Document x17k0N3pKJagQRrRpoLREdM50
INTEROFFICE MEMORANDUM
j0 Distribution
From
T. Barr
~
Distribution;
A. J. Diglfo A, E. Greene
D. C. Keehn R. C. Sander
R. H. Schenck J. K. Spata
Date 20 October 1982 Si.hiect Changes to EPA Standard for Vinyl
Chloride___________________________
(Location, Organisation. ot OtMrtmtnt}
Regulatory Response
(Location, Organisation, or D*arim*nt)
The Manufacturing Technology Committee of the SPI VC-PVC Producers Group met in Cleveland on 19 October to review the response by EPA to our earlier letter supporting changes in the VC standard. Comments were prepared and persons were assigned to act as discussion leader for each point. A detailed agenda was prepared for the meeting with EPA at RTI on 10 November. Industry positions were essentially unchanged from prior reports, except that it was decided to drop any other limiting criteria from the 100 lb de minimus exceptions for discharges, and ask for discharge size as the only criterion.
Several other items of interest were discussed during the day. These are summarized below.
Enforcement:
Goodrich is attempting to avoid filing of another civil suit at their Louisville plant by negotiating a settlement with Region IV. The Calvert City case is in obeyance pending this discussion. They have met with the EPA contractor who is evaluating their response to the Sec. 114 letter at Plaquemine, and their Pedrichtown - Sec. 114 response also has been referred to a contractor.
Shell also has met with the contractor concerning the Sec. 114 letter for their Norco plant, and expects a plant visit in November.
Conoco also expects a visit in November, and has been told that con tractor reports will be early In January. They expect action from Region IV also.
Ethyl lawyers are discussing their case with Region VI counsel.
(320)
APOOOf8855
Page 2 Hooker has no actions active at this time, but two old Sec. 114 letters are outstanding. Wastes: Goodrich stated that they had reviewed a letter from Kentucky regarding the closed BFG/AIrco landfill, and had thought that "we" should have gotten one, also. It is not clear if "we" is Airco or Air Products. The State selected it as one of 22 sites which scored the "best" in the 100 sites surveyed, and have recommended all 22 to Superfund for action. In-Service: In a general discussion of the meaning of "in vinyl chloride service", it was agreed that both liquid and vapor phases must be considered, and that a tank with a VC-rich vapor must be termed in-service. Several companies have had this question raised, and all agreed on that con clusion.
JTB:csm
APOOO18854
To From
INTEROFFICE MEMORANDUM
Distributlon J, T. Barr
Distribution
A. R. Adams L. W. Allen A. J. Digllo R, L. Duggan A. E. Greene B. Helms J. Kadlec
Datft 7 October 1982_____ Subject 1982 Meeting of the Vinyl Chloride
Safety Association_________________
(Location, Organization, or Oepartmant)
Regulatory Response
(Location, Organization, or Department)
R. C. Leltzau J, M. Norwood J. 8. Pfeiffer
T. Regan R. C. Sander A. J. Santay
R. H. Schenck H. J. Smith J. K. Spata
L. B. Tepper
R. Varllek H. L. Watson
The annual meeting of the Vinyl Chloride Safety Association met In Toronto on
23-24 September. Attendance was 47 persons from 27 companies In 9 countries. This was down from the previous year due to business conditions.
The officers elected for next year are:
President
- J.' Wallace, Esso Canada
Vice President - R. Frohrelch, Conoco
Secretary
- H. Olsen, Ethyl
Treasurer
- J. Gabbett, Ga. Pacific
Program
- H. Waltemate, BFG
The next meeting will be held In New Orleans in early October, 1983. Subjects
to be emphasized will be monitoring equipment, a review of the hazards of closed reactor operation, and a discussion of maintaining food-grade products.
The luncheon speaker on Thursday was J. Weisz, special assistant to the President of BFG. He discussed the reasons for formation of the Vinyl Institute, and Its goals. The cause Is the dissatisfaction of the Industry with present trade association response to the many new local and state attacks on the safety of
PVC products, especially pipe and other construction products which are being encouraged by activist groups, the fire community, unions, and competitors. The purpose Is to respond vigorously to these problems in a unified manner and
he spoke of eliminating unnecessary proliferation of groups active In this area. The Institute will operate as a separate organization with its own
staff but generally under the umbrella of the SPI. By-laws, staffing, and other details have been worked out by an ad hoc founding group consisting of BFG, Dow, Conoco, Tenneco, and others. A formal organizational meeting will be held in Chicago on 6 October.
