ENCLOSURE 4
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY WASHINGTON, D.C. 20460
OFFICE OK PESTICIDES AND TOXIC SUBSTANCE:
John D. Wynkoop Director of Water and
Water Pollution Control City Hall-Eighth Floor 455 North Main Street Wichita, Kansas 67202
Dear Mr. Wynkoop:
Administrator Ruckelshaus has asked me to respond to your letter of April 27, 1984, in which you expressed your concern over the Environmental Protection Agency's (EPA) intention to propose a ban on asbestos-cement pipes.
In .spite of previous ongoing regulatory efforts, asbestosrelated health hazards continue to be a serious problem in the U.S. Therefore, EPA is working on a proposal that would eliminate the use of asbestos in virtually all products over the next 10 years in a two-phased approach. In phase one, EPA's Office of Toxic Substances (OTS), would propose a rule under the Toxic Substances Control Act (TSCA) in July 1984, to prohibit the importation, manufacturing and processing of four asbestos products for which substitutes are now readily available.
These products accounted for about half of the asbestos consumption in 1981. They are: saturated and unsaturated roofing felt: flooring felt and asbestos felt-backed sheet flooring; vinyl-asbestos floor tile; and asbestos-cement pipes and fittings. These products were chosen because they are large-volume uses of asbestos, and the availability of substitutes can be easily documented. Additional categories of products which pose a disproportionately high risk of disease compared with their volume may be added. This action would have an immediate and significant impact on the asbestos hazard.
In phase two, OTS would propose a rule under TSCA in October 1984, to reduce the total amount of asbestos imported and used in all other applications and eventually eliminate most uses of asbestos through a staged phase-down rule over a 10-year period.
CAPCO JEN 0031934
As you correctly point out, our risk assessment is based on inhalation, not ingestion of asbestos and we have emphasized this in our .drafts of the proposal. Accordingly, at the present time,'we envision no circumstances under which removal of asbestos-cement pipes would be required.
-.1 must emphasize that this proposed action is presently in draft format at this time and may very likely undergo further changes between now and any future date of announcement. X have instructed our TSCA Assistance Office (TAO) to notify you promptly at the beginning of the 60-day comment period following the announcement of the proposed rule, so that your views will be considered before any final ruling is made.
Sincerely yours.
John A. Moore Assistant Administrator for Pesticides
and Toxic Substances
i
i
CAPCO JEN 0031935