The Plant Management Committee and Plant Union Committee held its regular meeting on September 19. 1968. The meeting was called to order by E. H. Jones. Present were:
UNION COMMITTEE
MANAGEMENT COMMITTEE
W. M. Recknor, Chairman D. E. Bozeman G. H. Bryan, Jr. J. C. Goodson Y. M. Goodwin R. F. Hawkins D. L. Knape D. L. Long W. B. Mitchell W. R. Pickett S. T. Tatum
E. H. Jones, Chairman E. R. Albritton E. N. Bras fie Id R. E. Daly W. C. Fuller J. J. Hickey Gerald Osterman N. J. Ruiz G. T. Ryan Leonard Schwab N. F. Wood
Absent from the Union Committee were: Carl Beard. Tom Choate, H. D. Utley, and Mitchell Williams.
Guests were: S. E. Hebert, Byron Johnson, Rex McDonnell, Jr. , Don Rogers, C. H. Smith, Alden Wilson, and W. J. Waits.
OLD MINUTES
SHIFT ASSIGNMENTS
UNION
said they were in disagreement with the Company's statement
on page 4 of the July 18, 1968, minutes regarding uneven staffing during
recent shutdown.
OLD BUSINESS
UNION
asked if the Company had any further information on staffing
in the pilot plant.
MAP 03981 LAM023712
Plant Management Committee Plant Union Committee Meeting
2
September 19. 1968
COMPANY
said the pilot plant workload has subsided somewhat, and this
plus the end of the fieak vacation period should permit a reasonable control
of the operator overtime load.
X-RAYS
UNION
asked if the Company had checked out the procedure used by
an employee to obtain an X-ray during his physical.
COMPANY
said they were in the process of formulating a new procedure
and hoped to have the procedure ready by the next meeting.
NEW BUSINESS
GRIEVANCE #68-6-19 - OVERTIME - WAITS - DEPT. 41
COMPANY
read grievance as follows:
Statement of Grievance
"The Company disregard of the personal rights to establish their overtime procedure on unit basis where it does not cost the Company money, the overtime is covered and has the approval of the men. "
Remedy Requested
Abide by minutes of this meeting of August 16, 1962, and allow department 41 to change the overtime agreement.
UNION
said the employees in the department had voted and a
majority are in favor of equalizing the overtime worked by the operators
and chief operators. This could be accomplished by keeping a single
overtime list for both groups with no additional cost to the Company, and
yet supervision has refused to institute this change to the existing overtime
procedure. Further stated their primary concern was the future overtime,
distribution and not what the present figures were.
COMPANY
said although there has been some dissatisfaction in the
operator group as a result of overtime distribution, the proposed change
. la i-T) /v!
CBY 3104020
MAP 03982 LAM023713
Plant Management Committee Plant Union Committee Meeting
3
September 19, 1968
to the procedure would cause the chief operators to become dissatisfied. Further pointed out'that the overtime spread had dropped from approxi mately 13 hours per month to some 5.7 hours per month since June, 1968, and it is the Company's opinion that with the return of a chief, who had been on long-term illness, this figure should become smaller. An answer to this grievance will be given to the Union.
GRIEVANCE #68-8-25 - OVERTIME - PRAESEL - DEPT. 41
COMPANY
read grievance as follows:
Statement of Grievance
"Shift supervisor, Tom Kennedy, sent me home on the 11:30 to 7:30 shift July 28th and upgraded an operator to chief when there was no extra man on shift. "
Remedy Requested
Pay for time lost on overtime.
UNION
said this employee brought to the attention of his supervisor
the fact that he should have been held over to work due to the fact that a
chief operator vacancy existed. The supervisor elected to send the chief
home and follow the erroneous schedule calling for an operator to be held
over. For these reasons the-grievant should be paid for the time he was
deprived of working.
COMPANY
said they were in agreement that a mistake had been made
when the initial schedule was made out, and this was compounded by the
fact that another employee was late reporting on the shift in question.
This occurrence may have been precluded had it been brought to the
attention of supervision earlier. The schedule had been posted since
_ Friday afternoon and the original mistake involved overtime coverage on
the graveyard shift Sunday night. The supervisor involved has been
instructed how to handle this situation should it occur in the future. An
answer to this grievance will be given to the Union.
CBY 3104021
GRIEVANCE #68-7-21 - SHIFT CHANGE - McGEHEE - MONOMERS LAB
COMPANY
read grievance ad follows:
1-.