(320)
AP00018855
TO: Distribution FROM: J. T. Barr
DATE:
7 October 1982
SUBJECT: 1982 Meeting of the Vinyl
Chloride Safety Association
PAGE 2
A strong pitch was made for the Safety Association to combine with the Institute. Discussion at a later business meeting Indicated little support for this, because of the feeling that the Institute would generally be concerned with commercial and political issues, while the Safety Association was directed at manufacturing safety.
A brief description of the various discussions and reports is attached.
JTB/cay Attachments
REGR1-D
AP00018856
1. True Confessions
A. John Vaughn of ICI described two incidents. In the first, the control room of the VC plant at Runcon had been receiving area monitor alarms from a leaking pump seal for several days. The pump was repaired but a snap-on nitrogen hose used in purging was left connected. The next time the pump was started the hose burst. The operator Ignored the area alarm because of Its past frequent action, and allowed about 10 tons of VC to escape. It flowed down a slope to the river, but wind blew It back toward the plant, setting off other alarms. Concentrations of 30-40 ppm were seen at 1,000 ft. from the pump and an ice build-up 2 ft. thick formed over a 10 x 40 ft. area of liquid flow, which took 2H days to melt. The operator and the mechanic who signed off the work order were disciplined.
The second incident was at their Australian plant. A technician removing the actuator on a 4" Mason-Nlelan Camflex valve scribed the actuator position on the valve body, but also removed the safety clip, so that when he replaced the device It had rotated 1 spline out of position. When the valve was returned to service It allowed about 1 ton of VC to flow to an open reactor. They no longer service valves in the field* but take them out of the line.
B. Jose Perez described a VC release at the Marlcalbo, Venezuela plant. Leakage began on the line Into a storage sphere just after restart of the monomer plant. Over 11 hours about 21 tons escaped, despite venting to the flare from the sphere. The cause was poor maintenance and Inspection procedures, plus production of wet, acid-containing product (the plant was 6 yrs. old). Control of the leak was hampered by Inadequate protective clothing, a poor deluge system, and Inability to pump water Into the sphere to seal off the VC.
C. Jorge Zarate of PRIMEX gave an update on the storage tank fire which was discussed at the 1977 meeting. Briefly, a mechanic removed the bonnet, rather than just the actuator on a valve on a storage bullet containing VC. The cloud ignited at a nearby plant, and the resulting fire destroyed all 7 storage tanks. Exploding tanks traveled as far as 400 meters, and destroyed the boiler house, laboratory, and other facilities. Fire and acid rain caused widespread damage outside the plant. A major contributor to the damage was undersized relief valves on the tanks which did not relieve adequately under fire conditions. The rebuilt plant has a single storage sphere, with deluge system and Insulation, excess check valves and minimum sized piping.
This year that plant had a slurry spill when an operator left a valve to the drop header open while lancing a reactor, and the slurry from another reactor backed Into the open reactor and onto the floor. The operator was fired and a double check on valve positions Is made by a second person before a batch is dropped.
AP00018857
D. Herm Waltemate of BFG described an Incident In their Australian VC plant In which 676 tons of VC were spilled In about 5 hours. A mechanic unfamiliar with the job removed the actuator support from the pipe below a valve on a sphere full of VC. The purpose was to replace that pipe section, which had been found corroded at an earlier Inspection. The wire mesh cage around the yalve was not removed, and in jockeying the pipe section the actuator was bumped,
pulling the valve partly open. An attempt to force the valve shut by using a lever on the actuator body broke the arm and the entire contents were lost. The plant was down for scheduled maintenance, so they were able to trip the main power circuit, and avoided Ignition. Concentrations of 1% were seen at 300 ft. and 1-2 ppm
at 6 miles. The weather was mild, with a 12 mph steady wind. Ice built up as much as 10 ft. thick under the tank and hampered
efforts to stop the leak.
A review of contributing factors indicated that what was thought to be an effective work order system failed because:
1) The WO was written by an engineer based on the Inspection report and not a field check.
2) The polymerization foreman signed off because the storage area foreman was busy elsewhere.
