Document rBv843OLYzmLjk7n4egOgmjvv
ENTRAL
... ...
flliJEtlsiG 1 N^EiE;'R||^G. gg
**#*'
E P A R T ME N T
CEA NO. 1430
PRODUCT
PROGRESS REPORT
AR NO.
DATE
Feb.
23,
1968
Aroclors
title
'
!
Increase Aroclor Capacity
DISTRIBUTION CEO SECTION MANAGER
ced project manager
R. P. SteVeHS R. W. Peterson
DIVISION Organic
PLANT Anniston
division representative_______W. F. Taffee
O. R. Bailey J. M. Depp M. Dmytryszyn R. E. Emling F. W. Enoch F. J. Holzapfel R. W. Kaltenrieder F. P. LaBelle R. E. Lenz Russell L. Miller E. Negro C- L. Parish A. B. Terry
(2)
ORGANIC DIVISION
H. C. Carder
R. J. Stratmeyer A. L. Klemm H. L. Williams
(Lett-
W. J. Burkett
.
R. R. Cook/R. ,'c. Herman
R. E. Howard
SCOPE
Aroclor production facilities at Anniston will be expanded by the addition of tankage for storage and for the preparation of blends, drumming facilities in a new building (to be expanded on another project, CEA 1452, into a product warehouse), new and larger flakers for solid Aroclors and for.biphenyl in the same building, and packaging equipment for flaked products. Tank truck loading and a new track spur with tank car loading and unloading facil ities are included.
DSW 200658
CONFIDENT I AL
in for m at i o n
THIS DOCUMENT IS THE PROPERTY OF MONSANTO COMPANY AND THE RECIPIENT IS RESPONSIBLE FOR ITS SAFEKEEPING AND DIS POSITION IT CONTAINS CONFIDENTIAL INFORMATION WHICH MUST NOT BE REPRODUCED. REVEALED TO UNAUTHORIZED PERSONS
OR SENT OUTSIDE THE COMPANY WITHOUT PROPER AUTHORIZATION.
CE- 14
STLCOPCB4058722
>
ProductAroclors
i_ocat j on
Anniston
Title
Increase Aroclor Capacity______________________________________________
Data Tabulated As Of February 9, 1968
CEAWo. 1430
ARtfa
Appropriation
Current Estimate Date of Estimate Expended A Committed Spent This Month Scheduled Completion On Schedule?
MS 1,400 MS 1,307*
December 1967
MS 336 MS 29
August and October
No (Sewer Delays)
1968
Process Design, % Complete
Mechanical Design, % Complete Construction, % Complete 1 % Expended & Committed Design Manpower | Construction Manpower
1430
Last Month This Mo.
74 80 50 60
19 26 1 2 12 -- AT 8
* $93,000 being handled under CEA 1452
SUMMARY;
Corrective sewer work is underway. Tank farm start-up will be August instead of July, and flaker-packaging probably mid-October. Detail definition of the flaker area is now underway.
Field Work;
The 24" process sewer is now being relocated. Gunnite repairs to the 36" storm sewer are well along, and promise to be successful. A new sanitary sewer has been tied in permitting excavation of septic tank fields. Power poles have been relocated to clear the site. We now plan setting tanks 5/6/68. About seven weeks were lost; two may be regained before start-up.
Tank Farm:
Design is well along. Plant ammendments to the blending process will require modifications at blend tank auxiliaries. A few in strument details remain to be resolved,,
Flaker-Packaging:
A workable layout has been developed on the study model and is be
ing discussed with the plant. The flaker vendor's strike has not
been settled. Quotations have been requested on solids handling
equipment. Tests are planned at selected vendors.
'
R. W. Peterson Acting Project Manager
vo
OS***1669 STLCOPCB4058723