Document x5zeOq3eyQ9JJaYDVm231254m
The Agency erroneously calculated the cost-effectiveness by not including a baghousc for mercury control. When the cost and efficacy calculations are corrected, the cost-effectiveness for non-mercury I 'AP metals is $24.7 million per ton, not $756,000 per ton, and the cost-effectiveness for mercury is $713,000 per ton, not $32,000 per ton.24
D. EPA Relied on Erroneous Data to Calculate Energy Required to Implement the Proposed BTF Measures at Jewell
EPA wrongly calculated that the increased energy to meet these proposed requirements would be 1.5.1 million kilowatt-hours of increased electricity use. 88 Fed. Reg. at 55858, 55894 (Aug. 16, 2023). SunCoke has not been able to locate any analysis by EPA that supports these estimates, thereby depriving SunCoke of the opportunity to analyze the "connection between the facts found and the choice made."' Motor Vehicle Allis. Ass'il v. Slate Farm Mid. Ins. Co., 463 U.S. 29, 43 (1983). SunCoke's calculation shows that the true increase in energy would be 93.18 million kilowatt hours (more than six times EPA's estimate).
E. EPA Did Not Consider Non-air Quality Health and Environmental Impacts of the Proposed BTF Measures
Related to its grossly inadequate estimate of the energy requirements for its proposed controls, EPA did not sufficiently consider the infrastructure upgrades that would be needed to serve the controls. At a minimum, the following electrical infrastructure upgrades would likely be required to address the incremental power demand of 10.5 MW:
An upgraded Appalachian Power Company substation for an additional 69 kV load;
Roughly 4,000 feet of 69 kV transmission line;
A new substation at the Jewell site to receive 69 kV and step down to 4160V for further distribution across the plant;
4160V switchgear and motor control centers for multiple induced draft fans; and
4160V stepdown to 480V, switch gear, and motor control centers for ancillary gear serving the baghouse and AC1 systems.
Moreover, in light of Jewell's topography, installing the infrastructure could require surfaces to be levelled and forested areas to be cleared. These electrical upgrades would likely impact wetlands, visual resources, soils, and/or vegetation and wildlife species in the affected areas, which EPA (foes not appear to have considered. This is especially true given the forested surroundings for the plant and the fact that the entirety of the facility lies in a floodplain; for this reason, federal law requires EPA, before requiring changes that would impact floodplains, to "consider alternatives to avoid adverse effects and incompatible development in the floodplains."2' In addition, the increased 10.5 MW demand would increase CO, emissions by more than an estimated 46,000 tons annually just to produce the electricity needed to run such a system. EPA further underestimated
('ompetre I'ab. 6 with Attachment I) (TRC Technical Memo) at 5 Exec Order 1 1 98 8--Floodrilain Management, 2(a)(2).
24
Sierra Club FOIA 2025-EPA-04883
ED_018388_00000109-00025
SC_EVERSPLIT0005699