Anniston Plant
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Anniston
C. K. Eastman A. J. Koenig J. C. Landwehr L. J. Boesch G. W. Miller W. B. Papageorge W. F. Taffee H. L. Williams
Summary February, 1969
Cost Improvement Results
Month YTD
27,135 46,975
21,960 40,410
123.5 116.2
General Offices
Organic Division
H. C. Carder W. R. Robirds * D. Danna (5) P. B. Hodges D. B. Hosmer (2) W. A. Kuhn C. F. Luecke * N. L. Sample J. E. Smith - R. J. Stratmeyer * H. S'. Trail
Manufacturing cost estimate to be made by March 15, 1969 on low color Solid Aroclor 5460 by sodium treatment of Santowax R. Marketing estimates 1 M lbs/yr. sales at start.
Debottlenecking the Biphenyl stills and upgrading No. 1 Tubular Unit project mechanically complete. Insulation, painting and dismantling phases remain for final completion.
Staley Grade and water-white HCl project continues to receive top priority. Aroclor off-gas catch tank installation being expedited for 3/15 completion, and this will give an immediate increase in recovery. Total project completion still scheduled in June.
PNP reactor cycle time controlling variables are under intense study by TSD process and statistical groups. If current batch size of 8,000$ and cycle time of 151 minutes/batch can be main tained, rate will improve to 1.78 M $/mo.
Construction underway on central chlorine unloading facility. Revised completion date is May 26, 1969.
OTHER LOCATIONS
Agricultural Division
> D. W. Jackson - WCK < T. M. Patrick -
So.2nd St. A. H. Forsten -
Alvin, Texas
Tentative amendment "A" to Niran process to Recover Acetone . was approved 2/17/69.
The Sulfur Recovery - Liquid Residue Recycle Process was re viewed with CED and Ag Division. CED has begun work on a preliminary project scope and evaluation grade estimate. -----------
_________________________ ;___________________________________ j
DSW 551382
M-306 REV. Il/l/l 960
COMPANY CONFIDENTIAL INFORMATION
,
"This document contains confidential information which is the property of Monsanto Company. Only those portions of the document relevant
to a duly authorized individual's need to know may be exerpted for him. The report must not be sent outside the Company without written
annrnval anr! thp rprinipnt ic arrnrintah In f nr Itn c-nfn l/nr^lnn
~ ^L ~~ J; -- i -- :
1 :i--------------------------------1
----------------_i:-----------------i m
STLCOPCB4089799
)
Company Confidential 2.
Deslgft and Drafting Installation of emergency radio communications equipment started with mid-March completion targeted. Solid Aroclor instrumentation (Phase II) drawings forwarded for review.
Process and Quality Analysis The Plant Quality Score was 94.9, up 5,4 from January, with YTD score of 92.0 against a target of 95.0 minimum.
C. Landwehr jw
OSAN S583
STLCOPCB4089800
) ORGANIC DIVISION
1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR- APR MAY JUN JUL AUG SEP OCT NOV DEC
Sol.Aro.
TAR
2250 2250 2250 2250 2250 2250 2250 2250 2250
Li-Still SpG. EST
AFE 3015 Sp.Solid Aro.
ACT TAR 2600 2600 ?6oq 2600 2600 2600 2600 2600 2600 -
-
Lower 5060
est: ACT
1500 5490 1500
Sol.Aro.-Still TAR
Coolout temp. EST:
AFE 3015
ACT
Sol .Aro. -Chlortcr TAR
Batch End
EST:
AFE 3015
ACT
SW/R Composition TAR
160 170 160 170 160 170 160 170 160 390 390 390 390 390 390 390 390 390
2750 2750 2750 2750 2750 2750 2750 2750
est:
AFE 3016
ACT
Solid Aro.
