Document vBZd1j4KjLb7LxmN2dG3bV5Z
COMPANY CONFIDENTIAL
Anniston
C. K. Kastman A. J. Koenig J. C. Landwehr A. E. Lelsy C. W. Miller W. B. Papageorge W. F. Taffee H. L. Williams
General Offices
H. S. Bergen J. 0. Bright H. C. Cerder D. E. Cayard D. Danna (3) L. C. Fuhrmelster H. 0. Hehner D. B. Bosmer R. E. Howard R. M. Kountz W. A. Kuhn C. F. Luecke H. L. Payton W. R. Klchard N. L. Sample A. J. Stratmeyer H. S. Trail J. H. Zwemer
Anniston Plant
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Summary August, 1968
Cost Improvement Results For First Eight Months
Estimated Actual
Target 1 of Target
Month
$21,150
$49,955
42.5
YTD
$369,940
$310,570
99.6
Organic Division
Solid Aroclor still level indicator-alarm project approved verbally for $8000 instrumentation. Total NFC $14.9 M - savings $63.2 M.
South Second St.
Two Montar handling projects forwarded for approval In August. NFC $20 M with expected savings of $24.2 M.
0. DeGarmo M. E. Gibbs J. F. Quinn J. R. Savage - JFQ
Other Locations
D. B. Edwards - DR A. B. Forsten - CB J. W. Graves - Lullng D. W. Jackson - NGK W. R. Kellogg - Nltro R. C, Swanson -
Sesttle J. F. White - Everett
Ssntowax R column project approved verbally for $3500 Instrumentation.
Received formal notification of January 1, 1969 target
to discontinue manufacture of Chlorine/Caustic at
Anniston. May be delayed past January to provide ad-
quate tank car unloading and distribution facilities
now In design on CEA-I83I,
,
Staley Grade HC1 via activated carbon treatment studied and reported by Pittsburgh Activated Carborv. Labora tory scale recommendations will be tested on plant scale with final recommendations targeted for October.
PNP reactor optimized at 175C. and 66 minutes. This time represents approximately a 6U decrease In cycle time. Reactor agitator and pressurization of charge
tank will be studied in September. 0346350
.
CONFIDENTIAL INFORMATION
.
confidential Information which U (ha property of Monsanto Company. Only those portions of'the document relevant to a
duly etfthorttkd flndlvlduat'* pood to know may be eicerpted for him. The report must not be sent outside the Company without written approval end
he Pirtherfiedepclpfent is accountable far fts eafe keeping, excerpting or otherwise disclosing of Its contents end for its proper disposal. The docu*
* menf femdlartye property of Monshnt Company end shall be returned within two months to Its author, except upon special authorisation to hold for a longer period."
`
TOWOLDMONOQ44446
Agricultural Division
Company Confidential
2.
Plant tests on experimental Sulfur Recovery unit are underway - scheduled for mid-September completion. Centrifugal separation looks good to date.
Fume Collection System 95% complete with start-up targeted for week of September 16.
Engineering Design and Services
Transmitted design packages for winterization of Nlran safety 6howers, plus several minor ones. Completed pre-startup checkout of Instrument and electrical Installations on the sulfur recovery pilot plant and the Nlran fume collection system. Forwarded project premises for water and sewer system projects.
Utilities Cost Improvement
Project premises have been Issued to collect sewered water In PNP and Aroclor departments. NFC $8M with expected savings of $4.2M.
Plant Improvement
Design packages for Nlran Storage Tank Dikes, and two minor Jobs were transmitted to maintenance.
AFE forwarded covering surfacing, curb and gutter on Fifth and Duncan Streets.
Liaison
Warehouse office complete; flushing of lines and tanks with Aroclor 1242 started by Production. Insulation Incomplete because of Insulator's strike.
Roof of warehouse complete, siding installation started but going slowly; flakers set. Warehouse section occupancy date will be controlled by siding Installation about October 1.
Installation of 300 M gallon Benzene tank started on CEA-1892.