3) A mechanic rather than an instrument man performed the work.
4) A very large section of line was removed In one piece without taking off the guard In an attempt to save time.
5) The maintenance foreman was out and a lead mechanic was supervising.
6) The valve was not fail safe, air to open, but air to close.
Norsk Hydro Epidemiology
S. Krlstensen of N-H summarized a recent epidemiology study at their plant. It covered 454 men with more than 10 years' exposure, most of them having been at the plant since the start-up in 1950. The major
points can be seen from the table below:
Expected
Observed
Oeaths, all causes
59 50
Deaths, all cancer
20 23
Anglo Lung
Melanoma
O1 35
0.8 4
2
AP00018858
The study was not controlled for smoking, so the significance of the
apparent excess of lung cancer Is not clear. The melanoma sites were the nose and chest. The expected cases were estimated on the Norwegian Cancer Registry data, age adjusted.
Based on estimated relative exposures, the data are:
Total Cancer
Lung
Melanoma
Low Medium
High
6 21 3 00
14 3 3
The number of persons in each category was not given. These results are being submitted to a journal. It Is the first study that associates melanoma with VC exposure, but the data are far from conclusive.
III. Stress Corrosion Update
Jim Wallace of Esso Canada gave an update on chloride-induced stress corrosion of stainless vessels. The first discussion on this subject can be found In my 1978 report. Experience has shown that predictive equation of 1979 has been fairly accurate for service below pH of 4, but
that service life Is longer than predicted at high pH. Also, absence of oxygen lengthens the service life.
Attachment I contains a summary of his presentation. Laboratory studies conducted by Esso show little difference In 304 and 316 steels, but plant experience continues to favor 316. Both chloride Ion and oxygen are harmful, but pH remains the major factor. There has been no cracking reported in high nickel or mixed metallurgy alloys.
Conoco reported the sudden total failure of a 304 slurry tank. Large cracks appeared over the entire Insulated area and a piece over 1.5 ft. long simply fell out. It was found that the mastic used to bond the Insulation had high chloride content.
IV. Relief Valve Survey
Bob laundrle of General Tire passed out summaries of the survey on reactor relief valves made shortly before the meeting. Several companies did not reply in time to have their data Included. See Attachment II.
There Is considerable variation in the relief area used per unit volume.
We are company B and are above average in our sizing. We are still In the minority in not having a vent In the pressure gauge assembly between the rupture disk and the relief valve at the Escambia plant.
V. Construction Safety
D. Matthews of Esso described the system used by them' to assure safety during a major expansion of an operating plant. Parallel staffs were used for construction and operation. The Maintenance Superintendent was chairman of a Construction Safety Committee made up of persons of
3
APOOOI8859
like responsibility from both groups: the Operating Supervisor and the Construction Manager; the Process Superintendent and the Start-Up Leader; and so on. These met every two weeks to set schedules and resolve conflicts. The job engineers met their peers weekly or more often as needed.
A safety coordinator was In charge of the safety watchers (one to five) and Issued all permits and oversaw all testing. All workers had a general Safety Watch Guideline, while the watchers had a thick detailed manual.
They aimed for zero defects and completed the job with no Incidents. Another expansion on a nearby polyethylene plant had two small valve stem fires and was shut down for two weeks to review their safety proce dures.
VI. Radioactive Level Gauges
Joe Serratore of Esso discussed the radioactive level gauges installed
137
on their reactors at this project. These were 500 mC Cs sources. Attempts to use these gauges on the reactor heads were abandoned because of poor performance due to back scatter from adjacent units, false readings during charging and heat-up due to foam, and excessive downtime due to calibration and maintenance.
ICI stated that they had used these devices successfully and that they had prevented any further overcharging problem. One other company said that It also uses these. Another company said that it had a different type of internal level Indicator In use. Three companies said that they had tried but abandoned the devices.
Esso did report successful use of the device as a stop-go indicator for reactor drainage. The receiver was located tight to the bottom nozzle neck so that the signal did not pass through the jacket at that end. Additional procedures are needed to prevent persons from entering the reactor when the source Is not fully shielded.
VII. Plant Team Safety Review
M. Tawney of BFG described a company-wide team safety review which was undertaken after the Australian Incident described earlier. A Corrective Action Team, consisting of persons from Safety, Engineering, and Manufac turing, with up to 6 persons, has been surveying each plant in a 4-step process:
1) Determine existing hardware and procedures.
