LOUISIANA DIVISION ENVIRONMENTAL CAPITAL SPENDING
AUTHORIZED PROJECTS
AUTH.
PROJECT
$M
NO.____________ TITLE__________________ TOTAL
74321
METHOCEL ENVIRON. UPGRADE
1900
74322
SPENT CELL EFFLUENT SYSTEM LHC
4400
74323
WASTEWATER SYSTEM LHC II
4900
74324 74325
EXCURSION CONT. LHC III
Me/MeCl STRIPPER
CMP
4200 1500
74326
SPENT H9SO4 CMP
1800
74327
THROX - CMP
3100
74328
LANDFILL - LAD
1700
7432?
RELIABILITY IMP. E.O.
1700
74330
EFFLUENT COOLING GLYCOL I
1250
75002
PER-TET SPLITTER SOLVENTS
4100
75003
SURFACE POND ELIMINATION CHLORINE
3000
SPENDING $M M* 1965 1986
1587
313
1987
RTO 6/85
3410
996
9/85
2106 2610
200
6/86
60 3231
685
6/86
1249
228
9/85
223 212 1400
12/86
486 1931 1000 170 329 600 957 786
12/86
600 12/87 3/86
1380
3/84
42 2000 2000
9/87
154 600 2200 12/87
BH:SB 2/86
00 074610
CONFrDFNTIAl
PROJECT TITLE: METHOCEL ENVIRONMENTAL UPGRADE AUTH. $M: 1900 TIMING:
PROJECT RTO - 6/85 REGULATORY - NEW NPDES PERMIT
PROJECT DESCRIPTION: THIS PLANT EXPERIENCED CHRONIC OIL LOSSES TO THE RIVER, HIGH TOD LOSSES TO THE RIVER, UNPERMITTED RUNOFF FROM PONDS, AND TWO PONDS THAT REQUIRED PERMITTING UNDER LOUISIANA SOLID WASTE PROGRAM. PROJECT INCLUDED SEPARATION OF ALL NON-CONTACT COOLING WATER, OIL SEPARATION AND SLAB RUNOFF COLLECTION, CONTACT WATER HANDLING, ORGANIC DISCHARGE PROTECTION IN CHEMICAL STORAGE, AND A TREATMENT SYSTEM FOR OFF-SPEC BATCHES.
BH:sb 2/86
DO 074611 CONFIDENTIAL
LHC II AND III SPENT CELL EFFLUENT TREATMENT SYSTEMS
THE NEW NPDES PERMIT, WHEN IMPLEMENTED, WILL REQUIRE THE LHC PLANTS II AND III MEET A BENZENE STANDARD. THE PERMIT LEVEL WILL BE BASED ON THE CONCENTRATION LEVEL ACHIEVABLE USING THE "BAT"
(-150 PPB). PROJECT CONSISTED OF INSTALLING HIGH SPEED
DECANTERS TO SEPARATE THE HYDROCARBON AND CELL EFFLUENT LIQUID PHASES, EXCHANGERS FOR HEAT RECOVERY AND STEAM STRIPPERS TO REMOVE BENZENE FROM SPENT CELL EFFLUENT.
BH:sb 2/86
DO 074612 CONFIDENTIAL.
LHC II WASTEWATER SYSTEM
THIS PROJECT JUSTIFIED ALONG WITH SPENT CELL EFFLUENT PROJECT TO REDUCE BENZENE LOSSES TO WATER. PROJECT CONSISTED OF REVAMPING THE QUENCH WATER TOWERS TO MINIMIZE NON-COMPLIANCES. THE OILY WATER EFFLUENT IS PHASE SEPARATED AND STEAM STRIPPED. THE HEAVY HYDROCARBON PHASE IS COLLECTED AND PROCESSED IN A DRYING SYSTEM AND THE OIL IS UTILIZED AS FUEL. THE SLOP OIL AREA HOLDING POND WAS CLOSED OUT AND THE "SLOP OIL" AREA DEMOLISHED AS THE RESULT OF THIS PROJECT.
