July 3, 1970 Status of Aroclor Pollutio: Control Month of June
Mr. W. B. Papageorge Oeneral Offices '
*^\ 'Vyufecwr?^'
C. Buckley -Corlew
W. Engman P. Hodges-0.0. F. McDonald-Newnort J. Savage-0.0. H. Williams-Anniston B. Young
Current PCB Levels
The estimated Aroclor losses from the production department remain at 65#/day. Sampling by the Pollution Control Group of the waste stream leaving the Sauget village treatment
plant indicates a loss to the river of 45#/day. This is a concentration of about 200 - 250 pph. Sampling of the
river indicates a definite increase in PCB's below the WGK discharge into the river. .For a summary of all analytical data to date, see TSD report 91341:9000, #3, to be issued
by 7/10/70.
During July sampling techniques will be refined, the sampling program revised, and analysis for PCB's begun in the WGK
laboratory. For the comprehensive plans please refer to W. C. Engman's memo to you on 6/25/70.
In the future this monthly Aroclor pollution control report will be prepared by the Technical Services Department.
Losses to Sewer in June
Other than the routine Aroclor production losses estimated above, losses were as follows:
Dept. 275 - Est. 10 gallons; did not go to Bewer. Dept. 242 - Est. 10 gallons. Dept. 251 - Est. 5 gallons.
PCB Project Work
A. Completed
1. Blow Tank Piping Alterations
.
ProJ. No. 1493 - completed on 3/16/70 $5400 expense, -0- capital Prevents major losses from continuous blow tank.
MOMS 09904<:
Mr. W. B. Papageorge Status of Aroclor Pollution Control Month of June
Page 2 7/3/70 WGK
2. Off-Oaa Piping Alterations
ProJ..No. 1948 - completed on 5/14/70 $550 expense, $2100 capital This project allows HC1 sewered In Dept. 246 from the chlorlnators to go through the off gas condenser and demister.
B. In Progress 3. Absorber Rupture Disc Alterations
ProJ. No. 1512 - EDC 7/10 (moved back from 7/1/70) $1500 expense, $4500 capital Will prevent losses from four rupture disc discharge lines.
4. Install Aroclor Settling Basin
ProJ. No. 1795 - EDC 8/1/70 (moved up from 9/1/70) $7000 expense, $7000 capital Will trap Aroclors In production department sewers.
5. Blow Tank Demister
ProJ. No. 2031 - Estimate Issued on 6/10, design work In progress. Installation EDC 10/1/70 This project will remove 250#/day of Aroclor currently being drained from the blow tank HC1 header, and will alBO remove an estimated 50 60#/day currently being sewered at the drowning Jet.