter, etc., must be removed from the deck. Hot applied bitumens tend to congeal rap idly In cold weather. Extra care must be taken to set insulation or roofing as quickly as possible while the bitumen is still hot. Do not heat bitumens above the maximum temperature limit Dated above to compete aate for rapid chilling, insulated contain ers along with carefully timed material delivery methods, must be employed. Base Shoot Alternate When substituted for the first ply in a solid mop application specification, the Base Sheet shall be embedded in a solid mop ping of Koppers Steep Asphalt followed by thorough brooming to eliminate air pock ets, wnnkles, fish mouth, buckles, etc. The remaining two (2) or three (3) plies of Tarred Felt shall be solid mopped with Coal Tar Bitumen in accordance with the specification. When substituted in a nailing application specification, the Base Sheet may be used in lieu of the two nailed No. 15 tarred felts. Whan rosin sized or sheathing paper is a part of the original specification it shall remain and be applied beneath the Base Sheet. Edge laps shall be 4" and end laps shall be 6". The nailing pattern for the Base Sheet shall be 9* on center through the lap and V from the edge lap and stagger-nailed down the center of each sheet on V centers. (Note: This is approximately 100 nails per squere.) When specifying the Bask Sheet alternate use of the designation be as a subscript to the specification number. For example, when substituting base sheet in a roofing specification over Metal Deck-designate as 17wlbs. Net*: If Koppers Asphalt Coated Base Sheet (ASTM D-2626) is substituted for the first pty (plies) of the Coal Tar Bitumen roofing specifications, it must not be left exposed or used as a work surface prior to roofing completion. Qood roofing practice dictates that the total roofing membrane be com plete the seme day. 7 Coal Tar Bitumen Built-up Roof Specifications deck construction: Wood Plank/ Plywood SLOPE See pg. 4 SURFACE Aggregate For recommendations on wood and wood treatment, contact: Koppsrs Company, Inc* Foreat Product* Olviaion. Lumbar Seles Dept, 750 Koppara Bldg.. Ptttaburgh. PA 15219 Spec. No. 1--5 ply Spec. No. 2--4 ply Spec. No. 1 wl--4 ply Spec. No.2wi--3piy wi: with board type ineuletion Spec. No. 1 wiv--4 ply Spec. No. 2 wiv--3 ply wiv: with board type insulation and vapor barrier Treated wood should be ueed wnere a vapor earner ia required, aaa Page 5. PROCEDURE Select ciausea as required. Optional c/auses in italic. Copy In color danotaa built-up rooting specification Condition of Surface to Receive Roofing See Page 5. Materia) Quantity Requirements See Page 7. Preparation Below Insulation 1. The wood root deck shall be covered with one (1) layer of approved rosin-sized shesthing paper weighing approximately five (5) pounds per one hundred (100) square feet. The sheathing paper shall be lapped two (2) inches and secured to the deck by occasional nailing. 2. Two full thicknesses of Tarred Fait shall be laid over the entire surface, lap ping each sheet nineteen (19) inches over the preceding sheet and nailing the sheets in placa. Application of Vapor Barrier Below . insulation Nota: When vapor barrlsr is required, use these procedure in addition to Prepa ration Below fnsuictlon notod above. Lay over the entire aiirfaee two (2) full thicknesaes of Koppere'Tarred Felt, lap ping each aheat njgjgtaen (10) inches over the preceding sheet--mopping with Coal Tar Bltuman tha full ninataen (10) inchaa so that in no placa shall fait touch fait. 8 such matarial finds its way through the boards into the building. Qood practice demends the cushioning and blotting effect of a layer of Application of Insulation 1. Mop tha antira surface with a uniform coating of Coal Tar Bitumen into which, while hot, firmly embed the Insulation. For application of roofing materials over insulation follow Application of Roofing Materials procedure for concrete decks. Pages. nl fjrurftng Matartdb Dfrectty on Wood let Lay one ply of rosin sized or other approved sheathing paper weighing not lets than five (5) lbs. per 100 square feet lapping each sheet two (2) Inches and nail sufficiently to hold In piece. 2nd. Spec. No. 1 Spec. Mo. 2 Install two (2) pljes of Koppers Tarred Felts over entire surface lapped nineteen (19) inches. Nail on sight and one-half (8%) inch canters one (1) inch from edge lap. (Nota: This ia approximately 100 naila per 100 aq. ft.) Nall thanks are to be of required length for maximum withholding power. 3rd. Spec. No. 1 Apply thraa (3) pllaa of Koppara Tarrad Fait lapping pllaa twanty-lour and twothirds (24*6) Inchaa. Whate a/ope of dack root deck is exposed to sir pressure created from open doors or windows, tongue-endgrooved lumber should be used. Is ona-half Inch par foot or more, nail each sheaf of fait sis (0) inchaa from tha back adga on twanty-lour (24) Inch cantata. All laps shall be moppad with Coal Tar Bl tuman tha lull twanty-lour and two-thirds (24*6) Inchaa, so that In no placa shall fait touch talt. 3rd. Spec. No. 2 Apply two (2) pllaa of Koppara Tarrad Fait, lapping pllaa ninataan (19) inehaa. Whan tlopa of deck la ona-half ('6) inch par foot or more, nail each sheet six (6) Inchaa from tha baok adga on twenty-four (24) Inch cantata. All laps shall ba moppad with Coal Tar Bltuman tha full ninataan (19) Inchaa so that in no placa shall fait touch fait 4th. Pour over the entire surface of the roofing membrane, a uniform coating of Coal Tar Bitumen Into which, while hot embed not leas than four hundred (400) pounds of gravel or three hundred (300) pounds of slag for each one hundred (100) square feet. General Requirements on pages 3,3 end 7 end OetaS Specttiqatione on pages 20 through 25 are a part of this specification and must be adhered to where applicable. t Specifications (continued) ''"N Qrav*! or Slog Emboddod In Pouring of Cot! Ttr Situmon Alfomtto Ctyart of Cot! Ttr fiftumtn tnd Ttrrtd Flt Mopoing of Cot! Ttr Situmon Inttilttion Embtddtd in Coal Ttr Situmtn Two Laytrt of Cot! Ttr Bitumon tnd Ttrrtd Ftlts Pourtd Concrete KOPPERS n ko Architectural and Construction Materials deck construction: Poured Portland Cement Concrete SLOPE See pg. 4 SURFACE e Aggregate Spec. No. 5--4 ply Spc. No. 7--3 ply Spoc. No. 5 wi--4 ply Spoc. No. 7 wi--3 ply wi: with board typo insulation Spoc. No. 5 wiv--4 ply Spoc. No. 7 wiv--3 ply wiv: with board typo insulation and vapor barrier Detail of Specification No. 5 wfv Pound concrete decks sometimes cause trou ble because the built-up roofing is laid before the deck is thoroughly dry. When this happene the result is a blistered end buckled membrane or. just as senous, the insuletion curt* end mikes in unsatisfactory job. The roofing con tractor. backed by the architect should Insist on a thoroughly dry dock befora beginning work. He should also see to It that the deck is free of loose sand, frozen scale and othsr foreign matter. Protections should be removed, low points tilled with cement grout or other suitable material, and ell cracks pointed up. PROCEDURE Select clauses as required. 0ptlonal clauses in italic. Copy in color danotaa built-up rooting spaclflcation Condition of Surface to Receive Roofing See Page 5. Material Quantity Requirements See Page 7. Application of Vapor Barrier Below Insulation 1. Apply a uniform coating of Coal Tar Bitumen to the deck. 2. Lay over the entire surface two (2) full thicknesses of Koppers Tarred Pelt, lap ping each sneet nineteen (19) Inches over the preceding sheet--mopping with Coal Tar Bitumen the full nineteen (19) inches so that in no place shall felt touch felt. 3. Extend all plies of felt up vertical sur faces and cut off at height of insulation. Application of Insulation Apply a uniform coating of Coal Tar Bitumen ovarthe entire surface into which, while hot. embed the insulation. If there are two (2) layers of insulation mop the entire surface of the first layer with Coal Tar Bitumen into which, while hot, embed the socond layer of insulation. Application of Roofing Materials 1st Mop deck (or insulation--aa applica ble) completely with Coal Tar Bitumen. 