Document qaqeqzxXwx6BQj9YRz7DDrBxk

LOUISIANA DIVISION ENVIRONMENTAL CAPITAL SPENDING AUTHORIZED PROJECTS AUTH. PROJECT $M NO.____________ TITLE__________________ TOTAL 74321 METHOCEL ENVIRON. UPGRADE 1900 74322 SPENT CELL EFFLUENT SYSTEM LHC 4400 74323 WASTEWATER SYSTEM LHC II 4900 74324 74325 EXCURSION CONT. LHC III Me/MeCl STRIPPER CMP 4200 1500 74326 SPENT H9SO4 CMP 1800 74327 THROX - CMP 3100 74328 LANDFILL - LAD 1700 7432? RELIABILITY IMP. E.O. 1700 74330 EFFLUENT COOLING GLYCOL I 1250 75002 PER-TET SPLITTER SOLVENTS 4100 75003 SURFACE POND ELIMINATION CHLORINE 3000 SPENDING $M M* 1965 1986 1587 313 1987 RTO 6/85 3410 996 9/85 2106 2610 200 6/86 60 3231 685 6/86 1249 228 9/85 223 212 1400 12/86 486 1931 1000 170 329 600 957 786 12/86 600 12/87 3/86 1380 3/84 42 2000 2000 9/87 154 600 2200 12/87 BH:SB 2/86 00 074610 CONFrDFNTIAl PROJECT TITLE: METHOCEL ENVIRONMENTAL UPGRADE AUTH. $M: 1900 TIMING: PROJECT RTO - 6/85 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: THIS PLANT EXPERIENCED CHRONIC OIL LOSSES TO THE RIVER, HIGH TOD LOSSES TO THE RIVER, UNPERMITTED RUNOFF FROM PONDS, AND TWO PONDS THAT REQUIRED PERMITTING UNDER LOUISIANA SOLID WASTE PROGRAM. PROJECT INCLUDED SEPARATION OF ALL NON-CONTACT COOLING WATER, OIL SEPARATION AND SLAB RUNOFF COLLECTION, CONTACT WATER HANDLING, ORGANIC DISCHARGE PROTECTION IN CHEMICAL STORAGE, AND A TREATMENT SYSTEM FOR OFF-SPEC BATCHES. BH:sb 2/86 DO 074611 CONFIDENTIAL LHC II AND III SPENT CELL EFFLUENT TREATMENT SYSTEMS THE NEW NPDES PERMIT, WHEN IMPLEMENTED, WILL REQUIRE THE LHC PLANTS II AND III MEET A BENZENE STANDARD. THE PERMIT LEVEL WILL BE BASED ON THE CONCENTRATION LEVEL ACHIEVABLE USING THE "BAT" (-150 PPB). PROJECT CONSISTED OF INSTALLING HIGH SPEED DECANTERS TO SEPARATE THE HYDROCARBON AND CELL EFFLUENT LIQUID PHASES, EXCHANGERS FOR HEAT RECOVERY AND STEAM STRIPPERS TO REMOVE BENZENE FROM SPENT CELL EFFLUENT. BH:sb 2/86 DO 074612 CONFIDENTIAL. LHC II WASTEWATER SYSTEM THIS PROJECT JUSTIFIED ALONG WITH SPENT CELL EFFLUENT PROJECT TO REDUCE BENZENE LOSSES TO WATER. PROJECT CONSISTED OF REVAMPING THE QUENCH WATER TOWERS TO MINIMIZE NON-COMPLIANCES. THE OILY WATER EFFLUENT IS PHASE SEPARATED AND STEAM STRIPPED. THE HEAVY HYDROCARBON PHASE IS COLLECTED AND PROCESSED IN A DRYING SYSTEM AND THE OIL IS UTILIZED AS FUEL. THE SLOP OIL AREA HOLDING POND WAS CLOSED OUT AND THE "SLOP OIL" AREA DEMOLISHED AS THE RESULT OF THIS PROJECT. BH:sb 2/86 DO 074613 CONFIDENTS STATUS REPORT LHC III BENZENE STRIPPING RUN TIME LIMITED TO ONE TO TWO WEEKS DUE TO FOULING POLYMER FORMATION IN TOWER FROM ALDOL CONDENSATION REACTION THAT IS CATALYZED BY HEAT AND CAUSTIC CONCENTRATION. POSSIBLE SOLUTIONS TO FOULING PROBLEM: USE A CHEMICAL SCAVENGER TO REDUCE CARBONYL LEVELS. DILUTE CAUSTIC