TAR
Montar 5 Flake EST
1080 1080 1080 1080 1080 1080 1080 1080
AFE 2949
ACT
Sol.Aro. Blend 4465
TAR EST ACT
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
1690 1920 1690
Sol.Aro.-Vertical Still Cond. AFE 2324 Sol.Aro.Cl2 T/C Dock AFE 2542
TAR EST' ACT TAR EST ACT
70
70 70
80 70 80 70 90
r~940 940 9-50
Cl2 Pit.Down No TAR
950 940 950 940 950 940 950
Unload
EST'
CED 1831
ACT
Solid Aro.-Flake TAR
3000 3000 5000 5000 5 Q00 5000 5000 5000 5000 5000 5000 5000
& Drum CED 1450 Liq.Aro.
EST.
00
ACT 0
TAR 3000 3000 - - ' - - - - - - - -
48-53 M #/yr. AFE 2545 Liq.Aro."No.2
EST ACT TAR
0 550C 0
3000 3000
Still Entrain Sep. EST:
AFE 5095
ACT
Liq.Aro.-Montar TAR
1080 1080 1080 1080 1080 1080 1080 1080 1080 1080
Disposal
EST'
AFE 2952
ACT
Warehouse
TAR 2000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
CEA 1452
EST: 2000 2000 ACT 2000
Liq.Aro.New
TAR
1500 1500 1500 1500 1500 1500 1500 1500 1500 1500
Burners #3 Still EST
ACT
Biphenyl Relocate TAR
No. 1 Preheat EST
CEA 1892
ACT
500 500 500 500 500 500 500 500 500 500 500 500
1500 150C
HB-40 2 A/C's AFE 3102
TAR
EST ACT
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
2230 2580
- -- - --
3490
DSW 551384
:n---
STLCOPCB4089801
ORGANIC DIVISION 1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Bi0 Improve
TAR
450 450 450 450 450 450 450 450
Tower Treat.
EST
AFE 3155
ACT
Improve Pit. Power Factor
TAR EST
900 900 900 900 900 900 900 900
ACT
Central Air
TAR
1000 1000 1000 1000
System
EST ACT
Optimize Rx Time TAR
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
EST 0
PNP ACT
Reduce Mole
TAR
4000 [4000 4000 4000 4000 4000 4000 4000 4000
Ratio NaOH/PNCB PNP
EST ACT
New Wash Water
TAR
50 50 50 50 50 50 50 50
Pump PNP EST 25
AFE P998
ACT
Automatic pH Control
TAR EST
500 500 500
PNP ACT
KC1 Filter Pump
TAR 330 330 340 EST . 330 330 ACT 330
New Blow Tank HC1
TAR EST ACT
200 200 200 200 200 200
200 200 200
150,000 Gal.-HCl Storage Tank
TAR EST
1760 1760 1780 17 60S 1760 1780 1760 1760 1780
AFE 2468
ACT
Produce Staley
TAR
780 1 730 790 780 780 790
Grade Acid
EST
AFE 3076
ACT
ClaPlt. Shutdown TAR
8880 388 3880 8880 8880 8880 8880
EST
CEA 1831
ACT
Hg Recover from Residue
TAR Hest
ACT
250 250 250 250
3910 0 3910
Hg Wash Tank AFE 2802
TAR EST ACT
250 250 250 250 o0 0
Biphenyl Productivity
TAR EST 0 9U0U
ACT 5150
Total Organic By Month M $
TAR
EST ACT
17.7 21.2 23,7 31.9 3(?, 7 45,5 44,0!' 46.0 46.0 47.1 47.9 45.0
27.1 19.8
Total Organic YTD M $
TAR 17.7 33.9 EST 46.9
94.6 131.3 1751s 222..9 2c79 516.0 1S7o 412.0 457.0
ACT 19.8
DSW 551385
STLCOPCB4089802
- AG DIVISION 1969 TSD COST IMPROVEMENT
ANNUAL JAN
Cooling Tower
TAR
Repiping AFE 2598
EST .'ACT
Optimize N2 &
TAR
Cl2 Levels
EST
. ACT
Increase Waste
TAR
Acid Sales
EST:
ACT
Chlorinator R.I.
TAR
EST
AFE 2244
ACT :
EVOP Condensation Rx.
TAR est: ACT.