2) Define deficiencies and recommend corrective actions.
3) Develop plans and schedules.
4) Follow up on implementation.
4
APOOOt 8860
Two problems were found that required Immediate action; other plans were spread over 6 months-5 years.
Typical actions included:
1) Work, order procedure revisions.
2) Plant organization clarification.
3) Standardize vessel Inspection procedures.
4) Standardize relief valve Inspection schedules.
5) Hardware standardization and revisions.
Specifications taken to prevent a recurrence of the sphere Incident In Australia Included:
1) Minimize the number of working bottom openings on spheres. There had been up to 9.
2) Install remote actuators on all working lines that are fail safe (closed) quick-acting fire safe. They are not comfortable with just excess flow check valves.
3) Install dual relief valves with locked service valves below.
4) Install a deluge system with continuous monitor activation/alarm.
5) Change the WO procedure to require job release at the site, with an audit function.
This report provoked considerable discussion and a poll by a show of hands was taken on several subjects.
Storage tank Inspection:
Internal - annual 2 years
3 years
5 years never
1 1
2
8 2
External - annual
several
Storage tank fire water protection:
Hone Hand hose Fixed monitor Deluge
Both fixed and deluge Burled tanks Insulate
0 D
11 16 12
2 4
S
APOOO18861
Storage area monitors:
None LEL
Chromatograph Both
0 13
15 12
Bottom valves:
Excess flow checks
Air operated El ectrlcal
6 15
0
Bench test relief valves:
Annually 2 years
3 years 5 years
19 0
2 0
Bottom valve type:
Gate Plug Ball Butterfly
1
11 13
0
Deluge system testing:
Full flow annually Controls only
10 17
ICI commented that their practice had been to test the control systems
only until they tried a full flow test and found that the pipe system collapsed.
VIII. Problems With Computer Systems
J. Gabbett of Georgia-Pacific discussed some of the problems they have encountered with computer control systems. Many of these stem from the reluctance of an operator to be criticized for missing a charging
window and the shortcuts taken to avoid this. Forgetting that overrides had been made led to several near serious Incidents and one fire. Their computer now cancels an override after 3 minutes.
IX. Cardinal Safety Rules
Goodrich has prepared slide/tape training programs on 4 basic subjects:
Hot Work Permits
Vessel Entry Lockout Procedure Forklift Trailer Entry
16 minutes 17 minutes 20 minutes 13 minutes
6
APOOOI8862
We were shown the one on hot work permits. It Illustrated each of the steps in preparing and complying with their procedure In a simple and detailed manner. These programs can be borrowed from BFG,
They had found that 7 of 11 recent fatalities had Involved these 4 procedures. Since Inauguration of these training programs, they have
had 14 violations, for which 7 men were fired, and the other 7 (and sometimes their supervisors) were disciplined. There have been no Incidents In the past quarter.
The Hot Work Permit program dwelt on common sense and job knowledge. It Is their general rule that a permit is needed In any Class I, Division 2 area, as defined by Safety, or In any confined area.
X. Vent Prevention System
C. Loechelt of Ethyl described the vent prevention system shown in Attachment III. If an unusual incident requires venting, valve 1 ahead of the vacuum compressor closes and the bypass opens. If the amount is
too great for the gasholder, valve 3 also closes and the excess vapor Is retained In the KO pot. The sequence can be Initiated by an over pressure as shown by detail A.
The system simply Is to buy time for the recovery system to catch up with demand. There are two in operation In their plant. One Is about half the size of a reactor, the other is about equal. One is agitated,
the other Is not. The system has been successful so far, but most tests have involved small amounts such as those resulting from an overcharge.
XI. Anglo Registry
John Stafford of ICI discussed the registry of worldwide angiosarcoma
cases which he has been maintaining. His count Is now up to 100, with 2 still alive, but one of these (Italian) Is not typical, and thus Is doubtful.
Job descriptions of the cases are as follows:
Reactor cleaners Other poly workers
Maintenance
Management/Research Other PVC PVC unknown
Monomer Other
42 28
2 3
2 17
3 2
He does not see a decrease In the rate of occurrence of these cases, especially In Europe. The last date of first exposure Is 1964, so we
do not know the effect of steps taken in that decade because of AOL. He notes that there Is only one case of both AOL and anglo. It may be that later cases may show longer latency and thus spread out the future
reports, but he points out that we can expect only a few dozen more cases at most, and not hundreds.
