ANNISTON PLANT TECHNICAL SERVICES DEPARTMENT
1966 OBJECTIVES
A. TSD Long Term Objectives I. Safe manufacture of quality chemicals at minimum long range cost. (See also separate Liaison Objectives)
II. Employ and train technical personnel to make manufacturing cost improvements and for plant growth.
III. Preserve and .improve physical assets and plan for plant growth. (See separate Plant Improvement Objectives)
B. 1966 Goals and Actions
1. Safe manufacture of quality chemicals at minimum long range cost,
a. Safety
1. Maintain major accident frequency of 0.0
(All)
2. Attain minor injury rate of 2.0 or less
(All)
J. Conduct monthly department safety meetings (TSD Members)
4. Engineer long range safety projects
a) Winterizing of safety showers
(J.C.Price 8/1/66)
b) Color coding of utility piping
(J.C.Price 5/1/66)
c) Dual relief systems
(J.C.Price 7/1/66)
d) Vents on vessels and tanks
(H.W.Ellis 4/1/66)
e) Separate city water and cooling water
systems in Niran
(J.C.Price 10/1/66)
b. Quality
1. Expand quality surveillance program by
charting all finished products having
25 lots and 50*000 pounds per year
(W.B. Dunlap 5/66)
2. Conduct training course for technical personnel in "Practical Statistics"
(W. B. Dunlap 6/66)
DSW 551727
STLCOPCB4090144
Anniston Plant Technical Services 1966 Objectives
-2-
3. Review conformity of all raw materials to
established specifications
(W.B.Dunlap 6/66)
4. Carry out a statistical study to determine need for improved container weight; control (W.B.Dunlap 9/66)
5. Apply statistical operations control to Aroclor Department
(W.B.Dunlap 12/66)
c. Cost and Process Improvement
1. Attain specific cost improvements of at least $548,000 as detailed in the 1966 Cost Improvement Program
2. Maintain technical effort of 55% on Process Improvements
3. Update all Process Improvement Plans 1 year from initial date of issue.
4. Implement Chlorine Control Program
5. Develop program to upgrade electrical facilities and replace knife switches in Chlorine Plant
6. Develop mercury material balance and
a program to reduce mercury losses in Chlorine
7. Complete program to upgrade Aroclor quality and reduce residue
8. Evaluate steel bottom cells for
Cklorine Plant
a) Upgrade existing cells
b) New cell bottoms
9. Increase PNP Production to 19.5 M #/yr,,
10. Debottleneck Solid Aroclor System to meet design rates
(Department 1/67) (L.C.Fuhrmeister) (Chemical Engineer) (Faulkner and Pro
duction 6/66)
(Veazey - Faulkner 4/66)
(J.Taylor 6/66)
(J.Bryant-J.MacPherson
8/66)
(J.Taylor - L.
Faulkner 8/66) (R. Taylor 6/66) (MacPherson 8/66)
11. Increase HCl recovery efficiency to 95% .
(R. Taylor 9/66) DSW 551728
STLCOPCB4090145
Anniston Plant Technical Services
1966 Objectives
-3-
d. Liaison and Start-ups
1. Provide liaison and back-up support for
1966 new plant expansions and major
projects
(W. F. Taffee - L.C.
Fuhrmeister)
2. Outline and determine start-up needs for all plant expansions in 1966
(Taffee-Fuhrmeister
3/66)
II. Employ and Train Technical Personnel to make Manufacturing Cost Improvements and for Plant Growth.
a. Personnel
1. Hire personnel to fill manning chart
(L.C.Fuhrmeister)
2. Hold bimonthly training sessions
(L.C.Fuhrmeister)
3. Continue development of technical personnel through technical seminars and short courses
(L.C.Fuhrmeister)
4. Investigate program for continuing education
a) Through Dr. William R. Bennett, Director of Graduate Division University of Alabama
b) Through Associate Industries of Alabama Committee on Educational Activities
(L.L. Faulkner 7/66)
5. Develop personal objectives for self Improvement, to be reviewed quarterly
(L.C. Fuhrmeister Engineer)
b. Function
1. Develop 6 new TSD Guidelines
(L. C. Fuhrmeister
12/66)
2. Update all plant maps and maintain current
(J. C. Price 7/66)
3. Revise department filing system and discard obsolete material
(L.C. Fuhrmeister * Engineers 12/66)
4. Update Drawing File System - investi gate micro film system
(G.C. Goodwin 10/66)
DSW 551729 STLCOPCB4090146
Anniston Plant Technical Services
1966 Objectives
-4-
5. Set up technical library
-
6. Survey plant power system, issue single line drawings of plant system and Individual departments
7. Set up Physical Constants Data Books for all primary products, to include data on raw materials and intermediates
So Move to new facilities with minimal interruption
9o Set up separate service budget for
(L.C. Fuhrmeister 0. E. Dolin 9/66)
(Jo Ao Veazey 12/66)
(Engineers 10/66) (L. C. Fuhrmeister) (LoCoFuhrmeister 5/66)
/kd
DSW 551730
STLCOPCB4090147