A. EASTERN REGION .anufacturing
MONTHLY MANUFACTURING REPORT AUGUST 1975
1. FINANCIAL SUMMARY a. Results
Inter-Co.
Trade *
Total
Plant Sales July Plant Sales Aug. Plant Sales YTD
b. Discussions
$ 177,000 211,000
$1,716,000
$ 118,000 118,000
$ 962,000
$ 295,000 329,000
$2 ,678,000
August sales were up 11.5* from July which still has the plant on a two shift schedule. The work force has been increased slightly and there are now 20* of the work force on lay off.
2. FUTURE VARIANCES
a. Red pe
X
Trials on 265A free Kalminex have not been made due to a strike at Latrobe Steel.. It is hoped that FPD will change their recipe to EP 3502 3 by mid September.
b. Foseco Trucking
Savings for the month were $9,562.68. 89 truckloads were hauled which was 64* of the total freight hauled from Mt. Braddock. Cost per mile was reduced from $.689 to .656. per mile. Accumulated savings thus far in 1975 are 78,4S0.35 for an average of $9,806.28 per month. Average cost per mile thus far is .696 per mile.
c. OSHA
In early September OSHA inspectors returned and ran air sampling tests and the results shall be forthcoming. The checks were for asbestos, silica and general nuisance dusts.
d. Quality Control
.
"rr '
Exothermics
Good plug production, yielded no scrap problems for the firs,t half of August. Other one-piece hot tops and Exothermics also ran well for the month.