7
APOOO18863
He has searched for some relationship between cases other than the clustering seen to occur at a few plants, but has not found any. There is no correlation between size of plant and cases, or latency and date of exposure. There may be a weak correlation between date of start-up and clusters, especially in the U.S., where there are no cases In plants started after 1957, but there are several other old plants with no cases. John retires next year and it Is not certain who may continue the registry after that. A copy of the full report Is available In my office if anyone is Interested. XII. EPA Enforcement Four companies were represented which had received Sec. 114 letters from EPA Region VI on emergency releases. A typical copy of this very extensive reporting demand Is available. Georgia Pacific sent in a 26-lb reply prepared by outside counsel. BFG noted that some releases were not included in the list. They sent In a 6" report for Plaquamlne. They also expect a similar letter for Louisville. PPG sent in a 5" report, claiming record retention limits on those over 2 yrs. old. Ethyl sent In a "full box" reply In 1981, and have had some discussions with Region VI. In addition, Pantosote received a similar letter from Region II at their Passaic plant. XIII. APCI Presentations Tony Santay described the VC exposure risk, study done for the 15 gal. reactor at Trexlertown Labs as an example of the risk assessment hazard review studies done by us. The writer presented an update of regulatory actions on Items of Interest to the VC/PVC industry. See Attachment IV for an outline. The general terms of the settlement with EPA at Calvert City also were described.
3
AP00018864
CHLORIDE STRESS CRACKING REVIEW
1978 VCMSA MEETING
PREDICTIVE EQUATION FOR STRESS CRACKING TIME PRESENTED
SHOWING 316 CRACKING TIME FOUR TIMES THAT FOR 304:
INDUSTRY SURVEY STARTED.
1979 VCMSA MEETING
GOOD SURVEY RESPONSE - RESULTS REVIEWED. conclusions:
AT PH VALUES <4 - PRECICTED TIMES REASONABLY
ACCURATE.
AT PH VALUES >4 - BETTER RESISTANCE TO STRESS
CRACKING THAN PREDICTED.
IN ABSENCE OF OXYGEN - BETTER RESISTANCE TO STRESS CRACKING THAN PREDICTED.
1980 ECC SLOW STRAIN TESTS ON STAINLESS STEEL IMMERSED IN SLURRY WATER AT 90C.
CONCLUSIONS - TABLE 1
WORST
STEEL
304 316 304 316 316 304 L 316L
HEAT TREATMENT
SENSITIZED (800C, SLOW COOL)
SENSITIZED SENSITIZED SENSITIZED NON"SENSIT1ZED EITHER EITHER
PH
4.3 4.3 7.2 7.2 4.3 4.3 4.3
OVERALL - LITTLE DIFFERENCE BETWEEN 304 AND 316. SENSITIZING IMPORTANT - MAY BE CAUSED BY WELDING. PH IMPORTANT. LOW CARBON GRADES SUPERIOR.
CONCLUSIONS - THE STRESS CRACKING WAS DUE TO HEAT SENSITIZATION AT THE WELDS AND BEGAN INTERGRANULARLY.
APOOO18866
1981
- A SECOND SERIES OF TESTS WAS RUN IN WHICH BOTH PH AND CHLORIDE WERE VARIED.
- RESULTS WERE AS SHOWN GRAPHICALLY.
CONCLUSIONS - INCREASING THE PH FROM 3 TO 7 DRAMATICALLY IMPROVED CRACK RESISTANCE IN THIS TEST ON EITHER 316 OR 304.
1982
- THE CURRENT SURVEY RECEIVED LESS RESPONSE. ANSWERS
ARE SHOWN IN TABLE 2. THE RESULTS SHOW LESS COHESION,
BUT GIVE THE FOLLOWING INDICATION:
- ITEMS 4A, 4B, 4C UNDER SIMILAR MILD VAPOR CONDITIONS AGAIN SHOWED 304 INFERIOR TO 316 OR 316L. CONCENTRATION OF LIQUID MUST BE SUSPECTED
THOUGH NOT DECLARED.