CONCENTRATION USING CONDENSATE. FUEL GAS STRIPPING TO RUN COLUMN AT LOWER TEMPERATURE. BH:sb 2/86 DO 074614 OONFTDFNTTAl LHC III EXCURSION CONTAINMENT THIS PROJECT JUSTIFIED ALONG WITH THE LHC III AND LHC II SPENT CELL EFFLUENT TREATMENT SYSTEMS AND LHC II WASTEWATER SYSTEM TO REDUCE BENZENE LOSSES TO THE WATER. THE PROJECT INVOLVES REPLACING AN EXISTING UNLINED RAINWATER IMPOUNDMENT WITH AN ABOVEGROUND TANK; AND THE INSTALLATION OF A FLOATING ROOF TANK AND STEAM STRIPPER TO HANDLE BOTH QUENCH COLUMN EMULSIONS AND BENZENE SPILLS WHICH CAUSE BENZENE PERMIT EXCURSIONS. DO 074615 CONFTDFNTIAL PROJECT TITLE: CMP METHANOL/METHYL CHLORIDE STRIPPER AUTH. $M: 1500 TIMING: PROJECT RTO - 6/86 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: THE CHLORINATED METHANES PLANT HAS SIGNIFICANT LOSSES OF METHANOL AND METHYL CHLORIDE. METHYL CHLORIDE LOSSES EXCEED PROPOSED PERMIT LIMITS FOR THE ENTIRE LOUISIANA DIVISION. THE METHANOL/METHYL CHLORIDE STRIPPER IS THE BEST WAY TO ACHIEVE A REDUCTION OF THESE LOSSES. BH:sb 2/86 \ DO 074616 CONFIDFNTTAL PROJECT TITLE: CMP SPENT H2SO4 AUTH. $M: 1800 TIMING: PROJECT RTO - 12/86 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: PROJECT WILL REDUCE THE LEVEL OF ORGANICS (I.E. DME METHYL CHLORIDE, METHANOL) IN THE PLANT'S SPENT H2SO4 ACID DISCHARGE STREAM IN ORDER TO MEET REQUIREMENTS OF THE "BPT" WATER REGULATIONS. ALTHOUGH DME IS NOT A PRIORITY POLLUTANT, REGULATIONS REQUIRE ITS CONTROL. A STRIPPING COLUMN WITH THE OVERHEADS PIPED TO A THROX UNIT WILL BE INSTALLED TO REMOVE THE ORGANIC CONTAMINANTS. BH:sb 2/86 DO 07461,7 CONFTDFNTTAl PROJECT TITLE: CMP THROX AUTH. $M: 1800 TIMING: PROJECT RTO - 12/86 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: THE CHLORINATED METHANES PLANT HAS A SMALL THROX UNIT THAT OPERATES NEAR CAPACITY MOST OF THE TIME. THERE ARE A NUMBER OF METHYL CHLORIDE VENTS IN THE PLANT WHICH NEED TO BE INCINERATED INCLUDING LARGE LOSSES THAT OCCUR DURING PLANT SHUTDOWNS. METHYL CHLORIDE IS A ONE POUND REPORTABLE UNDER SUPERFUND. LOSSES:. METHANOL - 700 LB/DAY METHYL CHLORIDE - 400 LB/DAY BAT LIMITS: 5 - 30'LB/DAY RANGE BH:sb 2/86 DO 074618 CONFTDFNTTAL PROJECT TITLE: LOUISIANA DIVISION.LANDFILL AUTH. $M: 1700 TIMING: SOLID WASTE - PROJECT RTO - 6/15/86 REGULATORY - APLF CLOSURE - 8/31/86 HAZARDOUS WASTE - PROJECT RTO - 1/88 DRIVING FORCE - INADEQUATE EXISTING H.W. LANDFILL PROJECT DESCRIPTION: THIS IS A PROJECT TO CONSTRUCT A STATE-OF-THE-ART SOLID WASTE AND HAZARDOUS WASTE LANDFILLS. THE USE OF SLURRY WALLS, IMPERMEABLE LINERS, AND LEACHATE COLLECTION SYSTEMS WILL BE UTILIZED TO MEET STATE AND FEDERAL REGULATIONS. THE EXISTING SOLID WASTE LANDFILL IS LOCATED ADJACENT TO THE DIVISION ON AUSTRALIA POINT. THE LANDFILL IS OUTSIDE THE MISSISSIPPI RIVER LEVEE SYSTEM