January 13> 1972 MONTHLY PCB REPORT DECEMBER 1971
" H. S. Bergen P. B. Hodges B3NA
TO : W. B. Papageorge.^'' B2NK
A. W. 0. KRUMMRICH PLANT
I. CURRENT LEVEL IN SEWERS
Aroolor sewer loss control data are attached. December losses are all time low. About 12 #/day and 6 #/day respectively at Treatment Plant Influent and Effluent, Hie lower chlorinated biphenyl (called Aroclor 1221) that appeared In the sewer streams In November has disappeared about mid-December. Coin cides with production of Aroclor 1105. During the production of 1105-1109 about 20 #/day of 1221 (?) were getting Into the sewer. If we continue to pro duce 1105 It will not be possible to reach our goal of l#/day loss with the existing facilities and operating techniques.
Extensive comparison of fast vs. slow samplers, filtered vs. unflltered samples, and comparison of different points of sample pick-up In the sewer stream would Indicate the PCB content In the sewer sample to be a function of the amount of solids present. We believe the Treatment Plant Influent and Effluent samples to be most correct. Further sampling refine ments being made at these points to obtain better data.
A. Aroclor Department - Early In the month, losses varied from 0.2 to 9#/day during period when 1105-1109 was being produced. Slow type sampler not truly representative of real Idbb occurring. Did not sample second half of the month because sampling spot at (4-Z) was not available when we re-routed the sewer flow for special testing.
Extensive sewer repair work in progress In the department to betber control PCB losses within the system. Fast type sampler will be installed at department in January.
10 HI V 11
HONS 038355
-2-
A W. 0. Krummrich Plant (Cont.)
I. Current Level In Sewers (Cont.)
B. Total Plant - During the month, two areas of Investigation were conducted to better define the magnitude and the source of PCB losses to the
sewer.
1. Diversion of the sewer streams from the Aroclor department such that all department flow was directed to the North and not per mitted to flow into the internal plant sewer system which exits at the 24" and 30" sewers. This test was conducted between 12/16 and 12/30. About a 6o$6 reduction in PCB losses were noted
at the 24" and 30" sewers from the plant.
2. Slow vs. fast sewer samplers were evaluated from
12/10 thru 12/29. Fast samplers will have re sults about three times the amount measured with slow samplers.
At present, we have both slow and fast samplers
installed at the 24" and 30" exit plant sewers. The attached graphs for the 24" and 30" sewers are results taken with slow samplers. Additional refinements must be made before we switch perma
nently to fast samplers. Expect to perfect sampling procedure in January.
C. Treatment Plant Effluent - The average daily loss of 6 #/day is record low. Includes the equivalent of
2 #/day of Aroclor 1221 (?), and results obtained with fast sampler. Expect this to approach 2 #/day average when producing Aroclors 1142 and higher.
II. PROJECT STATUS
Estimate No.
2422
"Paving and Curbing" - To contain losses in tank car and storage are in Dept. 246. Curbing and
pads complete. Major sewer to be installed to North. EDC extended to 2/1/72.
3102
"Enlarge Aroclor Settling Basin" - To permit containment of possible losses in the operating
department - In progress, EDC extended to 2/1/72.
HONS 038356
-3-
A. W. 0. Krummrich riant (Cont.)
IX. Project Status (Cont.)
(Estimate No.)
3^38
"Eliminate Underground Sewers 246" - Alter and repair departmental sewer system to eliminate cross flow of sewer water and underground water within the department. Essentially complete.
3500
"Repair Sewer and Paving in Second Street" -
To eliminate cross flow of sewer water and under ground water in area. Estimate approved. Design to begin week of 1/10/72. EDO 4/1/72.
III. PROGRAM STATUS
Isokinetic samplers to be installed at Treatment Plant Influent and at Department (4-Z).
Definitive longer range plans to be prepared in January. Did not do in December.
B. ANNISTON PLANT
I. CURRENT LEVEL IN SEWERS
Total Aroclor losses during December 1971 averaged
0.72 lb./day (73 PPb). The Aroclor (1242 and 1254) losses reported to the E.P.A. and the State of Alabama
averaged 0.37 lbs./day (37 PPb). This 0.4l lbs./day Increase in total Aroclor losses in December over
November is a result of being forced to change back to the #2 limestone pit because of a lining failure in
the #1 pit.
II. PROJECT
No changes from November.
III.SPILLS
There were no Aroclor spills in December.