SCRUBBER PRE-START AUDIT
LPP
$ec{'on fi/Hp2_
SAFETY REFERENCE C-6 PRE-START UP AUDIT
PAGE 1
PLANT: ____Chlorine I
PROJECT TITLE:____Air Ecology, Chlorine I (Scrubber Project)
DATE:__6/3/91
1. Has the Technology Center approved the process?
Yes, see attached copy of support letter. Also includes is CATC DesignGuideline Module 14 "Chlorine Scrubber System".
2. Has any reactive chemical data been generated?
Yes, see attached copy of Titanium/Dry Chlorine reaction conditons verses scrubber operating conditions graph. Also attached is Reactive Chemical Committee Support Letters.
3. Has a reactive chemical review been done since the design was finalized? __YES________ Attach the review letter along with a written answer to any questions that were raised during the review. Has reactive chemical checklist been completed?
YES, ATTACHED
4. Has Environmental Control reviewed and approved the project?
Support letter from Environmental Services is attached
When the construction project is essentially complete, a job
safety inspection should be made,
This inspection should m-
elude:
Plant Supervisors
Plant Operators
Plant Engineer/Mfg. Rep.
Safety Department
Their inspection should emphasize:
Pipe, valves, fittings, and
associated supports
Valve location and orientation
Structures and ladders
Electrical grounding
Insulation for personnel protection
Safety showers
Fire extinguishers and deluge guns
Intercom locations Lighting Line labeling
DO A 023418 CONFIDENTIAL
Freeze Protection
PSV's
Instrumentation
Has such a review been made?
No, will be scheduled
Operator training classes should be held. These class s should highlight the following:
PRE-START UP AUDIT - C-6
PAGE 2
A. Project benefits and expected results. B. Process description (include expected operating conditions)
C. Process controls
D. Operator responsibilities
E. New procedures:
1. Start up
6. Normal Operating Procedures
2. Emergency
7. Red Tag
3. Shutdown 4. Sampling
8. Loading/Unloading 9. Freeze Precautions
5. Job Procedures
(norma1/severe)
Lab Procedures
Has such training been done? YES, see attached training sch.
7. Procedures should be reviewed by as many plant people as possible
and revised as necessary.
A plant committee of operations and
technical people should make a final safety audit of procedures.
Has such a safety audit been done?
Yes, IPT modules were generated by operations personnel. These IPT modules used the MOD V program documentation and Operating Discipline as resources.
8. Has the system been pressure tested? _____No, this will be completed
prior to start-up. Washed or cleaned? No, this well be completed prior to start-up. How? ____The system will be "run" on water.
9. Is it possible to have a dry run operation such as operating the
system on air, nitrogen, or water?
yes
If so, has
this been done? _______Not yet________ Are other plants involved in
the new process? no
10. Have all instrument loops been checked and documented? All
instrumentation checkout will be completed prior to start-up.
Full range valve stroke? __________Fail safe valve positions
verified?
______
Have critical instruments been
identified and registered?
in process
11. Has the new electrical equipment been checked out? Are field
switches, equipment and MCC starters labeled properly? Refer to
S--316 for electrical safety standards.
WILL BE COMPLETED PRIOR TO START-UP
____ _____
12. Hav the block operating manual and emergency procedures been modified to include the new project? _____yes
13. Have pressure vessels and PSV's been added to the computer list?
YES _________ Do PSV's set pressure match design pressures
of vessels?
N/A
14. Have plant and engineering files and drawings (P&ID's) been updated to include the new equipment? yes
DO A 023419 CONFIDENTIAL
PRE-START UP AUDIT - C-6
PAGE 3
15. Has a list of necessary spare parts been added to the existing , spare parts stocking list?
16. Have training classes been set up for maintenance of the new equipment: __
17. Has all associated equipment been checked? YES
18. Has a review of the control system been completed? _yes If computer control, has a simulation been done? _yes
This check sheet must be filled out and reviewed with the Plant Superintendent prior to the start up of a new project.
11/90
t, 023*20
DO
PRE-START UP AUDIT - C-6
PAGE 4
PROJECT AND MODIFICATIONS SAFETY ASSESSMENT
'LANT __Chlorine I TITLE _Scrubber Project
** those factors which have been changed by the proposal.
PROCESS CONDITIONS
ENGINEERING HARDWARE & DESIGN
temperature pressure **flow level composition toxicity flash point reaction conditions
OPERATING METHODS
**start-up routine operation **shutdown going through explosive
range preparation for maintenance abnormal operation emergency operation layout and positioning of
controls & instruments
ENGINEERING METHODS
.ip and alarm testing maintenance procedures inspection portable equipment
SAFETY EQUIPMENT
fire fighting & detection systems
means of escape safety equipment for
personnel showers & eyewashes
ENVIRONMENTAL CONDITIONS
liquid effluent solid effluent gaseous effluent noise dust diking
UTILITIES power, steam, nitrogen, water, air, fuel gas
line diagram wiring diagram electrical feeders distribution plant layout
design pressure design temperature materials of construction **loads on, or strength of:
foundations structures vessels pipework/supports/bellows **temporary or permanent: pipework/supports/be Hows valves slip-plates restriction plates filters **instrumentation trips and alarms static electricity - grounding lightning protection radioactivity rate of corrosion rate of erosion isolation for maintenance maintenance - electrical fire protection of cables handrails ladders platforms walkways tripping hazards access for: operation maintenance vehicles plant fire fighting underground overhead: service equipment safety relief devices normal freeze protection severe freeze protection (20 deg. F, -10 deg. F
windchill)
[meyer.scrubber]prestart.audit