Document ykN85bDr4jXnJDK7D70Rmpp56
TO:
ALL SUPERVISION - LIST "A"
FROM: S&F DIVISION
VICTORIA PLANT
!
CENTRAL SAFETY COMMITTEE j
MINUTES OF MEETING HELD JUNE 13!, 1978
Members Present
A. D. Cyphers, Chairman A. H. Peters R. M. Robertson C. R. Steele J. V. Woodrick 0. A. Sampson R. E. Keith M. W. House (for W. J. Faassen) J. D. Jones (for W. T. Dodson) W. P. Ledet D. G. Jentsch B. W. Hardy (for H. W. Shanan) W. G. Todd (for J. S. Bray) M. C. Estep (for H. W. Anderson B. L. Sutphen B. S. Smith D. G. Kilpatrick (for M. A. Ervin) A. C. Vaught (for D. J. Logan) S. V. Hinson - Construction C. E. Bunn J. E. Borden J. M. Kayser W. T. Procter
Members Absent
| G. L. Brennan | W. L. Smith
W. J. Faassen j W. T. Dodson | J. S. Bray j H. W. Shahan
j D. Jv Logan
| H. W.. Anderson I M. A. Ervin | Visitors
Rocky Estrada Bill Busby Steve Nashatker j B. C. Pieritz A. H. Nickolaus
f
f
DUP 0801406
DU 007873
Victoria Plant Central Safety Committee Minutes of Meeting Held June 13, 1978
Page 2
I. Reports
The Monthly Safety and Housekeeping Aiidits and Injury
Summary for May were reviewed.
!
All area labs should be checked by Laboratory Super visors for proper lab safety. Area proprietors should set this up with lab supervision to be done on a set frequency.
Concern was expressed over a breathing air line laying on the floor where DCB contamination was possible.
A Rowan lighting panel in 512 was hot, which indicates the probability of containing water. It is good practice to check the panels after heavy rains.
Ant hills should be sprayed.
A hoist with a broken hook safety latch indicates a need for closer checks on safety equipment.
j
More attention to odors and their control is needed. A smelly area is not within SOC's. I
i
All areas should check ECR's for [proper pressure control, alarms, periodic inspection programs, and action required when low pressure alarm sounds.
A storage cabinet was severely bent out of shape
from excessive weight of contents. I
Congratulations to the Good Housekeeping Award winners.
A high potential injury occurred[when an employee's hand came in contact with a grinding wheel. The injury was classified as a Medical Treatment Case. An obser vation was made that not wearingjgloves is an exception to the glove policy and that if the grinding wheel operation does not require gloves, then the job descrip tion should specify this exception to the glove policy.
|
A high potential DCB burn resulted when an employee spilled what he thought to be condensate on his foot. This was also classified as a Medical Treatment Case.
The Wilmington S&F Audit is scheduled to begin August 21. Previous audit reports should be|reviewed to insure that
all items have been corrected. Repeat items are awkward and should be guarded against. |
DUP 0801407
; DU 007874 I i
Victoria Plant Central Safety Committee Minutes of Meeting Held June 13, 1978
Page 3
II. III.
IV.
Incident Reports
No. 78-24 - The Chairman expressed his concern for mixing organic and HNO3, and the need to pay strict attention to the basic chemistry of the process.
No. 78-27 - The EOD procedure should question potential piping problems when flow rates through piping or equipment are altered significantly.
Safety Activities Committee - B. S. Smith
On Plant
I
i
No lost or restricted workday cases.
Thirty-four safety dollars awarded for recognition
of unsafe acts or conditions.
|
Hugh Charlton and Jim Borden visilted Washington Works
in early May to discuss their plsjnt's safety program. They utilize the "area" concept as we are trying this year. Additional information was communicated to the committee for possible future use.
i
Off Plant
"DIAL 666 FOR EACH DAY'S BINGO NUMBER"
There were no off-the-job injuries in May that resulted in Jlost time. We still have 4 to-date.
Supervision was asked during the 'month to have a one-on-one discussion with employjees in their group
just prior to leaving for vacation. All should be reminded of their responsibility jtoward off-plant
safety, and conducting their activities so they and their families get through the vacation period injury free.
Mugs have finally arrived. Tickets have been sent to group coordinators for distribution.
S&F 23 - W. G. Todd
This procedure will be changed to allow foremen approval of "handling" and "removal of asbestos" permits.
I
DUP 0801408
DU 007875
Victoria Plant Central Safety Committee Minutes of Meeting Held June 13, 1978
Page 4
V. VI. VII. VIII.
IX.
Standard 7H Status
All of "Alathon" is now in compliance
Nylon is making progress and should be in compliance by year-end.
Acids will be in compliance by the end of the third quarter, 1978.
Manila Rope - R. E. Keith
Manila rope is to be restricted to isolated use - it will be used for tie down for hurricanes.
Respirator Program - J. M. Kayser
Jim gave an overview of the respirator program. The COD for the building and the construction site have been approved. The challenge aerosol recommended for the Quantitative Man-fit Test System is di (2 ethyl hexyl) phthalate (DOP). The DOP system is being used at Savannah River and by ESD. Its use has been referred to Haskell Lab for comment. The system can possibly be ready for use within three months.
Chairman Comments
Annual Personnel Safety Training - Do all groups have procedures to insure that all employees receive the.required annual training on stott Air Paks, Chemical Hazards, Fire Extinguishers, and Resusci-Ann? This requirement should be stated in the Safety Manual and we should insure that all new employees receive this training.
Relief Valve Tests
Relief valve test postponements should be a rare and exceptional case. He asked the question "Where would we be if a relief valve failure, causing death, was attributed to not inspecting on schedule?"
Key Safety Data
Overall data indicates trend in proper direction.