MONSANTO COMPANY Location : Texas City, Texas
Date
t July 29, 1964
Subject : Monthly Production Sunwary VCM Plant - July 1964
TO : W. R. Nisbet
cc: J. M. Chamberlin L. B. Bullock C. H. Duhon W. P. Gabel B. H, Hartsog J. W. Kongable
J. G. McQuarrie/^ T. E. Shirley
J. L, Price G. T. Ryan VCM Supervisors
SUMMARY
VCM production was 10.6 MS lbs. (92.1# of rated capacity). Reaction was down 88 hours with 54 hours because of acetylene availability. Rates were generally limited by C*H availability. Cracking was limited during the seoond half of the month by re frigeration problems and by VCM Redistillation Column {22D14) fouling.
The 350 ton Carrier unit had a bearing failure - inspection of the machine showed major damage to the internals of the compressor, requiring extensive repairs. This limited total VCM production to approximately 60# of rated capacity for the last 5 days of the month.
The VCM Redistillation Column fouled and was boiled out with EDC three times during the month.
EDC production was 13*7 MM lbs. (109.5# of rated capacity). Downtime totalled 28 hours.
Oxidative Chlorination production was 1.4 MM lbs. of EDC (48.5# of rated capacity. Downtime totalled 240 hours, 94 hours because of refrigeration failure, 72 hours for catalyst addition, 74 hours for maintenance (tube ferrule pulling, leaks, etc.).
CBY 1107259
RSV0032154
Monthly Production Smrauary VCM Plant - July 1964
Page 2
Operating Details
A. Summary Table Production
This Scheduled Month
Yr-to-Date
Standard
VCM, MM lbs.
EDC, MM lbs. - Dept. 23 - O.C.
10.52
13.27 2.25
10,6
75.2 88.8 11.1
11.5 12.5
2.89
Acid, gallons
Acid dumped, gallons HPT, $
480,000 0
90
Onstream TlmeT
Cracking Reaction Department 23
O.C. Acid Absorber, $ of time needed 21C2
100. 88.1 96.2
67.7^ 86.4
98.9
Yields
This Month
Standard
CaH* to EDC - Dept. 23 - O.C.
Cl# to EDC EDC to VCM C#Hs to VCM
95.0 90.0 95.0
95.5 97.0
95.0 92.0 95.0
95.5 97.0
B* Operations and Maintenance
The No. 2 Cracker was retubed with 3" tubes.
The No. 3 Reactor was retubed.
The 22C3, 350 ton Carrier refrigeration unit compressor failed, requiring major overhaul. This restricted production for the last 5 days of the month to 6o of rated capacity.
CBY 1107260
RSV0032155
Monthly Production Summary VCM Plant - July 1964
Page 3
B, Operations and Maintenance (continued)
The 22C6, 150 ton Carrier refrigeration unit compressor coupling failed during the month requiring major repairs
and limiting production slightly for 6 days.
The EDC Heavy Ends Column, 22D9, Reboiler was switched once during the month.
A major shutdown was taken in Department 26. The 26E3, Flare Gas Condenser, was replaced because of severe corrosion. The
recycle compressor suction line was replaced because of severe corrosibn.
The VCM Redistillation Column fouled 3 times in 6 days and required an EDC boll out each time.
The HC1 Compressor, 21C2, was down for 8 hours because of a
packing leak.
v-
C. Personnel and Safety
Two E.l.F. engineers, Kiam Lehrman and Dov Grolsman were trained in Oxidative Chlorination production know-how.
A major incident - a flash fire on the CsHa compressor, 22CT>occurred. This was the subject for special safety meetings with all personnel in VCM.
Regular monthly safety meetings were held using the Safety Departments`s dunany model as the subject in training in
resuscitation techniques.
CBY 1107261
RSV0032156
>
Monthly Production Summary VCM Plant - July 1964
Page 4
S Costs
1. July Variances
VCM EDC O.C.
Raw Materials
Price Performance
-10,000 -20,000
00 0 -10,000
Direct Conversion
Labor _ Repairs
Catalyst
- 4,000 -10,000
- 4,000
- 700
0 0
- 700
- 5,000 - 5,000
Volume
Off-scheduled Prod. Unscheduled Capacity
Total
+ 917 ' - +1,144
-11,231
+2,048
-58,314
+2,492
- 7,123 - 5.265
-33,088
Variance Explanation
VCM
Raw Materials:
Price
- Excess EDC used due to low C3H3 availability.
Performance - Below standard sales of HC1 to O.C.
Direct Conversion:
Labor
Overtime coverage of O.C.
Repairs
Retubing Hl-3. Repairs to refrigeration units.
CatalyBt
CaHa purification out of service.
CBV 1107262
RSV0032157
Monthly Production Summary VCM Plant - July 1964
Page 5
E Costs (continued)
Variance Explanation (July) - continued
O.C.
Raw Materials
- Below standard conversion due to low catalyst activity.
Repairs
- New 26E3, new recycle compressor suction line.
Catalyst
^ - Plugged tubes causing extra catalyst usage,
2, August Variances
Raw Materials
VCM BDC
O.C.
Price Performance
Direct Conversion
-10,000 -20,000
00 0 -10,000
Labor Repairs Catalyst
Volume
- 4,000
-- 5 >000 - 4,000
- 700 0 0
- 700 0
- 5,000
Unscheduled Capacity Total
- 1.604 -44,604
+2,048 +1,348
- 5.363 -21,063
RSV0032158