Design of facilities to handle liquid chlorine from tank cars underway on CEA1831.
Waste Heat Recovery
Progress report covering final phase issued August 21. Unit Is being placed in stand by condition for next three months.
Pollution Control
Two atmospheric pollution complaints were received and handled in August.
Malathlon waste studies complete. Malathlon reduction was 997.(+) In the pilot unit. This Indicates that malathlon waste can be effectively treated in our waste treatment plant. Final report targeted for September.
0346351 Quality Control
The RFT Index was 98.7 with 8 lots rejected out of 635; 8 out of 540 from the Organic Division. The Quality Score declined to the lowest level of the year, from 96.5 to 92.2, due largely to divergence in liquid Aroclors and Muriatic Acid.
TOWOLDMONOQ44447
240,000 200,000
i.<o, ooo
... il 19.6.8_ TSD COST IMPROVEMENT
_
1! YTD RESULTS VS ANNUAL TARGETS
? } 100,000
.
f
.
j
80,000
'
.
120,000
80,000
40,000
...
v*> O-
A?
-y -4
. .-3
k
z
<
QC
60,000 40,000
20,000
VOT'TM-'--
"T V
71
,.,a
TOWOLDMONOQ44448
Company Confidential
TOWOLDMONOQ44449
AROCLOR
Company Confidential E. E. Bowles, C. R. Mcllwain, D. A. Self, (V. R. Haupt)
3.
Cost Improvement
Month
YTD
Target $16,630
Actual
75*
$32,580 $25,435
Making solids on liquid system plus unusable liquid still revision
ISP Objective B-8(a) Evaluate Ouaternhenyl-Polyphenvl Effects on Solid Aroclor Yields.
Received verbal approval for $8000 on project 3015 to purchase radiation instruments. Instruments will measure specific gravity on the chlorinator end still receiver and also provide a low level alarm on the still. Total Total project cost will be $14,900 NFC and $900 expense. Savings claimed are $63,200/yr.
TSD Job No. 398 - Liquid Still Revision for Thermlnol Heating
No. 2 still was converted to Thermlnol heat supply. Pressure drop problems developed in Thermlnol system and resulted in unacceptable production rate. The still will be converted back to original heat supply. The main Thermlnol system containing 22 branches is being analyzed to decide what must be done to improve existing system and take care of future needs.
TSD Objective for 1969 - Montar Handling
AFE 2952 has been issued for approval to provide for pumping of Montars to the Montar pit. NFC is $10M with $13M savings.
AFE 2949 has been Issued for approval to provide for flaking Montar 5. NFC is $10M with $11.2M savings.
BIPKENYL-SANTOWAX
W. G. Niemeyer, J. W. McGee, (V. R. Haupt)
Month
YTD
Target $3,550
$30,150
Actual $4,990
$80,675
TSD Objective B-7(a) Debottleneck Biphenyl Stills to 87.6 M Lbs./vr. Biphenyl Rate Bv 2/69.
This work has been included in CEA-1892. CED and the plant are planning a capacity test run during the week of September 9 to firm up scope in this area.
TSD Objective B-7(c) Provide Assistance (Liaison) to CED As Necessary On Project To Upgrade No. 1 Furnace. CEA-1892.
Field construction is underway. Foundation work is in progress on dike wall for new benzene storage tank and footings and slab for new preheaters.
0366366
TOWOLDMONOQ44450
BIPHENYL-SANTOWAX - continued
Company Confidential
4.
TSD Objective B-l(a) Revise Biphenvl-Santowax Manufacturing Improvement Plan Bv
Rough drafts of all sections are complete. Review and revisions are in progress
Quality
TSD Objective B-7(d) Demonstrate Quality Improvement on Santowax Still via Addition of Eight Tray Column.
Received verbal approval on 8/22/68 to order long delivery equipment and in strumentation ($3500) for proper control of this column. Working with CED on their part of column auxiliaries.
