Document zdOeMY20znNg88g3yxmkkLX6z

. UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION III 1650 Arch Street Philadelphia, Pennsylvania 19103-2029 Report Title: Inspection Date: Regulatory Program: Clean Air Act Asbestos NESHAP Inspection - Howard Johnson June 28, 2023 Clean Air Act Company Name: Facility Name: Facility Location: Latitude: County/Parish: Howard Johnson Howard Johnson 1779 N. 9th St. Bartonsville, PA, 18360 40.998490 Longitude: Monroe -75.267180 NAICS Code: 331491 SIC: 3356 *** On-Site Representatives: Floyd Lane, Supervisor, Northeast Site Contractors Phone: Email: jimertle@ertlecars.com Point of Contact X *** EPA Inspector (s): Rich Ponak - Compliance & Enforcement Official / Inspector, EPA Region III Phone: 215-514-7151 Email: Ponak.Rich@epa.gov State Inspector: NA *** EPA Lead Inspector Signature/Date Rich Ponak Enforcement & Compliance Assurance Division (3ED23) 8/24/23 Date Supervisor Signature/Date Aquanetta Dickens Enforcement & Compliance Assurance Division (3ED23) 8/24/2023 Date I. Introduction On June 28, 2023, a Clean Air Act (CAA) Asbestos NESHAP Inspection was conducted at the former Howard Johnson's Motel and Conference Center, located at 1779 N. 19th ST., Bartonsville, Pennsylvania. a. Summary of Site / Facility Howard Johnson's Motel and Conference Center is located in Monroe County, Pennsylvania. Howard Johnson's is a former Motel and Conference Center. The site is being partially demolished and developed as a commercial property. b. Entry and opening conference. EPA, Region III Inspector Richard Ponak arrived at the facility at approximately 9:00AM on June 28, 2023, for an unannounced inspection. Upon arrival, Inspector Ponak presented his credentials to Floyd Lane, Supervisor for Northeast Site Contractors (North East), the Demolition Contractor for the project. Inspector Ponak explained to Mr. Lane that it was a CAA Asbestos NESHAP inspection. Mr. Lane informed Inspector Ponak that the asbestos contractor was no longer on site. Mr. Lane stated that North East arrived on site approximately two weeks ago. Mr. Lane stated that the asbestos contractor was no longer on site, and he thought the asbestos removal was completed. II. Site / Facility Walkthrough Inspector Ponak walked through the work area. The work area included guest rooms, common areas, and the boiler room. Inspector Ponak inspected the work area. Inspector Ponak did not observe and Regulated Asbestos Containing Material (RACM) anywhere on the property. Inspector Ponak did not observe any RACM debris in any of the work areas. III. Records Review No records to review. IV. Closing Conference At the conclusion of the inspection, Inspector Ponak met with Mr. Lane. Inspector Ponak informed Mr. Lane that he did not observe any RACM debris in the work areas, and that it appears the asbestos project was complete. Inspector Ponak asked Mr. Lane if there were any questions, Mr. Lane said no. Inspector Ponak left the site. V. Additional Correspondence-NA VI. List of Attachments- NA