- ITEM 5 (316 CLAD) FAILED IN 1/3 PREDICTED TIME,
BUT HIGH TEMPERATURE SURGES OCCURRED.
- ITEM 6 WOULD NOT HAVE BEEN EXPECTED TO FAIL UNLESS THE CHLORIDE WAS VERY HIGH.
AP000I8867
- ITEM 7 WAS ALSO PREMATURE.
FINAL CONCLUSIONS
THE WEIGHT OF EVIDENCE STILL INDICATES THAT:
- 316 IS BETTER THAN 304.
" LOW CARBON GRADES ARE BETTER THAN NORMAL, ESPECIALLY NEAR WELDS,
- NEUTRAL PH IS BETTER THAN ACID.
TABLE 2 1982 STRESS CRACKING SURVEY
MATERIAL TEMPERATURE CHLORIDE CALENDER ACTUAL EXPECTED a/e
(c=clad)
C/F
PPM
YEARS
A YEARS E YEARS
1. 304 2. 304 3, 304 4A. 304
71/160 120/233 199/390
30/86
?1 ?
7
10
16 4.8
55
12 7.2
10 10
70 0.14
5, 316C
82/180
6, 316L
115/239
7, 316 (Ti) 60/140
25 7
20
1.2 1
>5
0.84 0.75 >1.5
2.7 0.3 15 0.1
8. 321 9. 410
60/140 82/180
20 25
>20 1.3
>6
1
3.6-14
?
PH COMMENTS
3.6 SLURRY TANK
FLUID BED DRIER PANELS
9-10 SPRAY DRIER 7 VAPOR PHASE (EVAPORATION)
UNSPECIFIED PLANT
3-4 STRIP DRUMS IN WELDS 8-10 EXCHANGER 4-5 UNSPECIFIED PLANT
LIQUID AND VAPOR.
4-5 AS 7.
AGITATOR BOLTS
UNCRACKED
4B. 316 4C. 316L
30/86 30/86
10 10
10 10 100+ 10 10 100+
7 AS FOR 4A. 7 AS FOR 4A.
AP00018869
yinyl Chloride Safety Association
PVC REACTOR PRESSURE SAFETY RELIEF FACILITIES
COMPANY
____________A ___________________________ B
REACTOR VOLUME* USG
3500
7400
3750
6000
25*000
25*000
SAFETY VALVES (RV) Number Inlet Si2e Outlet Size Orifice Area/Type*in^
Set Pressure* psig
1 6 10 16/R 275
1 6 10 16/R 275
1 4 6 6.4/B 220
1 6 8 ll.O/Q 220
3 8 10 26/T 180
4 8 10 26/T
200
RUPTURE DISCS (RD) Series w/SV Number Type Size* dia.in. Material. Supplier Model Set Pressure/Temp.0F. Set PresSure/Temp.F.
Y 1 SCRD 6 Ni FIKE BT 332/72 318/190
YY
11
SCRD
64
Ni Ni
FIKE
FIKE
BT SD
264/72 220/72
251/180 218/212
Y 1
-
4 Ni FIKE SD 220/72 218/212
Y 1
-
16 Ni FIKE SD 188/72 178/212
Y 1 SCRD FSB 18 Ni BSB SSB 190/72
-
RUPTURE DISC LEAK DETECTION
Pressure Guage
YYY
Vent w/Valve
NN N
Free Vent
aN N
Exc.Flow Valve
YYN
Telltale Ind. Other
NN NN
N -
YY
Y
NN
N
NN
N
N*
Y
NN
N
- P.Switch P.Switch
REACTOR NOZZLES FOR SAFETY RELIEF
Nozzles, No*
1
Size
6
1 6
1 4
11
1
4 16 18
4000
1 3 4 3/200
Y 1 DV 4 SS BSB DV 205/72 194/132
N Y N N N -
1 4
6000
1 3 4 3/200
?
