71U3 SOAKING FITS FACILITIES
PROJECT SUMMARY AUGUST, 1968 GENERAL The Soaking Pits were lighted off during the month of July with all batteries being heated except Battery No. 1, which was lit off in the month of August.
Ingots were first charged into the pits 13 through 2k on July 21, 1968, and
the first hot ingot was withdrawn for loading on July 26, 1968. Loftus Construction Co. generally completed all remaining work on Batteries No. 1 and No. 2 during the month of August, with only small items remaining. Foothill Electric Co. completed their work in the Soaking Pits during the month of July and reduced their crews to a minimum in August. The Delta Construction Co. piping contract was also completed during this period. At the end of August all twenty-four (2k) pits were operating satisfactorily.
KEN 009366
71U3 SOAKING PITS FACILITIES
PROJECT SUMMARY JUNE, 1968
GENERAL Progress continued in miscellaneous areas of structural steel. Final
refractory lining was completed in Battery No. 3 through No. 6 area. Final lining for pits in Battery No. 2 area is 90% complete and Battery No. 1, 20% complete. Electrical continued to install exposed conduit,
lighting wiring and low voltage cable. All work requirements by Delta Pipeline Constructors have been completed except degreasing oxygen line and the installation of the car thaw fuel oil pipe.
KEN 009367
71A3 SOAKING PITS FACILITIES
PROJECT SUMMARY APRIL . 196ft
I. ENGINEERING Drawing revisions and sketches for miscellaneous minor changes are being made as required.
II. PROCUREMENT Only miscellaneous items of minor nature remain to be purchased.
III. CONSTRUCTION Ioftus is approximately 85% complete and is progressing well with mechanical, piping and refractory installation. However, the electrical installation for lotteries No. 1, No. 2 and No. 3, located at the west end of the structure, is dropping behind schedule. Service piping and electrical work is progressing well. High bay lighting is underway.
KEN 009368
Fpn-mrr NO. 7141
j/jTT. buildings SOAKING PIT AND HOT STRIP FIGURE 1.
Pit facilities to the Aerial view showing relationship of Soaking Hot Strip NiH facilities.
KEN 009369
PROGRESS REPORT NO. 16
PROJECT KG. 71/,?
FIGURE 2. SOAKING PIT BUILDING Aerial view showing stacks and north side of Soaking Pit Building. Service fey ready for sheathing.
VCEN 009370
PROGRESS REPORT NO. 16
PROJECT NO. 7111
FIGURE 3. SOAKING PIT BATTERIES Looking southwest Loftus pits with water-cooled rail girders in place.
KEN 009371
PROGRESS REPORT NO. 16
PROJECT NO, 71A3
FIGURE 4. SOAKING PIT STEELWORK
Looking northwest: Foreground - supply steel for Ingot Buggy Pulpit; MLddleground - Loftus pits with steel in place; feckground - heat protection plates erected on mezzanine level.
KEN 009372
71U3 SOAKING PIT FACILITIES
PROJECT SUMMARY JUNE 1967
I. ENGB1EERIMG Detail design is 95 percent complete.
II. PROCUREMENT Purchase Orders were issued during the month of June for the following: Side Wall Louvers Motor Control Center No. 7 Thaw Pits Grease Pumping Mechanism Fittings for Roof Drains Plant Air and Piping. Inquiries requesting proposals were issued on the following Engineered Equipment: Cinder Handling Buckets and Bucket Dumping Mechanism Fittings for Steam Siphon Discharge Collectors and Downspouts Well Water Lines Bulk Grease System and Pining - Thaw Pit Control House.
III. CONSTRUCTION Aooroximately 22,699 Cubic Yards of Concrete have been placed to date or about 73 percent of total. Structural Steel approximately 3,h9$ tons erected to date is about 82 percent complete. Loftus has erected Grillage steel for pits 15 through ?.h, Hearth floor steel plate has been installed for pits 20 through 21;,
flue framing steel is nearly complete for Batteries $ and 6 (pits 16 through 21;).
Refractory lining is being placed in pit flues and Main collector flues for
Batteries 5 and 6.
KEN 009373
PROGRESS REPORT NO. 13
PROJECT NO. 711*3
FIGURE 2.
SOAKING PIT FACILITIES MAY 5, 1967
Soaking Pit Structural Steel Framework and Stack Foundations (Looking South East at Col. Row "X")
KEN 009374
71ii3 SOAKING
PIT FACIUTIES
PROJECT SUMMARY
I. ENGINEERING
MARCH 1966
A. ENGINEERING REPORT
The Engineering Report was issued for final review.
B. DRAWINGS
The scope drawings were issued for final approval .the last week in
March.
Dewatering and underdrain drawings were approved and issued.
C. .CHART OF ACCOUNTS AND ESTIMATE The Chart of Accounts and Estimate will be revised to reflect the approved scope drawings and the Engineering Report.
II. PROCUREMENT A letter of intent was issued to Loftus Engineering on March lf>, 1966 for Engineering and supplemented in the last week in March to include purchase of Refractory.
III. CONSTRUCTION Construction is scheduled to begin the middle of June 19660