Monsanto Enviro-Chem Systems Inc Corporate Square Office Park Bo* 14547 St. Louis. Missouri 63178 Phone: (314) 694-1000
March 20, 1978
Mr. R. H. Hunt ASARCO, Inc. P. 0. Box 1111 El Paso, Texas
79912
^0 /SVj:A,Y,
%
Reference: Subject:
17H 0711
EA-26EP-NY3951* PLT. 623 MEC Letter No. 2102-216 GENERAL CORRESPONDENCE ASARCO File No. 8.1
Dear Rod:
This confirms the results of our meeting of `-'.arch 1*J, 1975 concerning the delayed start-up of the acid plant.
Personnel Present:
ASARCO
MEC
R. H. Hunt C. Glasser
J. L. Serra-Jones W. K. Wood
The following points were discussed:
1. The start-up of the acid plant will new be October 1, 1976. /
2. ASARCO and Enviro-Chem (MEC) will agree upon a mechanical
completion date, which will be considered as the date at which initial operations would have begun had the start up not been delayed. At that date, all items described in Exhibit C,
Paragraph A-l, "Completion of Construction", and Exhibit C, Paragraph A-2, "Commissioning", will be assumed to have been completed. This date is now projected to be April 1*1, 1978.
3. A similar completion date will be developed for the decolorization area.
*1. MEC, with ASARCO's concurrence, will develop a list of items which will have to be completed before plant is started up. Some examples are Installation of catalyst, hydrostatic testing of lines, etc. This list will be used to determine the estimated
ASARCO ELP 0008022
Mr. R. H. Hunt
-2
JLS-J March 20, 1978
final cost of the project, any adjustments to be made to the guaranteed maximum, and the lead time necessary before actual start-up.
2 5. It is assumed that the normal time lapse between initial
^ operation and plant acceptance. This is for the purpose of ' determining dates that final payments are due.
6. ASARCO will pay MEC the savings participation, fee adjust-
f ments due to variation orders and all accumulated retention to the acceptance date. ASARCO will retain any fee payment due after that date under contract Exhibit E, "Fixed Fee Payment Schedule".
7. Enviro-Chem will extend its catalyst and performance guarantees from the new start-up date and will recommend which major pieces of equipment should have their guarantees extended. MEC will also make preliminary contacts with those vendors to try to extend their guarantees.
8. Enviro-Chem will prepare a "mothballing" procedure specific to this plant, and ASARCO will be responsible for maintaining the plant during the idle period in accordance with that pro cedure. A copy of a typical "mothballing" procedure was given to Mr. Hunt for his information.
9. Enviro-Chem will require the execution of a formal addendum to the contract, signed by an officer of MEC, setting forth the above. A copy of a typical agreement was given to Mr. Hunt for his consideration.
10. Although no specific time was set for the completion of this agreement, it must be completed by April 14, 1978, which is the current projected mechanical completion date. In order to accomplish this, the punch list described on Item 3 ana the procedure required on Item 8 will be completed by April 3, 1976. Concurrence by ASARCO on the wording of the agreement described on Item 9 should be completed no later than April 10, 1978.
The above covers the main points discussed during the meeting. If you have any comments or suggestions, please do not hesitate to contact me.
Very t
j cc: ASARCO
Salt Lake City E. H. Haug/W. T. Sweat M. L. Leary W. H. Mahoney
J. L. Serra-Jones 'i
Senior Project Manager
El Paso W. Kelly C. Glasser
MEC D. R. Bounds D. L. Chapman
H. E. Crow G. H. Crozier
J. L. Serra-Jones W. K. Wood