Document wgBO7LNKNDEq8pxVBq18oJndB

ABD00055859 (conoco) Interoffice Communication To : Distribution From : S. B. Vick Date : October 8,1981 Subject; VCM LEAK SURVEY Attached are the results of the completed VCM Leak Survey. A total of 90 leaks were found.' To date, 90 leaks have been repaired. .A tabulated list of all leaks over 50 ppm VCM is given in Table I. If there are any questions or comments, please advise. Process Engineer Mike Nathan Process Engineer Process Engineer Steve Hillman Process Engineer Process Engineer tap c: CLM, CRM, PEM, RAF, SJV, AHS, VLT, VEM, MPB, JLH