R. C Herman - (6725) - General Offices
May 5, 1969 Status Review of CEA 1430
cc R. A. Haydel - Anniston CV*-.- Faulkner H. L. Williams H. E. Waldrep
R. M. Kountz R. R. Cook L. R. Burchfield J. B. Phifer W. L. Schuchat R. H. Henning R. W. Peterson
The following events have occurred since our meeting on Wednesday, April 30, 1969.
1. Dust Collection
As of Friday, May 2, 1969, there has been no pluggage of the dust collection system. (Successful operation since April 26, 1969). The float vlave has been modified for more reliable operation. All tracing and insulation required by the new ductwork has been completed. Mr. Faulkner has been alerted as to the necessity of keeping the three sumps drained1of eutetic. On Friday, May 2, 1969, the Plant drained the large sump at the rotoclone and collected between 2 and 3 gallons. CED construction has not received the drawing for the trench and curbed area. Bill Schuchat will check on this.
2. Biphenyl Temperature Control
The new therminol system (inside the warehouse) will be installed by the plant, as per an agreement with Lamar Faulkner. J. Arnold will mail 4 sets of drawings and sketches to L. Faulkner today. The Plant will purchase the pipe and valves, CED has purchased the pump, control valves, and the TIC. CED Construction will deliver these items (CED Purchased) to the Plant when they arrive.
3. Aroclor Flakers
CED construction has delivered the deflector plates (for the drum ends) to the Plant for their installation. This concludes CED work on the flakers.
4. complete
0367124
TOWOLDMONOQ44777
CEA 1430
-2-
May 5, 1969
5. Complete
6. Complete
7. Modify North Truck Docks to Provide Adjustable Steps
Adjustable steps should arrive by 5/15/69.
8. Installation of Drumming Scale
This installation is complete, except as follows:
a. Provision of manual filling valve - (P.O. 1430-9-0192) b. Provision of interlock to prevent movement of pallet
conveyor during filling cycle - this will be complete 5/5/69. c. Provision of manual printing of weight. Expected completion 5/8/69.
The Plant has requested an interlock to prevent the lance from being raised from the drum before flow is stopped. This feature is provided for automatic filling but not for manual filling. Interlocks would be needed for each size drum. CED feels that these interlocks should not be added because manual operation would be used only to complete the days work if there were a problem with the automatic system. Interlocks could render the manual system inoperative also. I have discussed several methods of manual operation with Lamar Faulkner that would minimize any potential problem iii this area.
9. Installation of Clay Oven
This oven will be available for operation on May 6, 1969. Temperature will be limited to 250F until the correct controller (250C) is installed. This controller changeout will be complete^ before May 9, 1969.
10. Insufficient Air Supply
CED will provide a plant air system for the warehouse. The compressor selected is a joy "twist-air-screw compressor". At L. Faulkner's request, vendor's data was sent to him on May 2, 1969 for Plant review.
The next Status Review will be held Wednesday, May 7, 1969 at 8:10 a.m. in Room F2E-103.