750 0 0
Cl2 Unloading
TAR
ESI
CEA 1831 Recycle Wash
: ACT ' TAR
Water
est:
AFE 2960
ACT.
Parathion Recovery TAR
ESI
AFE 2655
ACT.
Reduce Acetone Losses
TAR EST:
' ACT
Formulations
TAR
EST'
AFE 2897
ACT.
Change Cooling
TAR
H2O Item 737
EST
AFE 3067
ACT
Well
to Jets
TAR
EST
ACT.
Ag. Division
TAR 750
by Month
EST:
ACT
0
Ag. Division YTD
TAR
EST ' ACT_ ..
TAR
750 0
EST" ACT
TAR EST
ACT
FEB MAR APR MAY JUN JIM, AUG SEP OCT__ NOV DEC 420 420 410 41 420 420 410 420 420
i i 6600 6700 6700 6600) 6700 6700
400 300 300 40 300 =500 400 300 300
25! 250 250 250 250 250
750 500 0
*00 750 750 500 5000 5000 2000 2000 2000
29 290 290 290 290 290 _ _
i 5800 5800 5800 j i
43OO 4300 4300
1600 1600 1600 1600) 1600 1600
125 125 125 125 125 125 125 125 125 500 500 500
750 50C 9145 9145 913? 14615 1468 5 146R5 14575 1443 5 14435
0 1500 2000 11145 ?0?90 2952S 44rrrr 53785 7347C 38045 10253d 117015
0
0S\N 551386
STLCOPCB4089803
Company Confidential 5.
AROCLOR
E. E. Bowles, C. R. Mcllwain, (V. R. Haupt)
Evaluate QuaterphenylFolyphenyl Effects on Solid Aroclor Yields
1969 Savings $63,200 NFC $14,000
TSD Objective B-8 (a)
Nuclear gage instrument installation scheduled to begin week of March 3. Awaiting receipt of radioactive materials license from State Health Department before radio active source for level alarm can be shipped.
Drawings for second part of project, Still Condenser Coolant Control, returned from plant review with minor changes.
Make Solid Aroclor in Liquid Aroclor System
Meet 1969 Forecast _______ of 15 M lbs .B-8 (b)
TSD Objective
Project completed in early February. Produced 280 M lbs. of Aroclor 5460 in Liquid Aroclor system during February.
Montar 5 Flaking
Savings $ll,500/yr. ,NFC $12.000
TSD Objective B-8 (c)
Montar 5 flaking project will be transmitted in March and installed by May 1. Pump delivery prevents earlier EDC.
Low Color Aroclor 5460
Quality
TSD Objective
_________________________________________ NFC ~ to be estimated____________ B-8 (e)
Presently estimating capital investment required to produce low color Aroclor 5460 by sodium treatment of Santowax. Marketing estimates sales of up to 3 M lbs. yearly of low color Aroclor 5460. Manufacturing cost estimate to be completed by 3/15/69.
Therminol System
Evaluation 'B-8 (h)
TSD Objective
The Therminol distribution problem was discussed at the Solid Aroclor Expansion Scope Review February 4, 1969 with CED. CED will provide a new surge tank plus the pump and lines for the expansion Therminol needs. TSD will provide pump and lines to effectively distribute the Therminol in the existing system. Distribution in the existing system is poor and does not supply heat where needed without re- . adjusting most of the 22 branches from the main header.
DSW 551387
STLCOPCB4089804
> Company Confidential 4.
AROCLOR (Cont'd)
Montar Use and Disposal
Savings $13,000
Project 2952 ______________________NFC $10.000,B-8 (g)
TSD Objective
Installation is scheduled for March to provide a line for pumping Liquid Aroclor Montar to Montar disposal pond.
BIPHENYL-SANTOWAX
W. G. Niemeyer, J. W. McGee, D. A. Self (V. R. Haupt)
Debottleneck Biphenyl
Capacity
Stills to 87.6M lbs/yr.Increase
TSD Objective __________________ ;B-7 (a)
CED's work in this area was mechanically complete on February 28. The plant plans to put the Santowax C surge tank and column feed pump into service on March 15, 1969 after replacement of damaged Leveltrol instrument.