AND IS THEREFORE WITHIN THE 100-YEAR FLOOD PLANE. IT IS NOT PERMITTABLE BECAUSE OF THIS AND IS CURRENTLY UNDER AN AUGUST 31, 1986 CLOSURE ORDER. THE EXISTING HAZARDOUS WASTE LANDFILL IN THE LOUISIANA DIVISION DOES NOT MEET STATE AND FEDERAL REQUIREMENTS FOR PERMITTING. A PRIMARY PURPOSE OF THE NEW HAZARDOUS WASTE LANDFILL WILL BE THE STORAGE OF INCINERATOR ASH FROM THE DIVISION'S HAZARDOUS WASTE INCINERATOR. IN ADDITION, THERE IS A NEED FOR A PERMITTED DISPOSAL SITE TO HANDLE A FEW HUNDRED TONS PER YEAR OF MISCELLANEOUS INORGANIC WASTES. BH:sb 2/86 00 074619 CONFTDFNTIAl BLOCK 80 NON-HAZARDOUS LANDFILL SLURRY TRENCH CAP PERIMETER DRAINAGE DITCH SUMP PIPELINE TO CENTRAL WASTE TREATMENT INTERIOR DRAIN SYSTEM INTERIOR GRADING ACCESS ROAD WITH GUARDHOUSE MONITORING WELLS BH:sb 2/86 DO 074600 conftdfnttai. PROJECT TITLE: BIOX RELIABILITY IMPROVEMENTS AUTH. $M: 1700 TIMING: PROJECT RTO - 3/86 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: PROJECT INCLUDES MODIFICATIONS TO THE WATER TREATMENT PLANT TO IMPROVE OPERATIONAL RELIABILITY AND NOT JEOPARDIZE DIVISION PRODUCTION BY AVOIDING DISCHARGE PERMIT VIOLATIONS. IN ORDER TO ACCOMPLISH THIS, A CIRCULATION HEADER SYSTEM WILL BE INSTALLED TO IMPROVE EQUALIZATION IN THE FEED IMPOUNDMENT, THE INSTRUMENTATION AND CONTROL SCHEME OF THE FILTER PRESS WILL BE UPGRADED, AND THE INCOMING ELECTRICAL SWITCHGEAR UPGRADED TO AVOID PLANT SHUTDOWNS FOR PREVENTIVE MAINTENANCE. BH:sb 2/86 00 0?46?1 PROJECT TITLE: PER-TET SPLITTER COLUMN AUTH. $M: 400 TIMING: PROJECT RTO - 9/87 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: PROJECT INCLUDES A CHLORINE/HCl SPLITTER COLUMN THAT WILL REPLACE AN EXISTING WET HCl ABSORPTION, CHLORINE DRYING, AND CHLORINE COMPRESSOR UNITS. THE SOLVENTS PLANT PRESENTLY HAS CARBON TET EMISSIONS FROM THE PER-TET PROCESS IN EXCESS OF THE PROPOSED PERMIT LEVELS, AND THE EXISTING EQUIPMENT IN THE PER-TET ABSORPTION AREA CANNOT CONTROL AT LEVELS BELOW THE PROPOSED NEW REGULATIONS. INSTALLATION OF THE SPLITTER COLUMN REPRESENTS THE APPLICATION OF THE BEST AVAILABLE TECHNOLOGY. BH:sb 2/86 DO 074602 CONFIDENT TAl PROJECT TITLE: CHLORINE SURFACE POND ELIMINATION AUTH. $M: 3000 TIMING: PROJECT RTO - 9/87 REGULATORY - NEW NPDES PERMIT TSS RESIDUAL CHLORINE pH RCRA - GROUNDWATER CONTAMINATION SOURCES PROJECT DESCRIPTION: PROJECT WILL UPGRADE THE CHLORINE PLANT'S EXISTING WASTE ALKALINITY STORAGE AND WASTE EFFLUENT SYSTEMS. THE PROJECT WILL INSTALL ABOVEGROUND TANKAGE TO REPLACE THE EXISTING IN GROUND IMPOUNDMENT. IN ADDITION, A TREATMENT SYSTEM FOR REDUCING RESIDUAL CHLORINE LEVELS AND ADJUST THE PH OF EFFLUENT WILL BE INSTALLED TO ENABLE THE PLANT TO COMPLY WITH NEW PERMIT LIMITS; AND BRINE FILTER BACKWASH WILL BE RECYCLED TO ELIMINATE THE SOURCE OF TSS. BH:sb 