1 12 16 69/W 230
7
1 12 16 69/W 270
Y 1 DV 4 SS BSB DV 205/72 194/132
YY
11
KBA
KBA
12 12
SS SS
Continental --
--
230/184 270/18
NYY Y -N -N-N-- ---
1 22 4 12 12
APOOO18870
Robert W. Laundrie xd 9/13/82
Page 2
COMPANY
EF
REACTOR VOLUME, USG
75,600
7,250
SAFETY VALVES (RV) Number Inlet Size Outlet Size Orifice Area/^pe, in^
Set Pressure, psig
2 4/6 6/10 3.2/14,7 203/232
2 5 8 10.5/Q 285
RUPTURE DISCS (RD) Series w/sv Number Type Size, dia.in. Material Supplier Model Set Pressure/Temp.F
Set Pressure/Temp.F
Y
1
KVB 6
Ni
C
228/176
Y
1
? 6 SS bsb
SJO 276/72
256/175
RUPTURE DISC LEAK DETECTION Pressure Guage Vent v/Valve Free Vent Exc. Flow Valve Telltale Indicator Other
Y Y N N N
-
Y N N N N N
REACTOR NOZZLES FOR SAFETY RELIEF
Nozzles, No.
2
Size
6/6
1 6
G
13,000
800
3600
H 10,600
10,600
I 26,000
J 26,000
- - .. 1
"--
4
--6
- " -- 6.4/FF
240
240/247/254
N 4 KVB 6 Ni BSB S-9Q-II
232/176
NN
22
RVB
RVB
66
Ni SS
BSB
Marstoa/ Excelsior
S-9Q-II Maxivent
Y 1 HP
3 A1
M/E 2195
232/176 235/212 229/156
N 1 NW 12 A1
M/E 2195
-
273/158
N 4 RVB
12 SS Elfab-Hughes RR-76 225/203 250/207
Y 1 RVB 16 Ni BSB ?
-
232/158
tY N N-N N-I Y-V N- -
M N P.Switch P.Switch
P.Switch
P.Switch
2 2 2 22
1
8 6 6 6 12 12
1 16
AP00018872
COMPANY
K
REACTOR VOLUME USG
4000
2000
SAFETY VALVES (RV) Number Inlet Size Outlet Size Orifice Area/Type/ in2
Set Pressure, psig
-
-
-
-
RUPTURE DISCS (ED) Series w/SV Number Type Size, dia.in. Material Supplier
Model Sat Pressure/Tenp.F. Set Pressure/Temp. F.
N 2 BV 3 S BSB ? 248/72 233/182
N 2 BV 2 S BSB ? 248/72 248/182
RUPTURE DISC LEAK DETECTION Pressure Guage
Vent w/Valve Free Vent Exc. Flow Valve Telltale Indicator Other
N N Y N N -
N N Y N N -
REACTOR NOZZLES FOR SAFETY RELIEF
Nozzles, No.
1
Size
6
2 2
Page 3
Page 4
COMPANY
LM
REACTOR VOLUME USG
? 5000 5300
SAFETY VALVES (RV) Number Inlet Size Outlet Size Orifice Area/Type, in2
Set Pressure, psig
1 3 4
1.8A 180
1 6 6 0/7 200
.
-
RUPTURE DISCS (RD) Series w/SV Number
Type Size, dia.in. Material Supplier
Model Set Pressure/Temp.F. Set Pressure/Tentp. F ;
yY
l1
RVB
-
36
SS Ni
Continent.Frangible
ZAP
40559
- 205/72
180/170 200/170
N 1 BV 4 Ni BSB
210/72
-
RUPTURE DISC LEAK DETECTION Pressure Guage Vent v/Valva Free Vent Exc. Flow Valve Telltale Indicator Other
Y Y
-
Y
-
-
Y i-- NNNYN
REACTOR NOZZLES FOR SAFETY RELIEF
Nozzles, No.
1
Size
3
1 6
1 4
N______________________________ O
6600
9250
3750
?
? 35,000
1 4 6 -/3.6 200
1 4 6 P/ 6 3 188
1 4 6 ? 200
1
-
-
>1 2 -6
-8
- Q/ll - 185
Y 1 BV 4 Ni BSB
210/72
-
Y N N N N N
Y 2 DV/BV 4 Ni/TFE/SS BSS
_
mii
197/169 190/169
Y N N N N N
Y 1 j
4 NiTFE
Fike 7
205/72 194/200
N 2 7 4 SS BSB 3
240/72 230/230
N 2 7 4 SS BSB 13 240/72 230/230
Y 2 Composite 6 SS OSACO COV 198/72
-
YY
YY
N N_
-N N
N_ H_
-N --Y
N 1/4" SS w 5 psig RV
11 46
12 24
27 4?