CHLORINE
D. W. Dudley, G. L. Moore, (D.
Month
YTD
Target Actual
$2,625 $715
$33,375 $55,865
Comment
The Anniston plant was notified on 8/14 of the decision to shut down the Chlorine Plant by 1/1/69, or as soon thereafter as possible. TSD effort is being concentrated on shutdown preparations.
TSD Objective B-6(a) Monitor Mercury Usage by Radioactive Inventory
Thirty-one cells were spiked and samples forwarded to Organic Research for measurement. Determination and publication of results should follow in September.
TSD Objective B-6(b) Develop Program to Reduce Mercury Usage to 0.75 lbs. He/Ton Chlorine.
Mercury wash tank was delivered 8/21/68. Maintenance is scheduling installa tion for September.
TSD Objective B-6(c) Assist in Demonstration of Brine Dechlorination by 4/1/69
No change in status. Demonstration will follow maintenance revisions.
Process
TSD Job No. 328 Titanium Brine Heat Exchanger (Savings $2.500)
Project for reducing steam temperature was transmitted to maintenance for installation 8/14/68.
o3i,b3^
TOWOLDMONOQ44451
CHLORINE
continued
Company Confidential
5.
ISP Job No. 860 Central Chlorine Unloading
Plant goals and objectives for liquid chlorine handling and distribution faclll ties were defined and transmitted to CEP. Final project scope Is targeted for 10/15.
TSP Job No. 861 HB-40 Hydrogen Study
Objectives for this job are:
a) Pefine and report catalyst penalty for using untreated Biphenyl _ hydrogen at HB-40. Catalyst penalty would be $28,000/yr. plus a 4 M lb./yr. HB-40' capacity losses. The penalty was defined by company standard batches of HB-40 versus batches of HB-40 produced from Biphenyl hydrogen in a laboratory autoclave.
b) Pefine catalyst poison and propose means of reducing effects. The poison has been defined as carbon monoxide. Carbon monoxide Is pre sent in small percentages ranging from 2-107.. A means of reducing the carbon monoxide concentration Is presently being tested in the laboratory.
TSP Job No. B54 Chlorine Backflow Prevention - Safety
Project 2955 ($2,500 NFC) was estimated and approved for prevention of chlorine backflow from Aroclor to the chlorine plant. The project is scheduled for final design and drafting In early September.
HC1 K. J. Buturla, G. L. Moore, (P. C. Malm)
Cost Improvement
Target
Month $1,050
YTD $2,550
Failure to meet the month's target caused by hold-up on installing HC1 storage tank
Actual
$700
$1,900
TSP Objective B-10(a) Remonstrate Reduction of Unaccounted HC1 Losses to UK, of Total HC1 Available.
Recycle line project in maintenance backlog. No action.
TSP Job No. 497 Muriatic Acid Storage
With the shutdown of the chlorine plant, and the installation of a new central tank car unloading facility, chlorine tank cars will no longer be unloaded in the immediate area of the new KC1 storage tank. A decision has been made to change drawings and relocate the tank to the original site. Work will begin on the new drawings to construct the tank at the original location about Septem ber 1. All construction work will be halted until the design can be prepared. Package transmittal is targeted for October 1, 1968.
0346356
TOWOLDMONOQ44452
HC1 - continued
Company Confidential
TSD Job No. 801 Enable Routine Production of Staley Grade Acid
6.
The study to determine how to produce Stslev Grade HC1 is continuing. Pitts burgh Activated Carbon Laboratories have completed tests on Anniston HC1 and have written a report which indicates our carbon towers should be capable of removing organics. New tests are planned for verification of results in our HC1 plant. A coalescing separator filter is also being given consideration in solving the problem. Efficiency and economic evaluations of the alternatives will be made. Final recommendations are targeted for early October.