2/86 D0 074623 CONFTDFNTTAl PROJECT TITLE: BRINE PRODUCTION ENVIRONMENTAL UPGRADE AUTHORIZATION DATE: 1987 TOTAL $M: 1500 TIMING: PROJECT RTO - 1/89 REGULATORY - STATE ORDER 29-B, COMPLIANCE BY 3/89 PROJECT DESCRIPTION: THE PROJECT WILL RETROFIT TWO BRINE STORAGE SURFACE IMPOUNDMENTS WITH IMPERVIOUS LINERS TO PREVENT THE FURTHER MIGRATION OF BRINE SOLUTION. THE PROJECT WILL ALSO PROVIDE FOR INSTALLING LINERS IN H - 15 LOCATION PITS, AND CONTAINMENT FOR BRINE PUMPING STATIONS. A WATER POND THAT RECEIVES WATER RUNOFF FROM AROUND WELL LOCATIONS MAY ALSO REQUIRE A LINER. ENGINEERING WORK - TENTATIVELY SCHEDULED TO START IN JANUARY, 1987. CONSTRUCTION WORK - THIRD QUARTER, 1987 00 074fc?4 CONFTDPNTTAl- LOUISIANA DIVISION ENVIRONMENTAL CAPITAL SPENDING UNAUTHORIZED PROJECTS PROJECT DIVISION TANKFARM IMPROVEMENTS AUTH. DATE 3/86 $M TOTAL 1100 1986 800 1987 300 1988 BRINE PRODUCTION ENVIRONMENTAL UPGRADE 1987 1500 500 1000 BRINE STG. POND IMP. - CHLORINE 1987 250 150 100 RTO 3/87 DRIVING FORCE NPDES PERMIT 6/86 1/89 LA. DNR S.O. 29--B - 3/89 1/89 LA. DNR S.O. 29--B - 3/89 BH:sb 2/86 DO 074625 CONFTDFNTTAl PROJECT TITLE: DIVISION TANK FARM IMPROVEMENTS AUTHORIZATION DATE: 3/86 TOTAL $M: 1100 TIMING: PROJECT RTO - 3/87 REGULATORY - NEW NPDES PERMIT PROJECT DESCRIPTION: PROJECT WILL PROVIDE A MEANS FOR CAUSTIC I, GLYCOL I, AND SOLVENTS PLANTS TO COLLECT AND RECYCLE CHEMICAL LEAKS, SPILLS, AND CONTAMINATED STORMWATER RUNOFF, AND PREVENT CHEMICAL LOSSES TO THE SOIL AROUND PUMPING SYSTEMS, SAMPLING POINTS, PRODUCT FILTERS AND AIR POLLUTION CONTROL EQUIPMENT. THE PRIMARY REASON FOR ENVIRONMENTALLY UPGRADING THE TANK FARM IS TO COMPLY WITH FORTHCOMING NPDES PERMIT DISCHARGE LIMITATIONS. THESE REGULATIONS IMPOSE RIGOROUS REQUIREMENTS ON PERMISSIBLE CONCENTRATIONS OF EDC, CHLOROFORM, AND MATERIAL CONTRIBUTING TO TOD IN DISCHARGEABLE QUALITY STORMWATER. 00 074 CONFTDFNTTAl THE PROJECT WILL INSTALL INTERMEDIATE DIKING TO SEGREGATE NON-COMPATIBLE MATERIALS FROM RECYCLE STANDPOINT. FOUR SUMPS WILL BE INSTALLED TO COLLECT STORMWATER RUNOFF AND FORWARD IT INTO RECYCLE HANDLING SYSTEMS, OR DISCHARGE IT TO A PERMITTED OUTFALL. CONTAINMENT WILL BE INSTALLED AROUND PUMPS, SAMPLING/DRAIN POINTS, FILTERS, AND AIR POLLUTION CONTROL EQUIPMENT WITH DRAINS TO LEAK COLLECTION SUMPS. ENGINEERING COMPLETED 2ND QUARTER, 1986 CONSTRUCTION STARTED 3RD QUARTER, 1986 DO 074677 CONFIDENTIAL PROJECT TITLE: CHLORINE PLANT BRINE STORAGE PONDS UPGRADE (PITS 1 AND 2) AUTHORIZATION DATE: 1987 TOTAL $M: 250 TIMING: PROJECT RTO - 1/89 REGULATORY - STATE ORDER 29-B, COMPLIANCE BY 3/89 PROJECT DESCRIPTION: PROJECT WILL INSTALL IMPERVIOUS LINERS IN TWO BRINE STORAGE SURFACE IMPOUNDMENTS. THE 20-YEAR OLD CONCRETE IMPOUNDMENTS ARE SUSPECT OF LEAKAGE INTO THE ENVIRONMENT. BH:sb 