AP00018873
K. w. Latindrie xa 9/21/82
Page 5
i
COMPANY
p _______ _____________________________ _________ _________ Q
REACTOR VOLUME USG
4000
20, 000
18,000
1
32,000
21,000
SAFETY VALVES (RV)
Number
12
21
1
21 24
1 12
t 1
Inlet Size Outlet Size
6 6 66 6
88 88
6 6a
10 10 10
8
8
10 10 10 10
10 10 10
1
Orifice Area/Type, in2 18/-
11/-
11/-
11/Q
11/Q
26/T
26/T
26/T
26/T
16/Q
16/Q
26/Q
Set Pressure, psig
180
200
200
185
195
200
195
200
205
175
180
190
1 RUPTURE DISCS (RD)
j
Series w/SV
Y NYY Y
YYYY
Y YY
i Number
1111 1
1111
1 11
i Type
D
RVB
RVB
RVB
RVB
RVB
RVB
RVB
RVB
RVB
RVB
RVB
!i
Size, dia.in.
6 8 66 6
6888
668
Material
ss SS SS Ni Ni
Ni Ni Ni Ni
Ni Ni Ni
Supplier
BS
Continental
BSB
BSB
BSB
BSB
BSB
BSB
BSB
BSB
BSB
Model
BV KBA
KBA
S90
S90
S90
S90
S90
S90
S90
S90
S90
Set Pre3sure/Temp.F.
204/72
- 237/72
-
-
-- --
- --
Set Pressure/Tenp.F.
180/212 225/200 210/200 185/166 195/170 200/172 205/173 210/175 215/176 185/200 190/200 190/201
i RUPTURE DISC LEAK DETECTION
Pressure Guage
YYYY Y
YYY Y
YYY
vent w/valve
- - -N N
NN N N
N N 11
Free Vent Bxc. Flow Valve
- - -N N - - -Y Y
NNNM YYY Y
NNN YYY
Telltale Indicator
- - --
-
---
-
---
Other
-- -
--
--- -
- ---
REACTOR NOZZLES FOR SAFETY RELIEF
.
Nozzles, No.
2 3 32
2
2?
?7
2 22
Size
6/8
6/8
6/8
6
8
8?
?8
6 68
Design P = 200 pslg
Design P - 200 psig
R. W. Laundrie xd 9/21/82
APOOO18874
SZ88IOOOdV
2BJH7/1, VSDA
1<&
32
Via
ps
ruufi3A3#c/ s;a/\ vojoyay OAd
Update on Regulatory Status
EPA Vinyl chloride standard revisions under discussion with SPI. 0MB approved change to semiannual reports. Additional suits filed and Sec. 114 letters sent on emergency emissions. PMN exemption policy excludes VC, etc. Study of emissions. Including VC underway In Harris Co., Texas. Superfund reporting limits In revision, VC may stay at 1 lb. Revised Test Methods 106 and 107 published 7 and 8 September.
OSHA Comment period is closed on proposal to reopen the cancer policy - action next year? Corment period closed on revision of medical record retention rule. Labeling rule not expected until mld-83. Noise standard generally In effect. Respirator rule comnent period over. VC Training Film now available from National Audiovisual Center.
Voluntary programs now in pilot phase.
FDA Promised action on 1975 PVC proposal this October. Constituent policy comment period closed. No action on plasticizers - more tests.
Others Unpublished report suggest tumors from VAc exposure. Peroxides cause skin tumors in an 8[e) report. TCE bioassay being reviewed this month.
States Many'have own labeling, wastes, etc. rules.
APOOOI8876
EPA Settlement
Chronology
Complaint filed
Exchanged Interrogatories Draft settlement presented Justicfe-^draft Discussion Counterproposals Handshake Final
February 198 August August November January 1982 February, A June September (?)
Problems Add equipment - dropped^ Stipulated penalties for NESHAfiS- dropped. Penalt es for violation of decree^>*jJuced, classified,
Possible Sec. 120 complaint - avoided. Training - required for all, new and old.1
- Competencytest for new. Causalty - lost.
Final Version
Training, procedures (90/24,
nths for Maintenance}.
Logging of status, response
Penalties, cash and stipulated.
Time, 2 years operation or 3 years aft restart.
New equipment to be covered also.
APOOOI8877