No. 1 Furnace Upgrade
Capacity
TSD Objective
Liaison (CEA-1892)IncreaseB-7 (c)
This project was mechanically complete on February 28. Remaining work includes: piping and tank insulation, dismantling of tanks and piping, tank painting, and access road work.
Improve Santowax R Quality with New Distillation Column
________
Quality
TSD Objective
B-7 (d)
________ _____ ___________________________________
All instruments to be received in March. Installation of this project may be de layed due to maintenance manpower drain for the Niran turnaround.
CHLORINE
D. W. Dudley (A. G. McCarty)
Central Chlorine
CED I83I Liaison
Unloading Savings $55.300B-6 (a)
TSD Objective
Elevation grading for installation of new railroad tracks underway. Final design to be completed in March. Construction completion date is now targeted at May 1, 1969.
OS\N 551888
STLCOPCB4089805
HC1 0. J. Norris, G. L. Moore (A. G. McCarty)
Company Confidential 5.
Production of Staley Grade
New Earnings $28.8 M
TSD Objective
Acid - Project 5076 _____________ Potential Savings $71 MB-10 (c)
The catch tank portion of project 3076 continues to be expedited. Shop prefabri cation essentially complete. Bad weather held up pouring the concrete pad. Sche dule for week of 3/3 includes completion of concrete pad and walls and painting of pipe and tank. Field installation set for week of 3/10.
A meeting was held with Production and PR&D to outline program to define Staley Grade acid in terms of organic contamination level..
Muriatic Acid Storage ___________ Savings $21,200TSD Job No. 497 Rubber lining 857, complete. Piping work scheduled to begin by mid-March.
PNP 0. J. Norris, G. L. Moore (A. G. McCarty)
Debottleneck to
Capacity
1,8 M #/mo.Savings $27,500B-9 (a)
TSD Objective
Production rate continues to improve. Reaction time remains at targeted 66 min./batch with letdown continuing in 3O-35 minute range. Batch size continuing to be increased, now back to 8,000 #/batch. PR&D has completed their study of charge tank contents changes, and intensive study of process variables is leading to much better understanding of the causes of reactor letdown problems. Solid phase build up (measure of % solids) observed in sample bottles is attributed to NaPNP. This level build up is a better "before the fact" indication of letdown trouble than the old method of observing an increasing "hump" in the cooling curve. Letdown problem is strongly indicated to be phase-related phenomena. A progress report on developments to date will be issued by 4/1/69.
NIRAN
K. G. Hale, D. W. Dudley, (A. G. McCarty)
Demonstrate Parathion
Savings $17,500
TSD Objective
Recovery
10-15% Reduced
B-5 (a)
__________________________ '_______ ;______ C.O.D. Load______________________________________
Coalescer was inspected for cause of pluggage by representative of RPC corporation (coalescer manufacturer) and TSD February 6. Vendor reported that pluggage may have been caused by breakdown of wire elements since solids on elements were "high" in iron. Laboratory filtration of process stream and subsequent qualitative analy sis indicates filter and coalescer pluggages were caused by gelatinous ferric hydr oxide. Steps being taken to test sequestering of iron before filtration. Labora tory test to be run in early March.
DSW 551389
STLCOPCB4089806
.Company Confidential 6
NIRAN (Cont'd)
Parathion Formulations
Savings $10,000
TSD Objective B-5 (f)
Preliminary design for expanded facilities has been completed and drawings are out for review. Justification for the project is marginal and depends on a significant formulations volumn increase over last years Anniston production. Doubt now exist that this increased requirement will be forthcoming. In the event that an AFE is not submitted the design package will still be completed and held for future use.
Acetone
Savings $12,900
TSD Objective
Recovery
40-507, Reduction
B-5 (i)
_________________________________________ in C.O.D._______________________________________
Tentative amendment to Niran Process for recovery of acetone was approved 2/17. Gathering of background data on percent acetone presently remaining in batches is underway. Plant tests will begin on the number 3 condensation reactor in March.