PNP 0. J. Norris, K. J. Buturla, (D. C. Malm)
Cost Improvement
Month
YTD
Target
$16,500
$95,000
Actual
$6,000
$45,250
TSD Objective B-9(a) Assist in Demonstration of 20 M lbs./vr. Rate
Charge tank pressurization study indicated a 7 minute reduction in reactor cycle time is possible by pressurization and preheating raw materials. A project will be forwarded for approval by 9/10 to make the necessary modifica tion. If successful, this change will increase capacity to 22 M Ib./yr. Add! tlonal work in September will be aimed at a study of reactor agitation in an effort to Improve heat transfer rate and reaction rate.
TSD Objective B-9(b) Increase Reactor Temperature (9/1/Target)
Field tests at 175C. successfully completed with a 4 minute reduction in re action time. New reactor rate is now 1.78 M pounds per month based on a 66 minute reaction time. August production (1.66 M) below expected because of unusual repair downtime.
TSD Objective B-9(c) EVOP Study of Molar Ratios NaOH/PNCB
Test program will be outlined with production by 9/10 so that field tests can be started by 9/15.
NIRAN
K. G. Hale. 0. J. Norris. D . W. Dudley, J, L. Gaines, (D. C. Malm
Cost Improvement
Month
YTD
Target Actual
$22,175 $8,300
$115,275 $95,850
0346357
TSD Oblective B-5(a) Demonstrate Parathion Recovery ($70.000/vr. Yield. Savings + 10-15% Reduction in COD Loading)
Metal edge filters were removed and cellulose filter test unit Installed. Filter tests were begun but were Interrupted by feed pump failure - test to re sume in early September. August test of cellulose filter lasted two hours with
no build up of solids on filters as experienced with metal edge filters.
TOWOLDMONOQ44453
NIRAN - oontinued
Company Confidential
7,
TSD Objective B-5(cl Demonstrate Solvent Addition to Residue (Interim! Proceaa ' Bv 6/1/68 ($59.000/yr. Yield Savings')
Yield aavings of $8300 were obtained in August. Phase #3 tests (increase Cl2 level) were stopped in late August by production. Yield losses of $6000$8000/month are expected if Cl2 level is dropped back to 10$ average.
TSD Objective B-5(d) Evaluate Sulfur Recovery from Residue by 7/1/68 ($400.000/vr. Savinas 4- 317. Reduction in SOo to Air
Experimental recovery tests are approximately 607. complete. Results to date Indicate 907. recovery of solids with a dryness of 80-93% solids in cake depending on centrifuge condition. EDC for tests 9/15.
PR&D work on process continues. Completion of process is now expected during
10/68.
TSD Oblective B-5(el Demonstrate Reliability of Submerged Pump for R.I. Control of Chlorination
Temporary replacement of light source Installed. Tests will be resumed upon completion of repair work to circulation line.
Safety
s TSD Oblective A-10
Eliminate High HaS Pressure in Thlo Acid Reactor bv Demonstrating Temperature Controlled Alcohol Addition
Trial run completed by production with excellent control results. Alcohol addition time averaged S minutes/batch longer than on manual control. A progress report will be Issued in November.
TSD Objective P-10 Assist in Demonstration of Fume Collection in Parathlon Department
Construction completed 8/29. Water system checkout completed 8/3O. Startup will be delayed until old incinerator stack fan bearings have been replaced. Start up now scheduled for week of 9/23.
TSD Job No. 815 Survey Water Savings Potential in Parathlon Department
Design of experimental project ($3,700/yr. savings) to re-use water from wash columns at pre-washers will be transmitted by 9/6. Progress report covering survey of water savings potential was Issued in early August.
K. G. Hale, (D. C. Malm)
Cost Improvement
Month
Target
0
Actual
0
YTD 0 0
o3i, b3^8
TOWOLDMONOQ44454
PgS5 * contlnued
Company Confidential
8.
Safety
TSD Objective A-15(a) Provide Design to Reduce Fumea in PoS^ Working Areas by 4/1/68 at Surge Tank Vent
Project transmitted to P & S on 8/5/68.
ENGINEERING DESIGN AND SERVICES
.