2nd. Spec.No.> Apply over tha andra suriaca, tour (4) pllat of Koppars Tarrad Fait, lapping pllaa twanty-aavan and ona-halt (27Vi) Inchaa. Mop solidly batwaan each 27Vi Inch lap with Coal Tar Bltuman so that In no plaea shall lalt touch fait. 2nd. Spec. No. 7 Apply over the andra aurfaca thraa (3) pllaa of Koppars Tarrad Fait, lapping pllaa twanty-four and two-thirds (24H) Inchas. Mop solidly batwaan each 24% Inch lap with Coal Tar Bltuman so that In no placa shall fait touch MM.---: Where slope of dock Is one-half (Vi) inch per foot or more and deck permits nailing, nail along back or upper edge of each sheet on twenty-four (24) Inch contan. When deck does not permit nailing, nailing stripe an required and each sheet nailed along back or upper edge at spacInga to assure penetration of nailers. 3rd. Pour over the antfn surface of the roofing membrane a uniform coating of Coal Tar Bltuman into which, while hot, mbed not less than four hundred (400) pound* of gravel or three hundred (300) pounds of slag tor-each one hundred (100) square feet General Requirements on pages 5,6 and 7 and Detail Specifications on pages 20 through 25 are a part of this specification and must be adhered to where applicable. 9 Specifications (continued) deck construction: Precast Structural Concrete Sections SLOPE See pg. 4 SURFACE Aggregate Qrsvef or Stag Embedded tn Pouring of Coal Tar Bitumen Layers of Coal Tar Bitumen and Tarred Felt Mopping of Coal Tar Bitumen insulation Embedded m Coal Tar Bitumen Two Layers of Coal Tar Bitumen end Tarred Felts Spec. No. 10--4 ply Spec. No. 11--3 ply Spec. No. 10 wi--4 ply Spec. No. 11 wi--3 ply wl: with board type insulation Spec. No. 10 wiv--4 ply Spec. No. 11 wiv--3 ply wiv: with board type insulation and vapor barrier Detail of Specification No. 11 wiv Strip MODDtngs of Coal Tar Bitumen Flitting Clmint or Flitting Clmint and *" Stripping Sa* Pig* 5 Pmcaat concnti structural sections demand the same recommendation! se poured con* Crete decks, although the pretence of mois ture, due to insufficient drying time. Is not likely. It the contractor finds one or more sitbe resting unevenly, with edges projecting above the surface, this should be corrected by reset ting or leveling off. Open-call aggregate is not acceptable for filling or leveling low trass. All joints, grouted or not. should be caulked with trowel-grade asphaltic plastic esmant Slab sidaa and *nda should be square._rest firmly and evenly on aupporting members, and be installed to prevent lateral and vartical movement. PROCEDURE Select clauses as required. Optional clauses in italic. Copy in color denotes built-up roofing specification Condition of Surface to Receive Roofing See Page 5 Material Quantity Requirements See Page 7. Application of Vapor Barrier Below Insulation 1. On precast concrete slab or tile deck, strip mop with Coal Tar Bitumen up to four (4) inches from the edge of each joint. Not lass than 30% of the surface muat be mopped, at a min. rata of 10 lbs. per 100 square feet. 2. Lay over the entire surface two (2) full thicknesses of Koppera Tarred Pelt lap ping each sheet nineteen (19) inches over the preceding sheet--mopping with Coat Tar Bitumen the full nineteen (19) inches so that in no place shall felt touch felt 3. Extend all plies of fait up vertical sur faces and cut off at height of insulation. Application of Insulation: Over Vapor Barrier. Apply a uniform coating of Coal Tar Bitumen ovar the entire surface into which, while hot. embed the insulation. If there are two (2) layers of insulation (a.g. as required for pre-stresses concrete sections) mop the entire surface of the first layer with Coal Tar Bitumen into which, while hot. embed the second layer of insulation. Over Deck. On precast concrete slap or tile deck, strip mop with Coal Tar Bitumen up to four (4) inches from the edge of each joint Not leas than 30% of the surface must be mapped, at a minimum of 10 Iba. per 100 square feet While hot, embed the Insulation. If there are two (2) layers of insulation (a.g. as required for pra-stressed concrete sections) mop the entire surface of trie first layer with Coal Tar Bitumen into which, while hot, embed the second layer of insulation. For application of roofing materials over insulation follow Application of Roofing Materials procedure for concrete decks. Page 9. Application of Rooting Materials 1st Each slab shall ba spot or strip mopped with Coal Tar Bltuman, keeping Bitumen mopping back at least four (4) inches from til edges of each slab joint Not laaa than 30% of the surface muat be mopped. When applying ovar insulation, mop Insulation completely with Coal Tar Bitumen. 2nd. Spec. No. 10 Apply over the entire surface four (4) plies of Koppera Tarred Pelt lapping pile* twenty-seven end one-half (27%) inches. Mop solidly between each 27% Inch lap with Coal Tar Bitumen so that in no place shall felt touch felt 2nd. Spee.No.11 Apply over the entire surfeee three (3) piles of Koppera Tarred Felt, lapping plies twenty-four end two-thirds (24%; inches. Mop solidly between the 24% -inch lap with Coal Tar Bitumen so thet In no place shall felt touch fait. Where slope of deck Is one-half (%) inch per foot or'mora and the deck permits nailing, nail along back or upper edge of each sheet on a maximum of twenty-four (24) inch cantor*. Where deck does not permit nailing, nailing strips shall be in stalled and each sheet nailed along back or upper edge at spacing* to assure pene tration of nailers. 3rd. Pour over the entire surface of the roofing membrane a uniform coating of Coal Tar Bltuman Into which, while hot, embed not less than four hundred (400) pounds of gravel or three hundred (300) pounda of slag for each one hundred (100) square feet General Requirement! on pages 5,8 and 7 and Beta! Specifications on pages 20 through 28 are a part of this specification and must be adhered to where applicable. 10 Specifications (continued) The same recommendations applying to pra cist conerata slabs apply to pracist gypsum slabs and gypsum mstal bound planks. All uneven slabs should bs reset or leveled off so that the roof will be laid on a flat and svsn surface, free from projections and low areas. Because these slabs are precast the possi bility of a high moisture content being present is more remote than In the poured gypsum roof or lightweight insulating concrete roof deck. Pound gypsum decks sometimes cause trou ble because the built-up roofing is laid before the deck la thoroughly dry. When this happens the reeult Is a blistered and buckled mem brane. or, just as serious, insulation curls and makes an unsatisfactory job. The roofing con tractor, backed by the architect, must insist on a thoroughly dry deck before beginning work. He should also see to it that the deck Is free of loose sand, frozen scale and other fomign matter. Projections should be nmoved, low points filled with cement grout or other suit able material, and all cracks pointed up. KOPPERS 7.1/Ko Architectural and Construction Materials deck construction: Poured Gypsum Precast Gypsum Lightweight insulating Concrete SLOPE e See pg. 4 SURFACE e Aggregate Spec. No. 12--5 ply Spee. No. 13--4 ply Spec. No. 12 wi--4 ply Spoc. No. 13 wi--3 ply wi: with board typo insulation Spec. No. 12 wiv--4 ply Spec. No. 13 wiv--3 piy wiv: with board typo insulation and vapor barriar See paga 5 for Lightweight Insulating Pecks Thermosetting Asphaltic Concrete: Base sheet must be used as first ply--saa paga 7. PROCEDURE Salact clauaas as required. Optional clauaaa in italic. Copy In color danotaa built-up rooting apaoitioation Condition of Surface to Receive Roofing See Paga S. Material Quantify Requirements Saa Paga 7. Application of Membrane Below Insulation 1. Apply over antira surface one (1) ply oI Koppara coated baaa ahaat, lapping each ahaat lour (4) inchaa over pracadlng ahaat and nailing at lap no laaa than nina (9) Inchaa and ataggar nailad down cantar of aach ahaat on aightaan (IB) Inch cantata. 