BH:sb 2/86
DO 074613 CONFIDENTS
STATUS REPORT LHC III BENZENE STRIPPING
RUN TIME LIMITED TO ONE TO TWO WEEKS DUE TO FOULING POLYMER FORMATION IN TOWER FROM ALDOL CONDENSATION REACTION THAT IS CATALYZED BY HEAT AND CAUSTIC CONCENTRATION. POSSIBLE SOLUTIONS TO FOULING PROBLEM:
USE A CHEMICAL SCAVENGER TO REDUCE CARBONYL LEVELS. DILUTE CAUSTIC CONCENTRATION USING CONDENSATE. FUEL GAS STRIPPING TO RUN COLUMN AT LOWER TEMPERATURE.
BH:sb 2/86
DO 074614 OONFTDFNTTAl
LHC III EXCURSION CONTAINMENT THIS PROJECT JUSTIFIED ALONG WITH THE LHC III AND LHC II SPENT CELL EFFLUENT TREATMENT SYSTEMS AND LHC II WASTEWATER SYSTEM TO REDUCE BENZENE LOSSES TO THE WATER. THE PROJECT INVOLVES REPLACING AN EXISTING UNLINED RAINWATER IMPOUNDMENT WITH AN ABOVEGROUND TANK; AND THE INSTALLATION OF A FLOATING ROOF TANK AND STEAM STRIPPER TO HANDLE BOTH QUENCH COLUMN EMULSIONS AND BENZENE SPILLS WHICH CAUSE BENZENE PERMIT EXCURSIONS.
DO 074615 CONFTDFNTIAL
PROJECT TITLE: CMP METHANOL/METHYL CHLORIDE STRIPPER AUTH. $M: 1500 TIMING:
PROJECT RTO - 6/86 REGULATORY - NEW NPDES PERMIT
PROJECT DESCRIPTION: THE CHLORINATED METHANES PLANT HAS SIGNIFICANT LOSSES OF METHANOL AND METHYL CHLORIDE. METHYL CHLORIDE LOSSES EXCEED PROPOSED PERMIT LIMITS FOR THE ENTIRE LOUISIANA DIVISION. THE METHANOL/METHYL CHLORIDE STRIPPER IS THE BEST WAY TO ACHIEVE A REDUCTION OF THESE LOSSES.
BH:sb 2/86
\
DO 074616 CONFIDFNTTAL
PROJECT TITLE: CMP SPENT H2SO4 AUTH. $M: 1800 TIMING:
PROJECT RTO - 12/86 REGULATORY - NEW NPDES PERMIT
PROJECT DESCRIPTION:
PROJECT WILL REDUCE THE LEVEL OF ORGANICS (I.E. DME METHYL
CHLORIDE, METHANOL) IN THE PLANT'S SPENT H2SO4 ACID DISCHARGE STREAM IN ORDER TO MEET REQUIREMENTS OF THE "BPT" WATER REGULATIONS. ALTHOUGH DME IS NOT A PRIORITY POLLUTANT, REGULATIONS REQUIRE ITS CONTROL. A STRIPPING COLUMN WITH THE OVERHEADS PIPED TO A THROX UNIT WILL BE INSTALLED TO REMOVE THE ORGANIC CONTAMINANTS.
BH:sb 2/86
DO 07461,7 CONFTDFNTTAl
PROJECT TITLE: CMP THROX AUTH. $M: 1800 TIMING:
PROJECT RTO - 12/86 REGULATORY - NEW NPDES PERMIT
PROJECT DESCRIPTION: THE CHLORINATED METHANES PLANT HAS A SMALL THROX UNIT THAT OPERATES NEAR CAPACITY MOST OF THE TIME. THERE ARE A NUMBER OF METHYL CHLORIDE VENTS IN THE PLANT WHICH NEED TO BE INCINERATED INCLUDING LARGE LOSSES THAT OCCUR DURING PLANT SHUTDOWNS. METHYL CHLORIDE IS A ONE POUND REPORTABLE UNDER SUPERFUND.