Recycle Wash Water
Savings $3,500
TSD Objective B-5 (*)
Project 2960 to make washing operation counter current flow is scheduled for con struction during March turn-a round. Plant tests will begin on one washing system in April.
Sulfur Recovery From Residue___________________
$500,000/yr. Savings
TSD Objective
407, Reduction in SOaB-5 (d);
A sulfur recovery meeting was held in St. Louis on 2/20 with Representives from Ag Research, CED Engineering, Utilities Planning, Ag Manufacturing, Anniston PR&D and TSD. The purpose of the meeting was to review the proposed process, justifi cation, waste disposal, scale-up problems and other engineering aspects.
Jim Lakeraeyer, Project Manager for Sulfur Recovery, is preparing scope. Anniston TSD and PR&D will assist where possible on scope and follow-up design problems.
Submerged Pump for Refractive Index Control of Chlorination
Savings $1,500 (potential automation)
TSD Objective B-5 (c)
The pump has been re-installed. Refractometer tests have been delayed because of sandblasting and painting operations in immediate area. Production will run pump during each batch and begin collecting samples from circulating line. Refracto meter will be started-up in March to gain background data during ethyl run.
DSW 551390
STLCOPCB4089807
Company Confidential 7.
NIRAN (Cont'd)
Fume Collection System
Reduce Atomosphere
TSD Objective
in Parathion Department____________ Corrosion______________________
F-10___________
New fan still on order. Transmittal for new foundation and transition pieces was completed during February.
ENGINEERING DESIGN AND SERVICES
Mechanical/Electrical/Instruraent Design and DraftingJ. C. Price. J. A. Veazey. R. L. Brewer. J. K. Rennie. (W. F. Taffee)
Installation of emergency communications radio system (AFE 2951-$14 M) underway. Completion targeted for mid-March.
Design packages forwarded to Maintenance for Handrail and Lighting at Niran Limestone Pit (AFE 3O6I - $2500), Staley Grade HC1, switch Heat Exchanger to Tower Water.
Review drawings completed for Niran Formulation, P2S5 Vent Alarm (AFE 3I8I - $838 Recommendation of safety investigation), Solid Aroclor Instrumentation (Phase II).
Corrosion inspection services provided for Thio Acid and Condensation Reactors, Aroclor Blow Tanks and Roof Tank. Test panels of DuPont exterior finish for rigid frame structures installed as start of five year test exposure. Construction of rubber lined HC1 storage tank observed - testing scheduled for early March.
UTILITIES ENGINEERING
J. C. Price (W. F. Taffee)
Transmitted design package to P&S for Project 2988 - Biphenyl Gas Meter and Project 3067 - Cooling Water on Item 737 (savings $1500/yr.). Forwarded AFE 3184 - Relocate 1800 KVAR Capacitors (savings $10,800/yr.) for approval. Reviewed proposed improved treatment for Biphenyl Cooling Tower with John Bufe and 0. W. Siebert. Met with W. E. Chandler and discussed Utilities Cost Improvement.
PLANT IMPROVEMENT
G. C. Goodwin'(W. F. Taffee)
1968 Plant Improvement 4th quarter Progress Report was published. 1969 Plant Improvement Program was reviewed with W. E. Chandler.
DSW 551391
STLCOPCB4089808
POLLUTION CONTROL
E. G. Wright (W, F. Taffee)
Company Confidential 8.
Contact With
Community and Govt.
TSD Objective
Regulatory Agencies________ ______________RelationsF-2
One visit to city treatment plant during February. Solids continue to be their major problem.
Waste Audits
Pollution Abatement
TSD Objective
________________ ;______________________________________________ _________________?--jl_____ _
Planning underway for waste audits. Report will be issued in March.
Waste Treatment
All wastes were effectively treated during February. High solids concentrations continue to be the major problem. Average daily values for Monsanto's effluent are as follows:
Average Daily
Specifications
PNP 1.4 ppm
5
COD 52.6 ppm
<200
Parathion
.12 ppm
1.0
BOD 4 ppm
<200
PROCESS AND QUALITY ANALYSIS
W. B. Dunlap
Quality
The Plant Quality Score was 94.9, up 5.4 from January, with YTD score of 92.0 against a target of 95,0 minimum. Cost optimization experiments in Niran condensation, and a deliberate reduction in Aroclor 1242 gravity have made these products deviate from established averages. Statistical standards will be recalculated when equilibrium is reached.