2. Extend plies up vertical surfaces and cut off at haight of Inaulatton. For vapor barriar provisions contact your Koppara Representative. Application of insulation Over Membrane (or Deck) Apply a uniform coating of Coal Tar Bitumen over the entire surface into which, while hot. embed the inauietion. If there are two (2) layers of inauietion mop the entire surface of the first layer with Coal Tar Bitumen Into which, while hot, embed the second layer of Insulation. For application of roofing materials over inauietion follow Application of Roofing Materials procedure for poured concrete, PagaS. AppBeatton of Roofing Materials to Deck 1st Install two (2) plies of Koppara Tarred Felt over entire surface lapped nineteen (19) inches with approved nails. Neil on eight end one-half (8tt) centers one (1) inch from edge lap. (Note: This Is approximately 100 nails per 100 sq. ft). Alternate: Apply over antlra surface one (1) ot Koppara coated baaa ahaat, lapping aach ahaat tour (4) inchaa over pracadlng ahaat and nailing at lap no laaa than nlna (9) Inchaa, and ataggar nailad down cantar o1 aach ahaat on aightaan (18) inch cantata. 2nd. Spe&No. 12 Apply thraa (3) pltaa of Koppara Tamd Fait, lapping pllaa twanty-tour and twothlrda (24to) Inehaa. Whara alopa of dock la ona-halt ('A) inch par foot or more, nail aaeh ahaat of /eft six (8) inehaa from tha back edge on twanty-tour (24) inch can tata. All lapa ahall ba moppad with Coal Tar Bltuman tha full twanty-tour and twothlrda (24H) Inchaa, so that in no placa ahall fait touch fait. 2nd. Spec. No. 13 Apply two (2) pllaa of Koppara Tarrad Fait, lapping pllaa ninataan (19) inchaa. Whara alopa of deck la ona-halt ('A) inch par foot or more, nail aach ahaat six (6) inchaa from tha back adga on twanty-tour (24) inch cantata. All lapa ahall ba moppad with Coal Tar Bituman tha lull ninataan (19) Inchaa ao that in no placa ahall fait touch fait. 3rd. Pour over the entire surface of the roofing membrane a uniform coating of Coal Tar Bitumen into which, while hot, embed not lees than four hundred (400) pounds of gravel or three hundred (300) pounds of slag for each one hundred (100) square feet General Requirement! on pages 5, 8 and 7 and Detail Specifications on page* 20 through 2S are a part of this specification and must be adhered to where applicable. 11 Specifications (continued) deck construction: Metal Decks (Insulation Required) SLOPE* See pg.4 SURFACE Aggregate Spec. No. 17 wl--4 ply Spec. No. 18 wl--3 ply wi: with board type insulation Spec. No. 17 wiv--4 ply Spec. No. 18 wiv--3 ply wiv: with board type insulation and vapor barrier _ Qrsvei or Slag Emfitddtd m Pouring of Coat Tar Bauman Alternate Layers of Coal Tar and Tarred Pelt Bitumen Moopmg of Coal Tar Bitumen Inauiation Adhared to Vapor Barrier Detail of Specification No. 17 wiv It is absolutely nscsssary to install board typa insulation on a matal deck bafora tha built-up roofing it appliad. A matal dack must ba clean, smooth, and proparty anchored to tha steal purlins and all joints correctly lapped and faatanad. Typa of matal dack. fluta opening and van'oua other factors determine the typa and thicknesa of insulation required. Consult your Hoppers representative for recommendations. Metal roof decks shall bs designed so that they will not have a daflection exceeding 1/240 of clear span under all types of loads (live & dead). Designer should taka into ac count roof traffic conditions including mechan ical equipment uasd tor roof application. PROCEDURE Select clauses as required. Optional clauses in italic. Copy in color denotes built-up rooting specification Condition of Surface to Receive Roofing See Page 5 Material Quantity Requirement! See Page 7 Application of Vapor Barrier Below Inauiation A. Fait Typa Coat the ribs of the metal deck with Steep Asphalt and then install two (2) full thicknesses of Koppers No. 15 Asphalt Felt, lapping each sheet nineteen (19) inches over the preceding sheet, mopping with Steep Asphalt the full width of the nineteen (19) inch lap. Extend all felt up vertical surfaces and cutoff at height of insulation. Application ol Inauiation and Roofing Materials 1st a. Install insulation in steep asphalt applied to deck at rate of 12 to 15 lbs. per 100 sq. ft. and place insulation while steep asphalt is still molten to provide good ad hesion. See Attachment Page 6. b. If slope of deck is one-half (V4) inch par foot or more, insulation must be able to retain nails and, in addition to being set in steep asphalt, insulation must be fast ened to the metal deck with approved mechanical fasteners placed at alt four (4) comers and the center of each sheet. It two layers of insulation are specified, top layer joints shall not coincide with joints of bottom layer. Fasteners shall be driven after the top layer of insulation is installed. c. if U.L. and F.M. requirements are a (actor for insurance rating, insulation must be listed and approved in accordance with their current data. 2nd. Mop a uniform coating of Coal Tar Bitumen over the insulation preceding the applicetion of rooting membrane. 3rd. Spec No. 17 wt Apply over the entire surface, four (4) plies of Koppers Tarred Felt, lapping plies twenty-seven and one-halt (27Vi) inches. Mop solidly between each 27Vi inch lap with Coal Tar Bitumen so that in no place shall felt touch felt. 3rd. Spec. No. 18 wi Apply over the entire surface, three (3) plies ot Koppers Tarred Felt, lapping plies twenty-tour and two-thirds (24tt) inches. Mop solidly between each 24% inch lap with Coal Tar Bitumen so that in no place shall talt touch felt. If slope ot roof is one-halt (Vi) inch per foot or more, each ply ot felt shall be nailed along the back or upper edge on twenty-four (24) inch centers. It base sheet alternate is used, each ply of basa sheet shell be nailed two (2) inches from the back or upper edge on twenty-four (24) Inch centers. 4th. Pour over the entire surface of the roofing membrane a uniform coating of Coal Tar Bitumen into which, while hot. embed not less than four hundred (400) pounds of gravel or three hundred (300) pounds of slag for each one hundred (100) square feet General Requirement! on pages 5,1 and 7 and Detail Specifications on pages 20 through 25 are a part of this specification and must be adhered to where applicable. 12 ft rs Specifications (continued) Two Uyr* of Qrivtf or Slog Emboddtd in two (2) Pouring* of Co*l Tar Bituman Altsmats Livers of Coal Tar Bilumm and Tarrad Fait Mopping of Coal Tar Biluman Pouring Conerata. Qypaum or Pracaat Conerata Slap Oaek Detail of Specification No. 23 WATER COOLED ROOF: Watar is designed to bs contained on tha roof it ill Hum it a constant livil by mint of i drainig* lyitsm and a watar sourca. (Saa nota on cold waathar condition!.) Watar Coolad Roofs also includa spray pond roofs whara tha roof is constantly sprayed with watar but not nacassarily kept at a constant laval. Watar Coolad Roofs should ba applied ovar pound conerata, gypsum or precast concnta decks. IT IS MANDATORY THAT THE WATER COOL ING SYSTEM BE CLOSED DOWN AND THE ROOF DRAINED PRIOR TO COLD WEATHER. Neither roofing nor tha structun will withstand tha expansion caused by iea formation. WATER RETAINING ROOFS: PROCESS WATER: Water from manufacturing process, cooling towers, ate., that regularly deliver watar across tha roof for normal dminaga. RETARDED DRAINAGE PONOING: Drains am sized to deliver a controlled amount of watar to tha storm system and thus regularly neces sitate heavy watar ponding. KOPPERS 7.1/Ko Archrtectunland Construction Metarule deck construction: Poured Concrete e Poured Gypsum: Precast Concrete Water Cooled Roofs Water Retaining Roofs SLOPE See pg. 4 SURFACE Double Aggregate (with double pour) Spec. No. 23--4 ply--on dock Spoe. No. 24--3 ply--on dock Spoc. No. 23 wi--4 ply Spoc. No. 24 wi--3 piy wi: with board typo insulation Spoc. No. 23 wiv--4 ply Spoc. No. 24 wiv--3 ply wiv: with board typo insulation and vapor barrier Note: The base sheet alternate shall not be used. PROCEDURE Select clauses as required. Optional pounds of gravel or three hundred (300) specifications used shall be as follows: clauses in italic. pounds of slag for each one hundred (100) Water Cooled Roofs--Koppers Flashing Copy in color denotes built-up rooting specilication square feet. If slops of roof is one-half (Vi) inch per foot or more, each ply of felt shall be Specification No. 110 only shall be used. See Pg. 21. Water Retaining Roofs--Either Koppers Condition of Surface to Receive Roofing See Page 5. nailed along the back or upper edge on twenty-four (24) inch centers. 