Document ympXq8z1RJYD0X9rK8LL1gvd3
R. A. Conrad To:
Interoffice Communication
From: Dale:
R. D. Hillman, s. V June 5, 1987
Corkran, and G
W. Bacon
Subject: RCRA permitting of the incinerators for HEAVY ENDS" IW
Attached are the results of the study on whether to permit the VCM Plant incinerators as RCRA facilities for the disposal of heavy ends. The permitting process must begin immediately if Vista decides to RCRA permit the incinerators. The application must be submitted by August 1987 in order to meet the November 1988 deadline for permit approval imposed by Congress.
Three options were analyzed in detail:
Continue sending heavy ends to PPG. Send heavy ends to B. F. Goodrich (BFG). RCRA permit the VCM Plant incinerators.
We recommend that the VCM Plant incinerators not be RCRA permitted, and that the heavy ends stream instead be split between BFG and PPG. The recommended option provides:
Favorable economics ($0.5MM NPV relative to the incinerator permitting option).
A long term contractual outlet with BFG and two outlets for heavy ends disposal.
Reduced regulator/requirements and exposure. No engineering manpower drain for permit prepara
tion and incinerator test burns. No unfavorable publicity from public hearings on
the permitting of hazardous waste incinerators.
Please review the attached document and initiate the appropriate actions to arrive at a decision on permit ting. If the decision is made to permit, approximately three engineers and $210,000 will have to be committed to meet the application deadline.
Richard D. Hillman Process Engineer
Sandra V. Corkran Process Engineer
Graham W. Bacon^ V' PED Engineer
cc : PEM-GEH-WPS-MLA-/SCR+PLF-HLH-MGH-ERT-BED
CUH OOOOO9547
HEAVY ENDS DISPOSITION OPTIONS
SUMMARY
A study was made to examine several options for the disposition of
the heavy ends material produced at the VCM Plant. The objective
was to determine whether the VCM Plant incinerators should be per
mitted to burn the heavy ends, which is classified as a hazardous
waste material. This decision is required at this time. Currently
the VCM Plant has interim status for burning hazardous waste in
the incinerators. In order to retain this option, a complete RCRA
Part 2 permit application, along with a test burn plan, should be
submitted by August 8, 1987.
This is the expected latest date
that would allow sufficient time to complete the permitting pro
cess by the November 8, 1988 deadline set by Congress in the RCRA
Amendments of 1984. If this deadline is not met, then Vista would
lose the option of burning heavy ends in the VCM Plant incinera
tors until a complete reapplication could be submitted and ap
proved. An alternate disposition option would have to be used
during this interim period since Vista would have to cease burning
heavy ends once the interim status is lost.
The following options were examined :
Option 1 - Continue to send the heavy ends to PPG without a signed contract, possibly negotiating for a lower cost and a signed contract in the future.
Option 2 - Obtain a contract with B. F. Goodrich to have them pro cess the heavy ends material in their La Porte CATOXID Unit They recover the chlorine as HCl which is fed to their Oxychlorination Unit to produce EDC.
Option 3 - Obtain a contractual agreement with B. F. Goodrich and approval from PPG which would allow Vista to send approximately the same amount of heavy ends to both plants. This would provide two disposition options thereby making Vista less dependent upon one industry for the disposition of heavy ends. This should allow for price negotiations with PPG and would result in cost.savings for Vista.
Option 4 - Permit the VCM Plant incinerators to burn heavy ends and perform the required revisions to allow for this operation on a long term basis.
CUH 0000091548 1
Option 5 - Permit and construct a new hazardous waste incinerator to burn heavy ends at the VCM Plant.
Option 6 - Commercial incineration of all heavy ends by participa tion in a take-or-pay arrangement with a company such as Chemical Waste Management or Gulf Coast Waste Disposal Authority.
Option 7
- Negotiate an arrangement with Georgia Gulf in develop ing a process similar to the CATOXID Process of B. F. Goodrich, possibly building such a process unit at or near the VCM Plant.
The results of this study indicate that the best option would be
Option 3: Continue to send heavy ends material to PPG while nego
tiating a contract with B. F. Goodrich and then to split the
shipments of heavy ends material between the two companies.
This
would provide two disposition options and would allow for future
price negotiations. It should also provide for an annual savings
of about $30M relative to the current cost of sending all of the
material to PPG. This option would also provide a minimum of two
to three years in which other options, such as the Georgia Gulf
process, could be examined or developed.
It is recommended that this option be continued until it is demon strated that the processing of heavy ends in the CATOXID process is successful and can be continued at a reasonable cost. Then it would probably be advisable to gradually eliminate the amount of material sent to PPG. This would be especially true if the Geor gia Gulf process should prove to be a possible alternative or bar gaining tool to minimize the BFG charges.
There is also a choice to be made concerning the mode of transpor tation utilized for transporting the heavy ends to the BFG Plant in La Porte. The Net Present Value (NPV), for both rail transpor tation and trucking by Vista Transportation, relative to the cur rent PPG option, is about $90M. No capital revisions would proba bly be required for the trucking option while the revisions re quired at the VCM Plant to allow for railcar loading of heavy ends, including loading rack revisions (minor) and the required secondary containment would cost about $50M. However, much less risk of a serious exposure incident would be incurred by rail shipments than by the use of trucks. This factor should be more than sufficient to warrant the use of rail transportation for this material.
2 CUIH 00000954?