Mechanical/Electrical/Instrument Design and Drafting
J. C. Price. J. A. Veazev. R. L. Brewer. J. K, Rennie. (W. F. Taffeel
Highlights
Review drawings were issued for Emergency Escapeway at Nlran Foremen's Office, Emergency Escapeway and Reactor Dam at PgS^, alterations to wash piping at Nlran, safety shelter @ PNP, and slurry valves at Nlran. Revised drawings were issued for the Nlran Fume Collection System and #9 chlorinator pump and piping. Final drawings were issued and design packages forwarded for Hourly Parking Lot Lighting, Alarm on Fire Hater System, Power Distribution Panel for TSD Annex and Nlran Safety Showers. Forwarded premises for corrosion protection of 20" City Water Main and Sewer, to collect acidic spring water and HC1 loading dock drainage. Assisted In checkout and startup of the Nlran sulfur recovery pilot plant and the Nlran Fume Collection System. Design, construction and liaison services were provided for sixteen (16) other jobs during the month.
Objectives
There has been no change in status of objectives except as reported below:
TSD Objective A-5 Winterize Safety Showers '
Design package for Nlran showers (Project 2770) was transmitted to maintenance on 8/15.
TSD Objective A-6 Procedure for Electrical Testing
Forwarded report defining problem and scope. Plan to meet with maintenance to establish responsibilities and work plan In September.
UTILITIES COST IMPROVEMENT
J. C. Price, A. I. Hale, L. 0. Chambers, (W. F. Taffee)
Evaluation of a preliminary survey conducted In July indicates potential savings of about $200,000/yr. in the cost of utilities for the Anniston plant. Pre liminary estimated capital cost to obtain these savings is $325,000.
Progress reports on steam metering, water metering and program plans were forwarded for typing. Forwarded project premises for approval and AFE's for review on re-use of sewered city water at PNP and re-use of sewered tower water at Aroclor. Net savings at these projects will be $4200/yr. AFE's for water meters In Nlran and Organic Division steam meters were forwarded for approval. AFE's for Organic Division water meters and a gas meter at Biphenyl were for warded for review. Started evaluation of treatment for Biphenyl cooling tower to reduce or eliminate scaling of the tempered water cooler.
0346359
TOWOLDMONOQ44455
PLANT IMPROVEMENT'
Company Confidential G. C. Goodwin, (W. F. Taffee)
9.
Design packages forwarded to maintenance covering Nlran raw material storage tank dikes, upgrading chlorine lunchroom and revision of shipping office. Forwarded AFE's for resurfacing Fifth street east from Cls railway to new warehouse, Duncan street from fifth to sixth streets, and upgrading lights along Fifth street west side of plant.
CEP LIAISON
V. T. Langdon, (W. F. Taffee)
CEA 1450 - Aroclor Expansion
Training of operators on tank farm completed by L. L. Faulkner. Flushing of system and all other activities in the field will be carried out by Production. Insulator's strike has delayed insulation completion and our ability to handle anything higher than 1248. Flakers set in place, roof and siding of flaker "penthouse" remains to be completed. Approval received for pallet dispenser variance.
CEA 1452 - Warehouse
Installation of roof completed, siding Installation progressing slowly. Pre sent prediction is that warehouse will be ready for occupancy by September 23. Construction of Sixth street to serve warehouse and tank truck docks nearing completion. Sprinkler installation underway at months end.
WASTE HEAT RECOVERY
C. E. Woodward, (W. F. Taffee)
Progress report covering experimental observations obtained for Phase III published 8/21. Report contains test results for modified equipment. Special emphasis was made to compare performance of the test unit during periods of 1) normal fluctuation in #8 boiler firing rate and 2) during periods when the firing rate was held constant. Additional results for Brink and Selas Therminol recovery test units also Included.
Actions to place the test unit in a stand-by shutdown delayed one week. Equip ment and piping drained of Therminol and water inventory. Expect to complete shutdown 9/5.
