Shoring and Sloping of Excavations 400 Series All excavation* are to be shored or sloped if there is ANY danger or a possibility of caving. Figure* (1) and (2) show the type of shoring required on any trench. Figure (l) show* sheet piling added with first depth complete. Figure (2) show* shoring full depth. Figure* (l) and (2) are to be used on all depths exceeding 4'6', except where the Area Engineer*' signify otherwise. Figure (3) and Figure (5) show the types of shoring to be used in all cases less than 4'6'. except where the Area Engineers* signify otherwise. Figure (4) shows the way excavation* are to be sloped when type of work and location permits. Alt sides are to be sloped l to 1 and spoil banks are to be kept at a minimum of 3'0' from edge of excavation. ( In all case* additional precaution* by way of shoring and bracing must be taken when excavations are made in locations subject to vibrations from railroad or highway traffic, the operation of machinery or other source* of vibration and after heavy rain. Figure l--401 Figure 3--403 Figure 2--402 Figure 4--404 Figure 5--405 KEY A--Maximum of 4'0'. B--4' x 4'. C--2'xl2*. D--If possible, spans should not exceed 4'0'. Under no circumstance* are spans to exceed 6'0'. For span* 4 0' to 6 O', 4' x 5" waler* must be used. E--4' x 4' if width of trench is 1*0' to 3 0". E--4* x 6' if width of trench is 3'0' to 6'0'. E--6' x 6' if width of trench it 6'0' to 8'0'. E--Suitable trench jacks may be used in place of timber* in Figure 5. F--2' x 6'. *Amuism run responsibility. DUP 0912399 32