4th. All loose gravel or slag shall be Flashing Specifications No. 108. No. 710 or No. 110 shall be used. See Pg. 20 & 21. d. Insulation and vapor barrier, if used, Material Quantity Requirements swept from surface and a second uniform shall be applied according to procedures See Page 7. Application of Built-up Roofing pouring of approximately eighty-five (85) pounds of Coal Tar Bitumen shall be applied over the gravel or slag, into which, found in basic specifications 5 & 7 (Pg. 9). 10 & 11 (Pg. 10), 12 & 13 (Pg. 11). e. Specifications 23 and 24 may be ap 1st Mop deck completely with Coal Tar Bitumen. ' while hot. shall be applied a second layer of three hundred (300) pounds of gravel or plied over wood deck (Pg. 8) or metal decks (Pg. 12) only if used as Water Re 2nd. Spec No. 23 two hundred (200) pounds of slag for each 100 square feet. The entire surface shall taining Roofs. Insulation and vapor barrier, if used shall be applied according to pro Apply over the entire surface four (4) then be thoroughly broomed free from all cedures found with these specifications. plies of Koppers Tarred Felt, lapping plies loose gravel or slag. It is advisable to roil f. Roof Structure design live loads for twenty-seven and one-half (27'A) inches. Mop solidly between each 27Vt inch lap the finished surface with a light roller so that aggregate is thoroughly embedded. specifications 23 and 24 shall be a mini mum of 50 psi and deflection shall not with Coal Tar Bitumen so that In no place shall teit touch felt. nNO-fV-e- exceed 1/360 of the span, both in addition to the anticipated weight of the water. 2nd. Spec No. 24 a. At points where water pressure from the spray may be excessive, the roof Insulation joints must be taped. Vapor barriers must be two/rtfy, solid mopped. Apply over the entire surface three (3) surface should be protected with treated Use steep asphalt over metal decks. Wood plies of Koppers Tarrad Felt, lapping plies board platforms or other suitable construc must be treated to prevent warping (sea twenty-four and two-thirds (24H) inches. tion to break the force of the water. These "wood nailing strips"). t Mop solidly between each 24% inch lap platforms should be laid on top of the roof with Coal Tar Bitumen so that in no place surface and not fastened to the deck. shall lelt touch felt. b. Insulation under a Water Cooled Roof All felt shall be turned up not lass than should be of a type which is rigid, dimen four (4) inches at vertical surfaces. 3rd. Pour over the entire surface of the roofing membrane a uniform coating of Coal Tar Bitumen into which, while hot. embed not lesa than four hundred (400) sionally stable with high compressive strength and of a sealed cellular structure such as Foamgias. c. At all points where roofing membrane meets a vertical surface the flashing General Requirements on pages 5,6 and 7 and Detail Specifications on pages 20 through 2f are a part of this specification and must be adhered to where applicable. 13 Specifications (continued) deck construction: Wood Fiber SLOPE See pg.4 SURFACE Aggregate Spec. No. 27--4 piy Spec. No. 28-3 piy Spec. No. 27 wi--4 ply Spec. No. 28 wi--3 ply wi: with board type insulation Spec. No. 27 wiv--4 ply Spec. No. 28 wiv--3 ply wiv: with board type insulation and vapor barrier All decking mutt be instilled in strict accordtnce with the perttcuier deck manufacturer's reeommendttiont for mttelletion. Deck ma- teriel must be orotected during shipment job site storage end prior to rooting eopllcttion. No plenkt which htve become structurally weekened due to moisture, fractures or mutlleted edges mey be used. All joints must be level end preferably grouted full end level with pltnk surfaces are recommended by the deck manufacturer. All planks must be well anchored to supporting members to resist movement in t fashion rseommendad by the deck manufacturer. Any planks which bow or deflect or do not seat securely must be re placed. Responsibility for the selection of a particular type of wood fiber deck, Its installa tion. provision for expansion and contraction, Its suitability to job requirements, and its ability to support anticipatad loads in its en vironment rests with the designer and deck manufacturer. PROCEDURE Select clauses as required. Optional clauses in italic. Copy in color danotaa built-up rooting specification Condition of Surface to Receive Roofing See Page 5. Material Quantity Requirements See Page 7. Insulation and Vapor Barrier 1. Insulation without Vapor Barrier. In stall insulation in a uniform coating of Type ill steep asphalt Nailable insulation not exceeding one (1) inch thick may be installed using 14k inch Simplex Tube-Lok nails at all four corners and at center of board. Installation of roofing over insula tion shall be as per specification outlined below with base sheet mopped solidly to the insulation in steep asphalt For bonded roofing applications, fast eners. other than Tube-Lok nails, must be acceptable to Koppers. Fasteners shall be applied at the minimum rate of one (1) per square foot as recommended by the Struc tural Wood Fiber Products Association. 14 2. Insulation with Vapor Barrier. Install two (2) plies of No. IS asphalt felt lapped nineteen (19) inches in Type III steep as phalt as per 1st paragraph of this specifi cation. Plies shall be mopped solidly so that in no place shall felt touch felt. Install insulation in solid mopping of steep as phalt. Roofing over insulation is to be in accordance with the details of the specifi cations below with base sheet mopped solidly to the insulation. Application of Roofing Materials 1st Install one (1) ply of Koppers asphalt coated base sheet over entire sur face in solid mopping of Type III Steep .Asphalt so that base sheet shall not touch tha deck surface. Firmly broom or press entire surface of base sheet into hot steep asphalt so that no air pockets, wrinkles, buckles or kinks shall occur. Minimum side laps shall be four (4) inches and mini mum end laps shall he six (6) inches. All laps shall be continuously sealed the full width of tha lap. 2nd. Spec. No. 27 Apply three (3) plies of Koppers Tarred Felt lapping plies twenty-four and twothirds (24%) inches. Where slope of deck is one-halt (% ) inch per toot or more, nail each sheet of felt six (6) inches from the back edge on twenty-four (24) inch canters. All laps shall be mopped with Coal Tar Bitumen the full twenty-four and two-thirds (24%) inches, so that in no place shall felt touch felt. 2nd. Bpee. No. 2S Apply two (2) plies of Koppers Tarred Felt, lapping plies nineteen (19) inches. Where slope of deck is one-naif (Vi) inch per foot or more, nail each sheet six (6) inches from the back edge on twenty-four (24) inch centers. All laps shall be mopped with Coal Tar Bitumen the full nineteen (19) incites so that In no place shall felt touch felt. 3rd. Pour over the entire surface of the roofing membrane a uniform coating of Coal Tar Bitumen into which, while hot, embed not less than four hundred (400) pounds of gravel or three hundred (300) pounds of slag for each one hundred (100) square feet General Requirements on pages S, 6 and 7 and Dotal SpedflcaUone on pages 20 through 25 are a part of tMe specification and must be adhered to where applicable. DYCON CONCRETE ROOF DECKS BUILT-UP ROOFING SPECIFICATIONS DECK CONSTRUCTION: KOPPERS 7.1 /Ko Architecture and Construction Matenais Detail of Specification No. 60 Detail of Specification No. 50 Substrate: Steel Centering Spec. No. 50--5 ply Spec. No. 51--4 ply Substrate: Structural Concrete (Monolithic Precast or Vapor Barriers) Spec. No. 60--5 piy Spec. No. 61--4 piy Spec. No. 50 wi--4 pty / Spec. No. 51 wi--3 ply board type inauiatlon Spec. No. 60 wi--4 ply Spec. No. 61 wi--3 ply board type insulation Spec. No. 50 be--4 ply Spec. No. 51 ba--3 ply base sheet as first piy of roofing Spec. No. 60 bs--4 piy Spec. No. 61 bs--3 ply base sheet as first ply of roofing Detail of Specification No. 70 bs Substrate: Formboard and Bulb Tees Spec. No. 70--5 ply Spec. No. 71--4 piy Spec. No. 70 wl--4 ply Spec. No. 71 wi--3 piy board type insulation Spec. No. 70 bs--4 ply Spec. No. 71 bs-3 ply base sheet as first ply of roofing SLOPE See pg.