Document rx3QeN3Byx2OvNrY3RYjb5Z8J

i4)CX Subject: November 5, 1979 Kelsey Hayes/VM Requirements wlamor-r.dum From: To: E. F. PottS BJ Iwarsson As we discussed last week, I Indicated that our releases for this customer have not afforded adequate leadtime for Winchester to procure raw materials from Europe and for us to advise A.L. Hansen on disc brake back requirements. The A.F. Schmaltz letter of 10/30/79 on this subject (attached) indicates that the customer suggests, that we procure raw materials and steel to cover approximately 40,000 inners and 40,000 outers per month for the first 6 months of 1980. Please advise if this letter can be used as try authorization to procure raw materials and to contact A.L. Hansen Division for our raw material requirements. EFP/dh Attachment cc: R. L. Cutler r P. H. Grim A. F. Schmaltz D. Sedlock J. C. Thomas, III E. F. Potts SCI 01151