Document rp8Bk41NKNLQB8Xv4x0gVR7Vq

rc *1 Of: W. M. Lumb (6037) Corporate Engineering - G2WA December 5, 1975 Santosol Dielectric - CEA 3023 Evaluation Cost Estimates cc D. W. Caldwell-G2WC C. P. Orr -G2WD J. E. Downes 1. E Gibbs A. J. Koenig R. A. Pohl D. Wood - G2WA - W1A - B2SK - B2SB - B2SD The attached table shows the evaluation cost estimates developed for the three major cases for capacitor and transformer fluids. We have also included a fourth case ("D") which initially appeared to offer some cost advantages over the other cases. '' The Table shows the total new capital dollars required for each process (S-100, MIPB, LD, etc) at Delaware River and Krummrich. The total dollars for each unit includes the cost of facilities specifically required for a particular process as well as part of the cost of "shared" equipment and utilities. For this reason, deletion of a process unit usually does not reduce costs by the entire amount of capital shown as the cost of the unit. Each site will require a utility expansion of $450K if a manu facturing unit is installed. The $450K primarily includes a "minimum size" (2000 GPM) cooling tower which is adequate to supply all the new process units. Case A at WGK includes only one utility expansion (cooling tower) but Case B includes a cooling tower at AGK and at DR. The Delaware River cooling tower therefore is only about 25% loaded. Case D is similar to Case C except that Case D includes only one reactor for both S-100 and MIPB. This reduces the production capacity to about 75% of the base rate. Case C has two glass reactors and can produce material of the base rate. The comparative costs of the different process units are affected by the amount of existing equipment available as well as the degree of equipment and utility "sharing" that is possible. For example, the S-100 facilities at D.R. cost more in Case B than in Case C because "B" cannot share utilities or equipment with the other units at WGK. In another example, the MIPB facilities in Cases A and B cost less than in Cases C and D primarily because WGK has a large amount of equipment available for use in the manufacture of MIPB. And finally, the MCS 1839 DSW 185332 STLCOPCB4051578 J. E. Downes, et al December 5, 1975 Page 2 facilities at WGK cost less in Cases A and B than in Cases C and D because MCS 1839 can share equipment with MIPB. Cases A and B have MIPB at WGK but Cases C and D manufacture MIPB at Delaware River. The future requirements for S-100 appear to be somewhat questionable. The S-100 unit in Case B is the only new process at Delaware River and obviously can be deferred without affect ing the other units. The Case A S-100 facilities at WGK are integrated to some extent with the other new units at WGK. However, S-100 could be deferred and added at a later date by providing capacity in the equipment commonly used with the other process units. This would reduce the cost of Case A by about $1,90OK. The costs do not include funds for waste disposal but we are working with the environmental control group to develop waste handling information. The costs developed here are based upon preliminary process information available and can significantly change as detailed information is developed from Research. A meeting is scheduled at 8:30 AM on December 8 in B-291 to discuss these costs and other information required for the economic evaluations. J> W. M. Lumb L /cr DSW 185333 STLCOPCB4051579 TABLE 1 SANTOSOL DIELECTRIC-CEA 3023 CASE EVALUATIONS DESCRIP. S-100 MIPB TXS LD MCS 1839 CAPACITY (14 M PPY) (11 M PPY) ( 3 M PPY) ( 3 M