-4 SURFACE Aggregate The following specifications apply only to approved Oycone concrete formulations. The general requirements of Koppera cur rent built-up roofing manual are part of this specification and must be adhered to where applicable. PROCEDURE Select clauses at required. Optional clauses in italic. Copy In color denotes built-up rooting specification Condition of Surface to Receive Roofing See Page 5. Material Quantity Requirements See Page 7. Application of Membrane Below Rigid Board Insulation 7. Apply over entire surface one (1) ply of Koppers coated base sheet, lapping each sheet lour (4) inches over preceding sheet and nailing at lap no less than nine (9) inches, and aown center oI each sheet on nine (9) inch centers. 2. Extend plies up vertical surfaces and cut off at height of insulation. For vapor barrier provisions contact your Koppers Representative. Application of Insulation Over Membrane (or Dycon Concrete Deck) Substrates: Structural Conerete/steel Centering Apply a uniform coating of Coal Tar Bitumen over the entire surface into which, while hot. embed the insulation. If there are two (2) layers of insulation mop the entire surface of the first layer with Coal Tar Bitumen into which, while hot. embed the second layer of insulation. Formboard Bulb Tees Apply a uniform coating of Typo III Steep Asphalt over the entire surface into which, while hot, embed the insulation. It there are two (2) layers of insulation mop the entire surface of the first' layer with Type III Steep Asphalt into which, while hot. embed the second layer of insulation. When a membrane is installed under the insulation. Type III Steep Asphalt may be used in lieu of nailing over a Formboard Bulb Tee Substrate. Application of Roofing Materials Over Rigid Board Insulation 1st Mop insulation completely with Coal Tar Bitumen. 2nd. Spec. No. 50wf-e0wt--70wl Apply over the entire surface, tour (4) plies of Koppers Tarred Felt, lapping plies twenty-seven and one-halt (2714) inches. Mop solidly between each 2714 inch lap with Coal Tar Bitumen so that in no place shall fait touch felt. 2nd. Spec. No. 51wi--Slwi--71wi Apply over the entire surface three (3) plies of Koppers Tarred Felt, lapping plies twenty-tour and two-thirds (2415) inches. Mop solidly between each 2414 inch lap with Coal Tar Bitumen so that in no place shall fait touch felt. Where slope of deck is one-half C/2) inch per foot or more and deck permits nailing, nail along back or upper edge of each sheet on twenty-four (24) inch cen ters. Where deck does not permit nailing, nailing strips are required and each sheet nailed along back or upper edge at spacings to assure penetration of nailers. 15 KOPPERS 7.1/Ko Architectural and Construction Materials 17 Koppers Multipurpose Membrane (KMM,U) KMM membrane is a versatile, prefab ricated sheet of cold-applied roofing and waterproofing membrane, ft is de signed for application in new and maintenance roofing, foundations, plazas and various other areas of construction where effective water proofing is required. KMM membrane is supplied in two grades: Standard KMM Standard KMM membrane is a fivelayer laminate composed of a thick, flexible plastic core protected on each surface by a layer of modified bitumen and an outer film of polyethylene. 18 Aluminum KMM Aluminum KMM membrane is a fivelayer laminate composed of a thick, flexible plastic core which is pro tected on each side with a layer of modified bitumen. The top surface of Aluminum KMM is a heavy, embossed aluminum foil, and the bottom surface is a film of polyethylene. Both versions of KMM membrane are supplied in the form of compact, ready-to-apply rolls. Use Both KMM membranes are designed for use in various roofing and water proofing applications. Standard KMM membrane is normally used in roofing systems which incor porate an aggregate surface of where protection from the atmospheric ele ments is afforded to the KMM surface by other means. Standard KMM is ap propriate for use in vertically as well as horizontally applied waterproofing systems where surface protection is specified. Aluminum KMM membrane is ideally used in roofing systems in which the roof slope is too steep to permit aggre gate surfacing. Aluminum KMM is also employed in flashing systems.. KMM membrane has goodjsl'ongation properties to withstand nWRal struc tural movement when recommended architectural practicee are followed. It is suitable for application over most decks and commonly used insulating materials which provide continuous support for the KMM membrane. KMM is a prefafcgjcated membrane which is simple toTnstall. It results in a completely waterproof system im pervious to air. water vapor and gases. Since KMM membrane is factorymade, it provides a factory-assured quality membrane of uniform thick ness and material composition. The function of the bitumen covering is to protect the central plastic core from damage during installation, to provide the basis for the heat fusion between the sheets and to add to the water resistance of the laminate. The adhesion to~the bitumen to the central core is positive and allows enough flexibility for the complex to give a floating, membrane effect in service. In addition, KMM membrane has ggod elongation properties so there isvirtually no possibility of dam age from normal structural movement or minor substrate cracking. The Koppers method can allow con tractors to install roofing 'on new buildings at a much earlier stage than with conventional processes, and therefore proceed with other stages of construction. KOPPERS 7.1/Ko Architectural and Construction Materials Application STANDARD KMM Standard KMM is applied without ad hesive in a quick and simple manner. The KMM is unrolled directly onto the roof deck or insulation with 4" end and side laps. The laps provide a joint which is subsequently sealed by heat ing with a standard propane torch. When complete, the KMM-sealed roof is covered with a protective topping. Top Surfacing Several topping systems are recom mended for use with Standard KMMPlease contact your Koppers repre sentative for details. Stonemat Topping a. Fiber Glass Batting: Minimum 1' thick unfaced batting. Roll or sheet form is acceptable.* b. Aggregate: Either gravel, crushed aggregate or stone, graded to %" nominal size (S.P. No. 57--U.S. De partment of Commerce Simplified Practice Recommendation R-163). The quantity to be used is 1200 lbs. per square (approximately 1 Vt" thick ness of loose stone). 