Parathions - Correlate Intermediate and Parathion Isomers
Potential Savings $88,000
TSD Objective C-2
Job 878'
Laboratory tests for intermediate isomers have wide discrepancies which must be reconciled in order to correlate intermediate with parathion isomers. Routine surveillance of parathion isomers is continuing.
DSW 551392
STLCOPCB4089809
>
Company Confidential 9.
PROCESS AND QUALITY ANALYSIS (Cont'd)
PNP - Monitor Critical Process Variables
Potential Savings
$60,000
TSD Objective
c-3 Job 879_______
Extensive analysis of operating data was carried out with collaboration of the Process Engineer. This work is reported under TSD Job 482. There is strong evidence that extended reactor cooling cycles involve a phase change (crystalli zation of NaPNP) with liberation of heat. If this occurs at the boiling point, levitation of the reactor mass into the condenser and receiver results in loss of pressure drop and longer cooling cycles. This also recycles solids into the next batch, with continuing build-up of solids and increasingly severe "bumping" of the reactor during depressurization.
Manpower
Interviewing and testing of candidates for Process and Quality Analysis Technician was completed. A selection will be made early in March.
DSW 551393
STLCOPCB4089810
Company Confidential 10.
PLANT LABORATORIES G. W. Miller
PROCESS RESEARCH AND DEVELOPMENT J. T. Bell
Out of the scheduled 95 working days, 68 days were directed toward projects in the 1969 PR&D Program with 17 days expended on a nonscheduled project. The Blend Scavenger Refinement (Aroclor) study has been delayed approximately 3 weeks for a preliminary investigation of Montar 9 conversion to biphenyl or terphenyls. The program to establish possible Montar Utilization is approximately 8 days behind the published work plan.
p-Nitrophenol
W. H. Howard Reduce Cycle Times_______ ____________ J. T. Bell
Analysis of charge tank and 216 recycle water samples under normal and upset (prolonged cool-down) conditions has been completed. The only significant difference observed was an increased sodium paranitrophenate level in the charge tank under upset conditions. The laboratory reactor studies will be initiated according to the work plan with other studies included as may appear feasible.
Aroclor 1272
Sample Preparation ______ for Sales
G. L. Arnett
The program has been concluded and a report issued on the laboratory investigation.
Sulfur Refinement Sulfur Recoveryfor Reuse
I. Ransaw
A report entitled "Proposed Process for Purification of Sulfur" has been issued. A 40% or greater reduction in the COD level may be reached by chlorination of wash effluent. A technique for the quantitative determination of off-gases generated in the wash step has yet to be developed. A corrosion study to establish the feasibility of utilizing a nickel centrifuge as a substitute for the final filtration has been initiated.
Blend Scavenger
Improved Aroclor
Refinement (Aroclor)Electrical Properties__________
J. L. Brown
The project was delayed to permit a preliminary investigation of Montar 9 conversion to lower polyphenyls. A work plan is to be issued and effort resumed by 3/3/69. The work will be directed toward establishing if phenyl glycidyl ether is incapable of yielding excellent resistance values by virtue of molecular dipoles.
DSW 551394
STLCOPCB4089811
PROCESS RESEARCH AND DEVELOPMENT (Continued)
Company Confidential 11.
Possible Montar 9 Quaterphenyl Conversion:UtilizationJ. L Brown
Preliminary data indicates probable biphenyl and terphenyl production by Montar 9 reaction with AlCl^. Low yields and high catalyst requirements have been observed. Sodium-aluminum trichloride reaction with Montar 9 has produced an unidentified white crystalline material. This initial study is to be completed and terminated.