PPY) ( 6 M PPY) A 2160 (WGK) 1330 (WGK) 3900 (WGK) 610 (WGK) 650 (WGK) CAPITAL $K BC 1950 (DR) 1325 (DR) 1450 (WGK) 3130 (DR) 3980 (WGK) 4035 (WGK) 630 ' (WGK) 645 (WGK) 690 (WGK) 920 (WGK) D 675 (DR) * 3175 (DR) * 4035 (WGK) 645 (WGK) 920 (WGK) CAPITAL TOTAL $K EXPENSE TOTAL $K 8650 1400 8700 1300 10055 1300 9450 1380 * a. S-100 and MIPB rates are 9 and 11 MPPY respectively b. Each site includes a $450K utility expansion c. Costs are 25% d. Expense costs include about $320K for dismantling, relocation and contamination of Aroclor area at WGK. e. Costs do not include capital for waste disposal. OS'N STLCOPCB4051580 ANNISTON POLYPHENYL DEPARTMENT Capacity 90M lbs/year Current Requirements ca. 37^ lbs/year Capital (M&E): Gross $3,024M Net $ 390M Fixed & Budgeted Costs Total Mfg. Budget & 2M/year S 8M/year ANNISTON HB-40 DEPARTMENT Capacity 27M lbs/year Current Requirements ca. l4M Ibs/year Capital (M&E): Gross $ 713M Net $ 222M Total Mfg. Budget $ 3^/year p 0 i b P; RE. E 8 = 6 8 C 8 - i ;P: Pi 1. P; M SL E S 0 a 0000+ 'Pi 3 0 S i:;:i L E S 0 a 0000 i P 7RB3 SfiLES 0 = 0 0 0 Pi ii :25 4 :P; R!.... E S 0 0 pi 0 Pi i: 111 P B SfiLES 2 2 0 0 0 0 0 Q ii- BIPHENYL SfiLES 1 S 2 8 :: 8 8 8 if * ; S 1 2 3 B S fi L E :ii * x 0 fi 0 0 ,, Pi 6 P'i Pi i vi-.i SfiLES 1 5 1. h , R y 0 L:- f 4 8 SfiLES i 4 4. 5 ip , pi pi 8 i ;: ' 3 0 S h L. t. Si Pi.. 8R8S : H T O oi fi ' SfiLES 6 5 8 P 8 Pi ! " : O LI T 8 , 426 PHIiJPj-iE REST.1 3 b 1 T-6,.85 5 4 N Z E H E USAGE 1 . 1 ii- 4 i:: .PPPO fi V fi I L X ! ] ,- '1 V : ` I T HV DP GEM 8.0 1 2 0 :: P U R C i-i HVIi E:..4 0 - 2 1 b 8 0 8 P; T PURCH EiVL epi 1 " iPL P 21.. V P K: :- RPiPP i . PP - Pi L & I P H I 55*- RP ; Pi H I L DSW 185335 STLCOPCB4051581 ' Input Output ----- ^ ------- > ____ i , 10/31 Prod. Plan PUL_PHENYL MflTL BALANCE No Aroclor 8H lb. 1238 'POLYPHENYL MATL ' BALANCE No Dielectric P U L Y P H L N Y L N i i. 1 L BALANCE 1016 SALES 18800.00* 54201 CM SALES 5233.00* 70/30 SALES 5 0 1 A . 0 0 *' PYRB3 SALES 1645.0 0 *' 1254 SALES . di 0H . 0M* MIPB SALES 2 2 0 0.0 0 * BIPHENYL SALES 1520.0 0 * MCS 1238 SALES 2 0 0.00* VP-1 SALES . 1518.0 0 * HB-48 SALES 14455.00* HB30 SALES ' 0.0 0 * SAN I OH AN- SALES ' UR 65.0 0 * SPLIT 1.29 0.54 BENZENh REUD 42742.48 BENZENE USAGE 1.15 HV DRU AVH I L . 413.99 . UNIT HYDR GEN 0.01 LE: PIJRCH HYD - HB-48 164.21 UNIT PURCH HYD 0.0 1 I ^ TOTAL POLYPHENYL 37186.92 ' TOTAL BIPH 22450.10 UCM AVAIL 3379.23 MONTHS OCCUPIED 5.98 1016 SALE S 0.0 0 * 54201 CM SALES ' 0.00* 70/30 SALES 0.0 0 * PYRB3 SALES . 0.00* 1254 SALES 1016 SALES 0.0 0 * 54201 CM SALES 0.0 0 * i . 70/30 SALES 0.0 0 * . ; PYRB3 SALES 0.0 0 * : 1254 SALES MIPS SALES'' . MIPB SALES ' 2200.0 0 * BIPHENYL SALES 220 0.0 0 * BIPHENYL SALES 1520.00* MCS 1233 SALES 8 0 0 0.0 0 * VP-1 SALES 1510.00* H B-40 SALE S 1520.00* : MCS 1238 SALES 200.0 0 * : VP-1 SALES 1 A i 0 . 00* HB-40 SALE'S 14455.00* HB30 SALES ' 0.0 0 * SANTOUAN SALES ' 14455.00* H B 3 0 S ALES 0.0 0 * 8 A NiuU A N SALES . L- HI 6 5.0 0 * ' iJk . 6 5.0 0 * ' SPLIT 1.38 : SPLIT 1.41 0.29 BENZENE REQD 0. i 6 BENZENE REAL 29605.12 BENZENE USAGE 25456.77 BENZENE USAGE 1.23 HYDRO AVAIL 310.66 UNIT HYDR GEN 1.37 : HYDRO AVAIL- "P "! a H !"! UNIT HYDR GEN 0.01 LB PURCH HYD 0.01 LB PURCH HYD HB-48 ! HB-40 267.54 UNIT PURCH HYD.0i?C 299.37 UNIT PURCH HYD . 0.02 TOTAL POLYPHENYL 0.02 TOTAL POLYPHENYL d 3 w! y l t* y TOTAL BIPH . . 13599.68 TOTAL BIPH 8464.85 UCM AVAIL ' 4330.32 MONTHS OCCUPIED ' 3862.85 UCM AVAIL 4776.55 MONTHS OCCUPIED 4.71 4.43 N Biphenyl Unit Cost HB-40 Unit Cost - _ 19.20 1 23.64 24.04 29.50 DSW 185336 27.27 33.07 STLCOPCB4051582