'NOTE 1: If smooth gravel having no sharp edges is available, the fiber glass batting can be eliminated. Ag gregate application by gravel buggy is recommended. NOTE 2: Slag is not a permissible aggregate for the Stonemat Specifi cation. Bituminous Aggregate topping (BAT) BAT consists of a combination of graded gravel and asphalt emul sion. The recommended quantity is 650 to 700 lbs. per square (approxi mately %" to 1" thickness). ALUMINUM KMM Aluminum KMM is solidly adhered using a cold adhesive, and does not require a separate topping. It also may be applied to vertical walls and para pets. KMM Adhesive Package Size: 5 gal. containers. Weight: Approx. 55 lbs. (includes con tainer weight) Coverage: a. Roofing and Flashing Applications: 1 to 1 Vi gal. per square. b. Vertical and Plaza Deck Water proofing: 2 to 3 gal. per square. Color Coatings for KMM Aluminum Field applied coatings for KMM Alumi num are available in 14 colors. For color selection, consult Koppers Mas ter Color Selection Chart 560-L under Koppers Acrylic Emulsions, Numbers 600 and 610. Recommended Slopes for KMM Root Systems Koppers recommends that the maxi mum roof slope for loose stone top ping systems be one inch per foot and that the maximum slope for the emul sion aggregate system be one and one-half inch per foot. There is no maximum slope for the KMM Alumi num roofing system. Easy Modification and Repair KMM membrane readily accommo dates in-progress design changes such as the addition of unplanned rooftop projections, as well as any later additions or modifications to the building. In the event that KMM mem brane sustains physical damage, it is a simple procedure to repair, requir ing only a torch and appropriately sized pieces of KMM membrane. Guarantee A 5 year renewable guarantee is available for KMM membrane roofing installations. Consult your Koppers representative for details. Note: For additional information and complete details see the KMM specification manual (Sweets Catalog File No. 7.1/Kop KMM Membrane Roll Size Standard KMM 43* x33 L.F. 118 sq.ft. 107 sq. ft. coverage Aluminum KMM 43" x 33 L.F. 118 sq.ft. 107 sq. ft. coverage Thickness (nominal) 160 mils 120 mils Weight (nominal) 120 Ibs./roil (includes packaging & core) 95 Ibs./roil (includes packaging & core) Built-up Flashing Specifications General Flashings are the terminal closures of a roofing system which perform a waterproofing, and in some systems, a decorative function. Flashings must be installed at all intersections formed by vertical surfaces. Their im portance cannot be stressed too strongly. Water entering the roofing system through flashings can result in water vapor forces which will de stroy the effectiveness of the roofing. Koppers flashings are an integral part of a Koppers roof. Designed for flexibility so that slight movements do not dislodge them and fastened securely to the wall, they give many years of service. It is particularly important that the top edge of the flashing be protected by counter flashing, which will insure a diversion of the water away from any opening which might develop be tween flashing and wall.' In any case where the design or anchoring system of metal counter flashing is difficult, the top of the flashing system should be double stripped with Koppers Glasfab 4" wide set in Koppers tar base cement for Specification 110 or Koppers flashing cement in Specifi cation 108. Metal work is only useful for dec orative, water shedding, or protection against mechanical damage, and is not a waterproofing part of the flash ing system. Because of the high co efficient of expansion of sheet metals and the large temperature changes experienced on a roof, sheet metal or exposed metal components must be isolated from the waterproofing com ponents of the roofing and flashing system as efficiently as possible to prevent the metal from splitting the membrane. Flashing should be Installed as roofing progresses to prevent water damage to insulation or deck under the roofing. If this is not possible water cut-offs must be installed and later removed when flashing is in stalled. Metal counter flashing or a top seal of Glasfab and flashing ce ment must be installed as flashing progresses. The basic Koppers flashings re quire a metal cap flashing to be in serted in the raggle immediately upon completion of base flashing. The cap flashing is to extend into the raggle not less than two (2) inches and is to have not less than a four (4) inch exposed apron extending down over the base flashing. Completely fill rag gle with Koppers flashing cement. NOTE: 1. if bonded flashing is required, it must be installed in conjunction with a Koppers bonded roof and can be bonded for standard periods up to but not greater than the period for which the roofing is bonded. To be bonded, flashings must be set at least 7Vt~ above the roofing base. 2. Metal Cap flashings are not bondable and are not included under any flashing bond. 3. Metal work of any description used as flashing or a part of a flashing sys tem is not bondabie and is not in cluded under any flashing bond. *Note: Termination of flashing may be accomplished without metal counter flashing. Consult specification =710 on this page for specific details. Specification No. 710 (KMM Aluminum) This specification is applicable for use with any KMM membrane or builtup membrane roofing system where its terminal closure intersects a verti cal surface, such as a parapet wall. METAL CAP"' PRIMER ADHESIVE KMM ALUMINUM MEMBRANE Koppers Flashing Specification 710 consists of an aluminum clad KMM membrane applied to waterproof the terminal closure of the roofing system. The Aluminum KMM forms a water proof flashing system by total adhe sion to its substrate and through the use of joint heat fusion, a unique process whereby all contiguous joints are .affixed together to develop a monolithic waterproof flashing system. Application This specification system shall use Aluminum Grade KMM as the main flashing membrane. Each course of Aluminum KMM shall be unrolled and cut to appropri ate size prior to setting in place. Apply a coat of KMM Adhesive at a rate of 1 to 1 Vt gal. per square to the completed roofing membrane and parapet wall. While the adhesive is still tacky, set a layer of Aluminum KMM into place extending above the top of the roofing membrane a minimum of 7Vi" and out ontq the completed roofing membrane a minimum of 4 to 6". Ad jacent pieces shall be side lapped a minimum of 4". Rub or brush thoroughly to obtain proper adhesion and to remove all entrapped air out from under the flashing membrane. Heat-fuse all terminations, as well as side and end laps. The contractor shall thoroughly in spect completed flashing system at the end of each day's work. A high quality varnish-base alumi num paint may be applied to any ex posed streaks or seams of bitumen. **Note: Terminations of flashing spe cification =710 may be accomplished without a sheet metal counter flash ing. For additional details see Kop pers KMM specification manual or your Koppers representative. 20 r /"V KOPPERS 7.1/Ko Architectural and Construction Materials Specification No. 108 (reinforced asbestos) Application Detail ~ UetM Counter f / Oaewera* -(itr ? *ooin* \^ s ' --C<MenSt fvti*Qtoom >'iu>eu**o** sooottSteoaAMweanSieeaaaute t>out 'ipa mtu Specification No. 108 Recommended where sunlight flush with the surface with appropriate nail is the predominant exposure. Should be used tor all high flashing. through flat tin discs. End laps for the two (2) plies shall be not METAL CAP ASBESTOS BASE (1-1) COATED SURFACE less than three (3) inches and staggered not less than twenty-four (24) inches. End laps of reinforced base snail be nailed vertically a minimum of once into tne wall Application at upper edge and once into the cant at a Extend plies of roofing felts and bitumen moppings up all walls, parapets end curbe for a distanca of two (2) inches above cant strip. A raggle not less than Sevan and onehalf (7Vi) inches or more then twelve (12) inches above the roof deck is to be pro vided except where capped nailers are used.. Prime all masonry walls from top of roof ing felts to raggle with Koppers Asphalt Primer. Allow to dry thoroughly. In a uniform coating of Koppers Flashing Cement.