LOSSES:. METHANOL - 700 LB/DAY METHYL CHLORIDE - 400 LB/DAY
BAT LIMITS: 5 - 30'LB/DAY RANGE
BH:sb 2/86
DO 074618 CONFTDFNTTAL
PROJECT TITLE: LOUISIANA DIVISION.LANDFILL AUTH. $M: 1700 TIMING:
SOLID WASTE - PROJECT RTO - 6/15/86 REGULATORY - APLF CLOSURE - 8/31/86
HAZARDOUS WASTE - PROJECT RTO - 1/88 DRIVING FORCE - INADEQUATE EXISTING H.W. LANDFILL
PROJECT DESCRIPTION: THIS IS A PROJECT TO CONSTRUCT A STATE-OF-THE-ART SOLID WASTE AND HAZARDOUS WASTE LANDFILLS. THE USE OF SLURRY WALLS, IMPERMEABLE LINERS, AND LEACHATE COLLECTION SYSTEMS WILL BE UTILIZED TO MEET STATE AND FEDERAL REGULATIONS.
THE EXISTING SOLID WASTE LANDFILL IS LOCATED ADJACENT TO THE DIVISION ON AUSTRALIA POINT. THE LANDFILL IS OUTSIDE THE MISSISSIPPI RIVER LEVEE SYSTEM AND IS THEREFORE WITHIN THE 100-YEAR FLOOD PLANE. IT IS NOT PERMITTABLE BECAUSE OF THIS AND IS CURRENTLY UNDER AN AUGUST 31, 1986 CLOSURE ORDER.
THE EXISTING HAZARDOUS WASTE LANDFILL IN THE LOUISIANA DIVISION DOES NOT MEET STATE AND FEDERAL REQUIREMENTS FOR PERMITTING. A PRIMARY PURPOSE OF THE NEW HAZARDOUS WASTE LANDFILL WILL BE THE STORAGE OF INCINERATOR ASH FROM THE DIVISION'S HAZARDOUS WASTE INCINERATOR. IN ADDITION, THERE IS A NEED FOR A PERMITTED DISPOSAL SITE TO HANDLE A FEW HUNDRED TONS PER YEAR OF MISCELLANEOUS INORGANIC WASTES.
BH:sb 2/86
00 074619
CONFTDFNTIAl
BLOCK 80 NON-HAZARDOUS LANDFILL
SLURRY TRENCH CAP PERIMETER DRAINAGE DITCH SUMP PIPELINE TO CENTRAL WASTE TREATMENT INTERIOR DRAIN SYSTEM INTERIOR GRADING ACCESS ROAD WITH GUARDHOUSE MONITORING WELLS
BH:sb 2/86
DO 074600
conftdfnttai.
PROJECT TITLE: BIOX RELIABILITY IMPROVEMENTS AUTH. $M: 1700 TIMING:
PROJECT RTO - 3/86 REGULATORY - NEW NPDES PERMIT
PROJECT DESCRIPTION: PROJECT INCLUDES MODIFICATIONS TO THE WATER TREATMENT PLANT TO IMPROVE OPERATIONAL RELIABILITY AND NOT JEOPARDIZE DIVISION PRODUCTION BY AVOIDING DISCHARGE PERMIT VIOLATIONS. IN ORDER TO ACCOMPLISH THIS, A CIRCULATION HEADER SYSTEM WILL BE INSTALLED TO IMPROVE EQUALIZATION IN THE FEED IMPOUNDMENT, THE INSTRUMENTATION AND CONTROL SCHEME OF THE FILTER PRESS WILL BE UPGRADED, AND THE INCOMING ELECTRICAL SWITCHGEAR UPGRADED TO AVOID PLANT SHUTDOWNS FOR PREVENTIVE MAINTENANCE.
BH:sb 2/86
00 0?46?1
PROJECT TITLE: PER-TET SPLITTER COLUMN AUTH. $M: 400 TIMING:
PROJECT RTO - 9/87 REGULATORY - NEW NPDES PERMIT
PROJECT DESCRIPTION: PROJECT INCLUDES A CHLORINE/HCl SPLITTER COLUMN THAT WILL REPLACE AN EXISTING WET HCl ABSORPTION, CHLORINE DRYING, AND CHLORINE COMPRESSOR UNITS.