Solid Aroclor
Meet Color of
Color Improvement__________ Competitive MaterialG. L. Arnett
A chlorinated competitive material, KC-100 (Kanagefuchi) has been found to have lower color than Aroclor 5460. A sample of Kanagefuchi Santowax was chlorinated in the laboratory and found only equivalent in color to Aroclor 5460. This indicates an unknown color improvement step presumably relating to the terphenyl starting material. This project has been concluded.
Montar Utilization
Recover Aroclor Value
G. L. Arnett
The project work plan has been issued. Initial efforts to determine the maximum number of distillations that may be made prior to still bottoms removal has been initiated. Aroclor 1142 is being employed as material under investigation.
ANALYTICAL AND QUALITY CONTROL
S. 0. Kemp
Complaint Report
Quality
Number
Material
Customer
Reason
2-A-69
HB-40
General Cable
Color
YTD Quality Complaints/100 Shipments 0.16 Target 0.20
Service
None
YTD Quality Complaints/100 Shipments 0.0 Target 0.25
DSW 551395
STLCOPCB4089812
Company Confidential 12.
COMMUNITY RELATIONS. PERSONNEL. RECRUITING. AND DEVELOPMENT
Personnel 1. D. A. Self, B.S. Ch.E. University of South Carolina and 1968 summer
employee, joined TSD permanently 2/10/69. 2. A. G. McCarty, K. G. Hale, and Ish Ransaw made presentation to Ag Division
Management & CED on Sulfur Recovery Project 2/20/69. Development 1. R. L. Brewer attended glass lined equipment training course at Pfaudler
Co., Rochester, N. Y., February 3-7. 2. E. G. Wright attended a training course "Biological Treatment of Waste
Waters & Sludges" at Taft Sanitary Engineering Institute, Cincinnati, Ohio, February 10-21. 3. J. A. Veazey attended a seminar on control valves, sponsored by Fisher Governor. in Birmingham, Alabama, February 3, 1969. 4. Four people from Engineering Design and Services attended a demonstration seminar on Armstrong steam traps 2/17. 5. J. L. Brown attended an Instrumentation Seminar at Central Research on 2/13/69. 6. A. G. McCarty attended Kepner-Tregoe in St. Louis week of February 10th. 7. J. C. Landwehr attended Capsule Process Control Course at Delaware River Plant 2/17 & 2/18 and Comprehensive Interviewing Course in St. Louis week of 2/29. Visitors 1. B. B. Hedleston visited the plant to discuss railroad repairs and relocations on CEA 1831.
DS\N 551396
STLCOPCB4089813
).
' DISTRIBUTION OF TIME BY TECHNICAL SERVICE
PROCESS IMPROVEMENT
NEW PRODUCTS
i j gsrss- cznzi.
PLANT IMPROVEMENT
N t'
i. J'J
r-.n i j 3
n oH FO-
SPECIAL ENGINES'-INC SERVICES
O !
2-i |
--r-- _ L_ _
1 __ i___
=----
>--
TECHNICAL MANPOWER
MISC ELLA lNEO'JS ACTIVITIES
STLCOPCB4089814
. ......
>
.
.............
. '
.
.
...
. OUtU^ciM^ ouilixucuu JlU!
V:
.
.^
J
TSD PROJECT SUMIMARY
IN MAINTENANCE
FOR CONSTRUCTION
IN MAINTENANCE COMPLETE!;
NOT CLOSED
Fr-? APPROVAL
cao
J oa a o Ma
vai o H
a
APPROVED PROJECTS IN TSD
600 500 400 500 200 100
0 Dec. Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec. Jan.
STLCOPCB4089815
ANALYTICAL SAMPLES
60 56 52 48 44 40
LABORATORY ADMINISTRATION
i s 8 1 *
8 1 1V 1
ANALYTICAL MANPOWER
Manpower/sample
11.00 10.00
$/Manhours
9.00 8.00
7.00
% Total Plant Operating Cost
2.0 1.5 1.0
0.5
i l l 1a
11 11
____ 8
-- i--
e>
i .I
Overtime %
--|------ -
1 1 1 1
1
iI l___
1 i
I------- 1--------
11 11 !! _____ 1____ _
STLCOPCB4089816