LAM023714
MAP 03983
Plant Management Committee Plant Union Committee Meeting
4
September 19. 1968
Statement of,Grievance
"Company failed to notify me of shift change with proper notice. "
Remedy Requested
Time and one-half rate apply to first eight (8) hours worked under new schedule.
UNION
stated they did not feel it was proper for the Company to give
a shift change notice to anyone other than the employee involved. In this
case an employee is being deprived of premium pay because of poor planning
on the part of the Company.
COMPANY
said it is their policy that Article 3, Section 1, paragraph (d)
is complied with, if a responsible member of the employee's household is
notified of the shift change one week in advance of when it is to take place.
In this case the grievant's wife took the message, and said she would relay
it. An answer to this grievance will be given the Union.
GRIEVANCE #68-7-22 - SHIFT ASSIGNMENT - RAWLS - DEPT. 17-18-24
COMPANY
read grievance as follows:
Statement of Gr-ie--v- ance
"Straight day job 18C. In the past the straight day man had been picked with the most seniority, who has not had the job before. I feel supervision had discriminated against past practice rule. "
Remedy Requested
(None requested. )
UNION
said it was their understanding that over the years the
straight day job in this department had been rotated to the senior man
interested in the job, who had not had it in the longest time. In this case
a man was selected who had it before, and no explanation was given those
not selected. They said they realized that this is not a formal procedure,
but since it had been followed for a number of years, supervision should
at least inform their people why they were bypassed.
CBY 3104022
LAM023715
MAP 03984
Plant Management Committee Plant Union Committee Meeting
5
September 19, 1968
COMPANY
said the procedure for selection of a straight day operator
varied throughout the plant and no formal procedure had been established
in the unit in question. When the senior man interested has been selected
it is because he is best qualified, and in the case of the employee selected
this time he had held the straight day job once in the past for only a short
time but was unable to complete his year due to illness. If the grievant
wishes further explanation he should arrange to see his supervisor. An
answer to this grievance will be given the Union.
GRIEVANCE #68-8-24 - LEADMEN - CHOATE - PIPEFITTER
COMPANY
read grievance as follows:
Statement of Grievance
"I was notified at 0930, first of August by Mr. Hickey I would be reclassified to journeyman on the 19th of August, 1968, if I was still the pipefitter steward. This would be a 22 an hour decrease in pay."
Remedy Requested
According to Article 12, the Union may designate a shop steward. I was designated by the Union. I wish to remain steward without loss of pay and without further harrassment.
UNION
said they felt it was their right to select whomever they
wished to represent them as steward and those selected should suffer no
penalty as a result of this. To their knowledge there has been chief
operators and leadmen on the credit committee, the fire department and
other extracurricular functions in the past, and they saw no reasons why
a steward should be treated any differently. In fact, they said they knew
of chiefs and leadmen who had been stewards in the past. The Company's
action was a direct violation of Article 12 of the contract.
COMPANY
said they felt that being the steward of a major craft was a
very time-consuming duty, and would definitely interfere with the duties of
a leadman. They recognized the Union's right to select their representatives
and had every intention of recognizing the grievant as the steward for the
pipefitters. At the same time it is the Company who appoints the leadman
and his duties and responsibilities as a leadman are such as to preclude
CBY 3104023
LAM023716
MAP 03985
Plant Management Committee Plant Union Committee Meeting
6
September 19. 1968
his serving concurrently as a leadman and the craft steward. They further stated that to their>knowledge no leadman had served as a steward with the exception of a few cases where there was some delay in electing a replacement. As for chief operators acting as stewards, this is no problem, because a chief is only responsible for one area as a steward. An answer to this grievance will be given the Union.
GRIEVANCE #68-8-26 - JURISDICTION - UTLEY - INSULATORS
UNION
requested this grievance be postponed until next meeting.
COMPANY agreed.
STAFFING
UNION
said there were still instances of truck drivers being used
on overtime without helpers, and often a.helper is needed.
COMPANY
restated their position that helpers would be scheduled for
overtime on an as-needed basis.
VENDING MACHINES
UNION
said coke machines throughout the plant were being left
empty quite often.
COMPANY
said they would check this out. Also stated .employees
should call office services, extension 2201, when a machine is empty or
out of order.
CAFETERIA
UNION
said salaried employees beginning to cause congestion in
the line at Noon.
COMPANY said they would check this out.
/u ro
?
/f
gb 10-7-68
CBY 310*024