* install one (1) piy of Koppers No. 15 Asphalt saturated asbestos felt extending from the raggle to not less than four (4) inches from the base of the cant onto the roof. On top of this apply a second point not lower than the mid point of the cant. End lap* of reinforced base after nailing shall be covered with a strip of Koppers asbestos felt not less than four (4) inches wide set in a coating of Koppers Flashing Cement. Coat entire surface of flashing with Koppers Flashing Cement or Koppers Asphalt Roof Coating No. 454 (including nail caps along top edge of flashing as well as top edge* of felts to seal at wall.) Interply and top coatings shall be trow eled uniformly, full height and continuously approximately one-eighth ('/) inch thick. Piles must be laid in smoothly with no pockets, wrinkles or buckles. Install m9tal cap flasning. uniform coat of Koppers Flashing Cement into which embed one (1) ply of Koppers `NOTE: Hot applied steep asphalt may be reinforced asbestos base flashing (rein used as an alternate to the two (2) Interply forced fabric side down . Nail with one troweling* of asphaltic plastic cement. One and one-half (Hi) inch masonry roofing (1) ply of No. 15 asphalt felt may be used nails through fiat tin discs along upper in lieu of the one ply underlayment sheet edge eight (8) inches o.c. maximum into of No. 15 asphalt asbestos felt when mortar joints. For concrete construction, required. All other requirements of this nail to treated wood nailing strips set in specification must be adhered to. i i I j | | ; j j j j I Specification No. 110 (For water cooled roofs only) Application Detail f Mat* Couthrr Specification No. 110 Recommended for water and the raggle: the first extending out onto the corrosive atmosphere exposure. deck not less than four inches from the Low capped and sealed flashings. bottom of the cant strip, and the second, METAL CAP COMPOSITION BASE (2 -r 2) COATED SURFACE one inch beyond the first. Over this apply two layers of tar saturated asbestos felt similarly imbedded in Koppers Tar Base .Roof Cement, each ply extending onto the Application deck one inch beyond the preceding ply. the preceding ply. Cant strips shall be installed at the angle Nail with one and one-half (V^) inch between the roof deck and the parapet wall barbed roofing nails through flat tin discs or any other similar perpendicular surfaces. at upper edge approximately ten (10) Extend plies of roofing felts and bitumen inches o.c. (For brick or block construc moppings up all walls tor a distance of two tion. nail into vertical mortar joints. For (2) inches above cant strip. concrete construction, nail to treated wood A raggle of not less than ten (10) inches nailing strips set in flush with the surface.) above the roof deck is to be provided for Felts are not to exceed ten feet three water cooled roofs and water retain roofs. inches (10'3") in length. Ends of connecting Pnme all masonry walls from top of roof strips are to overlap three (3) inches and ing felts to raggle with Koppers Concrete are to break at least twenty-four (24) Priming and Refractory Oil (coal tar base). inches with laps of underlying strip. Allow to dry thoroughly. All piias of felt shall be firmly pressed Set two plies of Koppers Tarred Felt in into the trowelings- of Koppers Tar Base troweimgs of Koppers tar basa roof cemant. Roof Cement so thst there will be no Have plies extending from the bottom of wnnkles in the finished surface. j 21 Flashing Details GENERAL INFORMATION There are numerous flashing details that have been proven by experience over the years. There are normally a number of acceptable construction details for accomplishing one purpose. The archi tect should select a detail that best serves the purpose under the various and different condi tions concerned with the specHie Job at hand. In certain cases, slight modifications are necessary to adjust a proven detail to job conditions or one method may serve better than another. The details shown in this manual are some sug gestions based on experience. Space limitations prohibit listing many others. Design or selection is a responsibility of the architect Koppers representatives are available to review flashing details to assist the architect in providing the best details for specific jobs. 7.1 Raised Edge N*ISSCK*0 I" from edge of metW strip end 3" aoert through neeprent wiftft. 4` 6* Wood Cam Mamteane ftaahng Material left Ory * verne* face and Nailed 6" O.C. at Bottom 7.4 Parapet/Precast or Poured Concrete Wait Shat) be P'toered to Eliminate Water Penetration Through Concrete to Underside of Footing 7*5 Parapat/Matal Curtain WaM CurtMn yOecoratneWauCao 2Bhaa at Membrane Sot *i ~ WBBpTi Fi*hvweECdgeement / 3 7.2 Relief Joint Treadso woes ft 7.3 Equipment Support 2 Plies o( Membrane in iu Screw Flashing Cement Turned Down / * Ovar Edge ^ j ^ Neoprene Pad FlatKIna Spec. 10S #710 or *110 -Sheet Mate) 7.6 Parapet/Wall Cap Mates Counttfftasntnf (When Required) bland Qoen--rd 4* Set m Ftaanmg Cement 2 Plies of Membrane Set m ftoooart fiasmng Came* Ti^nea Oown over Edges i ---------------- Cant 4" * * Treated Wood Nailers 22 Cementitious W*m 3 Flashing Details (continued) 7.7 Tapered Cant HOPPERS 7.1/Ko Archrtactunrtand Construction Matenat* 7.8 Taparad Cant Flvf *dth A* minimum MentG/*5M04 SFlsatmmiKngaeOeewn l NMsoaesd msw Mop and 3' apart m treated oaa *.<* no. fm tMMna over Ftenge *n Coei T#r Sdurmn dr Tar teas Camsnt Tapered Cam .Mas. mewt* 2" par *oot -Roofing Msmorana 1 Not mu mm 1 iV-- 4---*( o>c* M .Nom) 1 Treated *ooa Ned* pin totuMMA 7.9 Hanging Guttar Keopars (tooting AporapnateNart* and length For Maximum Ancnpregi Fienge<Mdtn4* minimum Metat Gravel Smo Sat<n Koooan Fteamng Cament Matat Prtcn Oam; Satm Koooart Fiaeiung Camam Nentspeeed 1 tromeogeot mee ttnp and 3" aoan * treated ooe over Flange m Coat T*f grtumenor T#f Bate Camam Taoarad Cant . Max .name 2-oar foot Roc^mf Msmcrans TraatadWcodNauer 7.10 Vantad Edga Flange Set n Kopoars Fiaamng Camam Fed Emaiooa' .Graast Slop neuedl-trommnereageof Flange and J^OC. Flange vndtti A* mwimgn t Footing f~ 7o Am of Fett raatfxrej Orar Flange m Coal Tar tduman or Tar leaa Cement Taoarad Cant Maumum .ncim*_2" oar root insulation vsoor Berner Treated Wood Natter 'T vent nom Openings 18- to 24- 0 C. 7.11 Lead Sieavewrtri Flange Mt m Koopart Flaafung Cement Vent Pipee, Stacks, Flagpoles, and Other Projections 7.12 Te Fait Strips Set n Srtumen over Lead Flange Koppars Roofing Macel Send aoded On Metal Hood Lead Sleeve with Flange set m Koppers Flashing Cement Metal Bitumen Oem Set m Koppers Flearung Cement Matai Muwwn 0n Sat m Koppars Raahtn* Cament All vent pipe*, stacks, flagpoles, or other projections penetrat ing the built-up rooting, whether Indicated on drawings or not, must have a proper metal sleeve flashing with flange, pan flash ing with flange or other flanged flashing installed. Behind metal sleeves and beneath the rooting membrane next to deck install a metal bitumea dam as shown in detail. The sheet metal flange mutt be cemented to the surface of the felt with a mopping of hot Coal Tar Bitumen. Over flange apply, with alternate moppings, two (2) reinforcing pliee of felt so that the first extends not less than three (3) inches beyond the outer edge of the flange and the second not lea* than six (6) inch**. 23 Flashing Details (continued) Future Columns, Sign Supports and Anglo Irons 7.13 7.14 Cant Treated Wood Nailer Surrounding Column Stub Column Attacned to Structural framing At all locations where stub or future columns, sign supports and angle irons are to penatrats built-up roofing, Koppars recom mends wooden curbed base units with cant strips to bs installed to accept standard built-up composition-flashing system. Where structural steel section extends beyond "stub" height, metal cap flashings with tight fit to tha structural saction must be fabricated and continuously weldad to tha projection to assure a watartight matai cap. For pitch pocket daslgn consult your local Koppers salsa representative. 