I'm sure I'll have some more questions later on, but for now am just trying to get YG up to speed on how the process will work.
Thanks for your help.
Andrew
Andrew G. Smith
Senior Planner Executive Council Office | Major Projects Yukon T 867-456-3857 | Yukon.ca
"Ellis-Wouters, Lesli" <lellis@blm.gov>
From: Sent: To: Subject: Attachments:
"Ellis-Wouters, Lesli" <lellis@blm.gov> Wed Apr 04 2018 12:26:23 GMT-0600 (MDT) "Hayes, Miriam (Nicole)" <mnhayes@blm.gov> Re: [EXTERNAL] EIS Process for 1002 image003.png
Have you started an interested parties list? You can answer and let him know we can add him to that list as well to check our website for updates. It would be okay to explain the basic NEPA process.
Lesli J. Ellis-Wouters
Communications Director Alaska State Office Bureau of Land Management 907-271-4418 | cell - 907-331-8763
On Wed, Apr 4, 2018 at 10:24 AM, Hayes, Miriam (Nicole) <mnhaves@blm.gov> wrote:
Hi Lesli, Would you like me to respond or should you?
Nicole Hayes Project Coordinator Bureau of Land Management 222 W. 7th Avenue #13 Anchorage, Alaska 99513 Desk: (907) 271-4354
--------- Forwarded message----------From: <Andrew.Smith@gov.yk.ca> Date: Wed, Apr 4, 2018 at 10:21 AM Subject: [EXTERNAL] EIS Process for 1002 To: mnhayes@blm.gov
Good morning Nicole.
I got your contact information through Mike Suitor here at Yukon government. We are looking at how we will be able to participate in the EIS scoping and commenting period for the potential lease opportunities in the 1002 area.
Right now, I am just trying to find some resources that describe that process - stages and timelines, matters to be considered in the scoping, etc. Are there any quick reference guides to your process?
I'm sure I'll have some more questions later on, but for now am just trying to get YG up to speed on how the process will work.
Thanks for your help.
Andrew
Andrew G. Smith
Senior Planner Executive Council Office | Major Projects Yukon T 867-456-3857 | Yukon.ca
"Hayes, Miriam (Nicole)" <mnhayes@blm.gov>
From:
Hayes, Miriam (Nicole)" <mnhayes@blm.gov>
Sent: To: Subject: Attachments:
Wed May 09 2018 15:39:19 GMT-0600 (MDT) Andrew.Smith@gov.yk.ca Re: [EXTERNAL] EIS Process for 1002 image003.png
Hi Andrew,
BLM is in the scoping phase which began April 20, 2018. The National Environmental Policy Act guides the EIS process, and you can
obtain more information about meeting times/locations (when announced) at our website which will have the most up to date information.
https://www.blm.gov/programs/planning-and-nepa/plans-in-development/alaska/coastal-plain-eis
Thank you,
Nicole
Nicole Hayes Project Coordinator Bureau of Land Management 222 W. 7th Avenue #13 Anchorage, Alaska 99513 Desk: (907) 271-4354
On Wed, Apr 4, 2018 at 10:21 AM, <Andrew.Smith@gov.vk.ca> wrote:
Good morning Nicole.
I got your contact information through Mike Suitor here at Yukon government. We are looking at how we will be able to participate in the EIS scoping and commenting period for the potential lease opportunities in the 1002 area.
Right now, I am just trying to find some resources that describe that process - stages and timelines, matters to be considered in the scoping, etc. Are there any quick reference guides to your process?
I'm sure I'll have some more questions later on, but for now am just trying to get YG up to speed on how the process will work.
Thanks for your help.
Andrew
Andrew G. Smith
Senior Planner Executive Council Office | Major Projects Yukon T 867-456-3857 | Yukon.ca