POLLUTION CONTROL
E. G. Wright, (W. F. Taffee)
TSD Objective F-3 Establish a Monitoring System for Air Effluents from the Plant
Thirty-six atmospheric samples were collected and analysed for S02 in August. Will begin sampling at a second point as soon as Instrument shelter arrives.
TSD Objective F-5 Publish a Newspaper Article to Further Community Understanding of Pollution Abatement Problems.
An article will be published in the plant newsletter during September. A pro gram to invite local political figures and newspapermen in the plant is being worked out with the Plant Manager and the Personnel department.
0346360
TOWOLDMONOQ44456
POLLUTION CONTROL - continued
Company Confidential
10.
TSD Objective F-7 Investigate Installing Permanent Monitoring Device on Choccolocco Creek.
Potential sites still being Investigated.
TSD Job No. 808 Install Solids Removal Equipment at Waste Treatment.
November IS is target date set by maintenance for installation.
TSD Job No. 864 Effluent Task Force.
Issued a memo outlining a method for controlled caustic sewering. Also issued recommendations of repairs required to the HC1 neutralization pit.
Special Activities
1. Collected samples at Paul Hodges request for Research to begin their in vestigations of Aroclors in Snow Creek.
Waste Treatment:
All wastes were effectively treated in August. Average values for Monsanto effluent in August are as follows:
Average Dally
Specifications
PNP COD Parathion BOD
1.0 PPM
100 PPM .11 PPM
1.0 PPM
-t-5 PPM -c200 PPM
^1 PPM -c.200 PPM
PROCESS AND QUALITY
J. P. Chadwick, (W. B. Dunlap)
TSD Objective C-2 Apply Statistical Control to Solid Aroclor Process
The plant experiment designed to verify predictions of the computer study reported in July continues to show a 5-7% improved yield. The test is continuing.
TSD Objective C-6 Correlation of PsS,. -Parathion Operations
Still controls were found to outweigh all other variables studied. No prolonged yield changes were revealed which could be expected to relate to upstream units. Work on this phase of the study will be completed in September and a progress report written.
Procress Improvement Plan for PNP
A quality control and process surveillance section was contributed to the Manufacturing Improvement Plan for Paranltrophenol.
03Ab*>V
TOWOLDMONOQ44457
Company Confidential
11.
COMMUNITY RELATIONS., PERSONNEL. RECRUITING. AND DEVELOPMENT
Development
1. Cliff Woodward attended the ASME/AIChE Joint Heating Transfer Conference held in Philadelphia, Pa., August 12-14; he assisted in a Paper which he coauthored with D. E. Steinmeyer of CED.
Recruiting
1. Lee 0. Chambers, Co-Op, was hired August 26. He attends Auburn University.
Visitors
1. Mr. Carl R. Martinson, CED Specialist in "L" Standards for Painting, visited the plant August 30. A special consultation was held with Maintenance and TSD.
2. Mr. Elwood Robinson and Mr. G. Huchannan, Lion Oil El Dorado, visited August 13 to discuss electrical test procedures for insulating fluids.
Public Relations
1. Mr. J. C. Landwehr attended the Associated Industries of Alabama Water Pollution Task Force meeting held at Mobile, Alabama, August 14.
q3*63<>2
TOWOLDMONOQ44458
PROCESS IMPROVEMENT
Company Confidential
DISTRIBUTION OF TIME BY TECHNICAL SERVICE Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec.
NEW PRODUCTS
PLANT IMPROVEMENT
ASSIST OPERATIONS
SPECIAL ENGINEERING SERVICES
TECHNICAL MANPOWER
MISCELLANEOUS ACTIVITIES
AND ABSENCES
Jan. Feb. March-Apr. May June July Aug. Sept. Oct. Nov. Dec. 03A63b3
TOWOLDMONOQ44459
uompany uoniiacntiai TSD PROJECT SUMMARY
IN MAINTENANCE COMPLETED
NOT CLOSED
PROJECTS SUBMITTED
FOR APPROVAL
APPROVED PROJECTS IN TSD
TOWOLDMONOQ44460