THE SOLVENTS PLANT PRESENTLY HAS CARBON TET EMISSIONS FROM THE PER-TET PROCESS IN EXCESS OF THE PROPOSED PERMIT LEVELS, AND THE EXISTING EQUIPMENT IN THE PER-TET ABSORPTION AREA CANNOT CONTROL AT LEVELS BELOW THE PROPOSED NEW REGULATIONS. INSTALLATION OF THE SPLITTER COLUMN REPRESENTS THE APPLICATION OF THE BEST AVAILABLE TECHNOLOGY.
BH:sb 2/86
DO 074602 CONFIDENT TAl
PROJECT TITLE: CHLORINE SURFACE POND ELIMINATION AUTH. $M: 3000 TIMING:
PROJECT RTO - 9/87 REGULATORY -
NEW NPDES PERMIT TSS RESIDUAL CHLORINE
pH
RCRA - GROUNDWATER CONTAMINATION SOURCES
PROJECT DESCRIPTION:
PROJECT WILL UPGRADE THE CHLORINE PLANT'S EXISTING WASTE ALKALINITY STORAGE AND WASTE EFFLUENT SYSTEMS. THE PROJECT WILL INSTALL ABOVEGROUND TANKAGE TO REPLACE THE EXISTING IN GROUND IMPOUNDMENT. IN ADDITION, A TREATMENT SYSTEM FOR REDUCING RESIDUAL CHLORINE LEVELS AND ADJUST THE PH OF EFFLUENT WILL BE INSTALLED TO ENABLE THE PLANT TO COMPLY WITH NEW PERMIT LIMITS; AND BRINE FILTER BACKWASH WILL BE RECYCLED TO ELIMINATE THE SOURCE OF TSS.
BH:sb 2/86
D0 074623 CONFTDFNTTAl
PROJECT TITLE: BRINE PRODUCTION ENVIRONMENTAL UPGRADE
AUTHORIZATION DATE: 1987 TOTAL $M: 1500 TIMING:
PROJECT RTO - 1/89 REGULATORY - STATE ORDER 29-B, COMPLIANCE BY 3/89 PROJECT DESCRIPTION: THE PROJECT WILL RETROFIT TWO BRINE STORAGE SURFACE IMPOUNDMENTS WITH IMPERVIOUS LINERS TO PREVENT THE FURTHER MIGRATION OF BRINE SOLUTION. THE PROJECT WILL ALSO PROVIDE FOR INSTALLING LINERS IN H - 15 LOCATION PITS, AND CONTAINMENT FOR BRINE PUMPING STATIONS. A WATER POND THAT RECEIVES WATER RUNOFF FROM AROUND WELL LOCATIONS MAY ALSO REQUIRE A LINER. ENGINEERING WORK - TENTATIVELY SCHEDULED TO START IN JANUARY, 1987. CONSTRUCTION WORK - THIRD QUARTER, 1987
00 074fc?4 CONFTDPNTTAl-
LOUISIANA DIVISION ENVIRONMENTAL CAPITAL SPENDING
UNAUTHORIZED PROJECTS
PROJECT
DIVISION TANKFARM IMPROVEMENTS
AUTH. DATE
3/86
$M TOTAL
1100
1986 800
1987 300
1988
BRINE PRODUCTION
ENVIRONMENTAL UPGRADE
1987
1500
500 1000
BRINE STG. POND IMP. - CHLORINE
1987
250
150 100
RTO 3/87
DRIVING FORCE
NPDES PERMIT
6/86
1/89
LA. DNR S.O. 29--B - 3/89
1/89
LA. DNR S.O. 29--B - 3/89
BH:sb 2/86
DO 074625 CONFTDFNTTAl
PROJECT TITLE: DIVISION TANK FARM IMPROVEMENTS
AUTHORIZATION DATE: 3/86 TOTAL $M: 1100 TIMING:
PROJECT RTO - 3/87 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: PROJECT WILL PROVIDE A MEANS FOR CAUSTIC I, GLYCOL I, AND SOLVENTS PLANTS TO COLLECT AND RECYCLE CHEMICAL LEAKS, SPILLS, AND CONTAMINATED STORMWATER RUNOFF, AND PREVENT CHEMICAL LOSSES TO THE SOIL AROUND PUMPING SYSTEMS, SAMPLING POINTS, PRODUCT FILTERS AND AIR POLLUTION CONTROL EQUIPMENT. THE PRIMARY REASON FOR ENVIRONMENTALLY UPGRADING THE TANK FARM IS TO COMPLY WITH FORTHCOMING NPDES PERMIT DISCHARGE LIMITATIONS. THESE REGULATIONS IMPOSE RIGOROUS REQUIREMENTS ON PERMISSIBLE CONCENTRATIONS OF EDC, CHLOROFORM, AND MATERIAL CONTRIBUTING TO TOD IN DISCHARGEABLE QUALITY STORMWATER.