7.15 Curbed Expansion Joint 7.16 Roof Drain Curb expansion joints are to be flashed in accordance with Koppers specifications for parapet walla and must provida nailing to hold metal cap and flashing membrane in piece. Metal cap must be designed to expand so as not to disturb flashing. it is tha responsibility of the designer of the building to provide for adequate expansion joints. For the protection of the roofing system against splits caused by expansion and contraction, Koppers recommends that an expansion joint be installed: (1) on large roof areas at least every 200 feet in each direction, (2) at all places where the structural supports and roof assembly change direction, (3) where type of adjoining dack materials change. Where control, expansion, or contractlon^jointa are provided in structural steel, deck material, or deck''ayatam, provisions must be made tor continuation through the roofing system. See (Expansion Joints) Page 6. Ail roof drains shaft be provided with metal roof drain flashing flanges which extend at least 12" beyond drain opening and shall be stripped with fait in accordance with drain detail. All drains should be provided with expansion Joint s(eaves. The sheet metal flange furnished with the drain must be ce mented to the surface of the felt with hot Coal Tar Bitumen or flashing cement Over the flange apply, with- alternate moppings or trowelings, two (2) reinforcing plies of felt so that tha first ex tends not leas than three (3) inches beyond the outer edge of the flange, and thejMCond not less than tix8) inches. Root drainainust be of a type provided with a wide lead or copper flange. Strainer conatruction should provide adjustment for meeting variations in roof level or slope. To obtain proper drainage, roof drains should be located at points of lowest expected deflection in roof deck. Special care muat be taken to prevent bitumen migration into drain openings. 24 ) s~s Hashing Details (continued) 7.17 Roof Vent KOPPERS 7.1/Ko Architectural and Construction MManM 7.18 Pitch Pocket Loom Insulation f M ~,,Tr 9~~r^H.' A*"I i?S"rv KopperS Poos not recommend occasions! or spot vonts through tha root as tho only vanting method or a substltuta for undarsida or continuous vontad systems. There may be certain instances where spot or mushroom-type vents might be deemed advisable by the designer for a new building (eg. at expansion joints tor vent relief on long run underside continuous venting systems, etc. Although controversisl. the "Pitch Pocket" is one of the most frequently used design, details. The sheet metal flange must be cemented to the surface of the felt with hot coal-tar-bitumen or flashing cement. Over the flange apply, with alternate moppings. two (2) reinforcing plies of tarred felt so that tho first extends not less than three (3) inches beyond the outer edge of the flange and the second no less than six (6) Inches. Fill metal pan with hot coal-tar-bitumen or flashing cement. Paint exposed sections of all reinforcing rods with dampproofing paint. 7.19 Walkway* (Traatad Wood Walkway) l>**td Wooaan Traatad P**wfc Ww>--y floeftAf Mamdran#P>us Siaaear* P*teh . 2 Pty StnooH* . c 7.20 Traffic Pad CaramscGranuta A(gr*gata 7.21 Roof Opening Curbs extending a nominal 8 inches to 12 inches above roof surface shall be provided at all openings for skylights, ventilators, expansion joints, etc., to pro vide for installation of adequate base flashing. Skylight - Condensate Gutter < Ventilator Flashing Nailed 10"0.C. Flashing Specs. #108 #710 or tllO Koppers Roofing no Deck Wood Cant 4" x 4' Treated Wood Nailers 25 * Koppers Roof Bond/Guarantees Program Bonds and Guarantees are available for listed specifications in this man* ual. To qualify for a Koppers Roofing Bond or Guarantee, roofing and flashing must be constructed in ac* cordance with Koppers Specifica tions, with Koppers materials, and by a roofing contractor approved by Koppers. ROOF BOND PROGRAM I. Description Koppers bonds are available for 10, 15 or 20 year terms, and only cover built-in roofing and flashings where approved. Koppers will issue a standard roof bond for Coal Tar Bitumen flat or low slope roofing and will include such Koppers steep asphalt roofing as re quired in conjunction with the fiat or low slope roofing, provided, the steep roofing does not exceed 25% of the total roofing to be bonded. All roofing to be' bonded must be constructed in conformance with Koppers specifi cations. Koppers bonds are not available for residential roofing. Koppers bonds are transferrable upon timely written notice of change of property ownership.* 'NOTE: Koppers roof bonds provide for repairs of leaks to the roofing not occasioned by defects in the building, abuse or extreme weather conditions during the term of the bond up to the monetary limit specified in the bond. II. Coverage A. Roof bonds provide for the fol lowing general benefits: 1. Use of quality materials. 2. Use of time proven specifica tions. 3. Roof application by a roofer knowledgeable in the application techniques of Koppers products. 4. Discussion of specifications during the planning stages and during construction. 5. Assistance to the owner as nec essary for items such as leaks to the roofing not occasioned by building defects or additional roof projections, etc. which relate to the performance of the roofing. 6. Flashing membranes covered on request only. B. Roof Bonds DO NOT cover the repair, installation, or replacement cost of the following: 1. Decking Materials 2. Vapor barriers 3. Insulation Products 4. MetalWork 5. Products in the roof assembly furnished by others. 6. Damage to the bonded roofing or flashing caused by the use of the products listed in 1 through 5 above, their installation or attachment. 7. Vandalism or owner abuse. 8. All other items presented in the sample bond presented above: C. Koppers bonds are available within the Continental United States in all cases except those areas where Koppers does not presently provide inspection service. D. Built-up flashing may be bonded for terms up to but not exceeding the term for which the roof is bonded. E Charges for the roofing bonds are made on a per square (100 sq. ft.) basis of the roofing membrane. F. Koppers reserves the right to cancel the bond if the roof is damaged due to causes not covered by the bond if It is determined its satisfactory per formance tor the remaining term of the bond is impaired. Cancellation due to damage of this type does not provide for any refund of the original charge. KOPPERS 7.1/Ko Architectural and Construction Material* Contact a Koppers Sales Office Near You 'Bessemer. Alabama 35020 (Birmingham) P O. Box 752 205-744-9110 'Commerce. California 90040 (Los Angeles) 5900 S. Eastern Avenue Suite 104 213-726-8666 Burlingame. California 94010 (San Francisco) 1801 Murchison Drive 415-692-3330 'Elmhurst. Illinois 60126 (Chicago) 188 Industrial Drive 312- 833-3380 Southfield. Michigan 48075 (Detroit) 24800 Northwestern Highway 313- 352-3920 St. Paul. Minnesota 55104 1000 N. Hamline Avenue 612-646-7801 Kansas City. Missouri 64111 Room 5 V.F W. Building 816-531-6680 St. Louis. Missouri 63101 706 Chestnut Street 314- 241-8096 'West Orange. New Jersey 07052 Paragon Building 10 Rooney Circle 201-736-9150 Charlotte. North Carolina 28203 1409 East Boulevard P O Box 3186 704-375-4427 Wickliffe. Ohio 44092 30060 Lakeland Blvd. , 216-944-3800 Tulsa. Oklahoma 74103 310 Thompson Building 918-583-2233 Portland. Oregon 97229 7540 N W. St. Helens Rd. 503-286-3681 'Pittsburgh. Pennsylvania 15219 1028 Koppers Bldg. 412-391-3300 Houston. Texas 77015 Old Industrial Rd. P O Box 9746 713-453-5446 'District Offices KOPPERS Architectural and Construction Materials OMJ796 f