00 074 CONFTDFNTTAl
THE PROJECT WILL INSTALL INTERMEDIATE DIKING TO SEGREGATE NON-COMPATIBLE MATERIALS FROM RECYCLE STANDPOINT. FOUR SUMPS WILL BE INSTALLED TO COLLECT STORMWATER RUNOFF AND FORWARD IT INTO RECYCLE HANDLING SYSTEMS, OR DISCHARGE IT TO A PERMITTED OUTFALL. CONTAINMENT WILL BE INSTALLED AROUND PUMPS, SAMPLING/DRAIN POINTS, FILTERS, AND AIR POLLUTION CONTROL EQUIPMENT WITH DRAINS TO LEAK COLLECTION SUMPS. ENGINEERING COMPLETED 2ND QUARTER, 1986 CONSTRUCTION STARTED 3RD QUARTER, 1986
DO 074677 CONFIDENTIAL
PROJECT TITLE: CHLORINE PLANT BRINE STORAGE PONDS UPGRADE (PITS 1 AND 2)
AUTHORIZATION DATE: 1987 TOTAL $M: 250 TIMING:
PROJECT RTO - 1/89 REGULATORY - STATE ORDER 29-B, COMPLIANCE BY 3/89 PROJECT DESCRIPTION: PROJECT WILL INSTALL IMPERVIOUS LINERS IN TWO BRINE STORAGE SURFACE IMPOUNDMENTS. THE 20-YEAR OLD CONCRETE IMPOUNDMENTS ARE SUSPECT OF LEAKAGE INTO THE ENVIRONMENT.
BH:sb 2/86
D0 074628 CONFIDENTIAL
LOUISIANA DIVISION ENVIRONMENTAL EXPENSE PROJECTS
PROJECT BLOCK 49 CLOSURE
$M TOTAL
2800
TM5 1115
SPENDING
1986
1987
1000
400
1988 300
DRIVING FORCE
ADMIN. ORDER FROM DEQ
APLF CLOSURE
1050 374 675
CLOSURE ORDER
8/86
BH:sb 2/86
DO 074079 CONFTDFNTTAL
PROJECT TITLE: BLOCK 49
TOTAL $M: TIMING:
2800
PROJECT - CONTINUING THROUGH 1988 REGULATORY - ADMINISTRATIVE ORDER, LA. DEQ
PROJECT DESCRIPTION:
THIS PROJECT WILL CONTINUE REMEDIAL ACTIVITY TO RECOVER CONTAMINATED GROUNDWATER FROM THIS INACTIVE WASTE DISPOSAL SITE. THE PROJECT INVOLVES THE INSTALLATION OF A SERIES OF RECOVERY WELLS, A PHASE SEPARATION SYSTEM, A STORAGE TANK, A TRANSFER LINE TO BLOCK 19, AND EQUIPMENT WASHDOWN STATION.
BH: SB 2/86
DO 074630 CONFTDFNTTAl
PROJECT TITLE: AUSTRALIA POINT LANDFILL NO. 2 CLOSURE AUTH. $M: 1050 TIMING:
PROJECT - 3RD QUARTER, 1986 REGULATORY - CLOSURE COMPLIANCE ORDER, LA. DEQ - AUGUST 31, 1986 PROJECT DESCRIPTION: THIS AREA CONTAINS GENERAL INDUSTRIAL SOLID WASTE (NON-HAZARDOUS) AND IS LOCATED ON THE RIVER SIDE OF THE MISSISSIPPI RIVER LEVEE. THE PROPERTY IS IN THE 100-YEAR FLOOD PLANE AND FLLODS REGULARLY. CLOSURE WILL INCLUDE A SECURE CLAY CAP, TOP SOIL, VEGETATION, AND A LEACHATE COLLECTION SYSTEM.
BH:sb 2/86
DO 074631 CONFTDFNTTAl-
LOUISIANA DIVISION UNDERGROUND STORAGE TANKS
LOCATION DOWANOLS
VOLUME (GALLONS)
1700
MACHINE SHOP
23
POLY C
1300
BRINE PRODUCTION 1000
MAINTENANCE BLOCK 30
4000
MAINTENANCE BLOCK 30
4000
MAINTENANCE BLOCK 30
4000
PIPELINE
4000
"CATHODIC PROTECTION COSTS
CONTENTS GLYCOLS, ETHERS, AND
ALCOHOLS HYDRAULIC OIL SYSTEM WASTE OIL GASOLINE LEADED GASOLINE
DIESEL FUEL
UNLEADED GASOLINE
GASOLINE
BH:sb 2/86
COST $15,000*
$3,000 $85,000
$40,000
DO 07463? CONFIDFNT T Al
NAPHTHA PIPELINE TANKS*
LOCATION
VOLUME (GALLONS)
CONTENTS
PIPELINE - COURTABLEU
208 NAPHTHA
PIPELINE - W. OPELOUSAS
208
NAPHTHA
PIPELINE - E. OPELOUSAS
208
NAPHTHA
PIPELINE - BASILE
208 NAPHTHA
PIPELINE - E. EUNICE
208 NAPHTHA
PIPELINE - W. EUNICE
208 NAPHTHA
PIPELINE - W. VINTON
208 NAPHTHA
PIPELINE - E. VINTON
208 NAPHTHA
PIPELINE - BUHLER
208 NAPHTHA
PIPELINE - LOBDELL
2100
NAPHTHA
PIPELINE - BLOCK 110 TANKFARM
2100
NAPHTHA
TOTAL COST
EXEMPTED FROM FEDERAL REGULATIONS
BH:sb 2/86
COST
$2000 $2000 $2000 $2000 $2000 $2000 $2000 $2000 $2000
$3500 $3500
$25000
DO DO NF
0;,4633
TFNTTfitl
1986, 1987 SPC AND SPCC CAPITAL PROJECTS
SPCC POLY A POLY A POWER II SOLVENTS R&D MAINTENANCE
UTILITIES
$M 30 50 30 30
20
23
90
TIMING 1986 1986 1986 1986 1986 1987
1986
WASTE OIL
ENLARGE SUMP BY AC 1 - 4
OIL/H.W. STORAGE
COMPRESSOR OIL DIKING
OIL CONTAINMENT
GAS TRUCK OFF LOAD CONTAINMENT
DIVISION TRANSFORMER CONTAINMENT
SPC $M CMP 150
VINYL II
200
CA II CAUSTIC POLY B
250 180
20
SPC AND SPCC CHLORINE
$M
200
MARKET DEVEL.
BH:sb
2/86
20
TIMING 1986 - $50M 1987 - $100M
TANKCAR LOAD RACK CONTAINMENT
1986 - $75M 1987 - $125M
1986 1987
TANKCAR/TRUCK LOADING CONTAINMENT
CAUSTIC TANK CONTAINMENT (5)
TO COMPLETE BLOCK CONTAINMENT
TANKCAR CONTAINMENT
TIMING 1986
1986
OIL AND SPC CONTAINMENT (EXTENSIVE) OIL AND SPC CONTAINMENT
DO 074634 CONFTOFNTTAt