2/86 D0 074628 CONFIDENTIAL LOUISIANA DIVISION ENVIRONMENTAL EXPENSE PROJECTS PROJECT BLOCK 49 CLOSURE $M TOTAL 2800 TM5 1115 SPENDING 1986 1987 1000 400 1988 300 DRIVING FORCE ADMIN. ORDER FROM DEQ APLF CLOSURE 1050 374 675 CLOSURE ORDER 8/86 BH:sb 2/86 DO 074079 CONFTDFNTTAL PROJECT TITLE: BLOCK 49 TOTAL $M: TIMING: 2800 PROJECT - CONTINUING THROUGH 1988 REGULATORY - ADMINISTRATIVE ORDER, LA. DEQ PROJECT DESCRIPTION: THIS PROJECT WILL CONTINUE REMEDIAL ACTIVITY TO RECOVER CONTAMINATED GROUNDWATER FROM THIS INACTIVE WASTE DISPOSAL SITE. THE PROJECT INVOLVES THE INSTALLATION OF A SERIES OF RECOVERY WELLS, A PHASE SEPARATION SYSTEM, A STORAGE TANK, A TRANSFER LINE TO BLOCK 19, AND EQUIPMENT WASHDOWN STATION. BH: SB 2/86 DO 074630 CONFTDFNTTAl PROJECT TITLE: AUSTRALIA POINT LANDFILL NO. 2 CLOSURE AUTH. $M: 1050 TIMING: PROJECT - 3RD QUARTER, 1986 REGULATORY - CLOSURE COMPLIANCE ORDER, LA. DEQ - AUGUST 31, 1986 PROJECT DESCRIPTION: THIS AREA CONTAINS GENERAL INDUSTRIAL SOLID WASTE (NON-HAZARDOUS) AND IS LOCATED ON THE RIVER SIDE OF THE MISSISSIPPI RIVER LEVEE. THE PROPERTY IS IN THE 100-YEAR FLOOD PLANE AND FLLODS REGULARLY. CLOSURE WILL INCLUDE A SECURE CLAY CAP, TOP SOIL, VEGETATION, AND A LEACHATE COLLECTION SYSTEM. BH:sb 2/86 DO 074631 CONFTDFNTTAl- LOUISIANA DIVISION UNDERGROUND STORAGE TANKS LOCATION DOWANOLS VOLUME (GALLONS) 1700 MACHINE SHOP 23 POLY C 1300 BRINE PRODUCTION 1000 MAINTENANCE BLOCK 30 4000 MAINTENANCE BLOCK 30 4000 MAINTENANCE BLOCK 30 4000 PIPELINE 4000 "CATHODIC PROTECTION COSTS CONTENTS GLYCOLS, ETHERS, AND ALCOHOLS HYDRAULIC OIL SYSTEM WASTE OIL GASOLINE LEADED GASOLINE DIESEL FUEL UNLEADED GASOLINE GASOLINE BH:sb 2/86 COST $15,000* $3,000 $85,000 $40,000 DO 07463? CONFIDFNT T Al NAPHTHA PIPELINE TANKS* LOCATION VOLUME (GALLONS) CONTENTS PIPELINE - COURTABLEU 208 NAPHTHA PIPELINE - W. OPELOUSAS 208 NAPHTHA PIPELINE - E. OPELOUSAS 208 NAPHTHA PIPELINE - BASILE 208 NAPHTHA PIPELINE - E. EUNICE 208 NAPHTHA PIPELINE - W. EUNICE 208 NAPHTHA PIPELINE - W. VINTON 208 NAPHTHA PIPELINE - E. VINTON 208 NAPHTHA PIPELINE - BUHLER 208 NAPHTHA PIPELINE - LOBDELL 2100 NAPHTHA PIPELINE - BLOCK 110 TANKFARM 2100 NAPHTHA TOTAL COST EXEMPTED FROM FEDERAL REGULATIONS BH:sb 2/86 COST $2000 $2000 $2000 $2000 $2000 $2000 $2000 $2000 $2000 $3500 $3500 $25000 DO DO NF 0;,4633 TFNTTfitl 1986, 1987 SPC AND SPCC CAPITAL PROJECTS SPCC POLY A POLY A POWER II SOLVENTS R&D MAINTENANCE UTILITIES $M 30 50 30 30 20 23 90 TIMING 1986 1986 1986 1986 1986 1987 1986 WASTE OIL ENLARGE SUMP BY AC 1 - 4 OIL/H.W. STORAGE COMPRESSOR OIL DIKING OIL CONTAINMENT GAS TRUCK OFF LOAD CONTAINMENT DIVISION TRANSFORMER CONTAINMENT SPC $M CMP 150 VINYL II 200 CA II CAUSTIC POLY B 250 180 20 SPC AND SPCC CHLORINE $M 200 MARKET DEVEL. BH:sb 2/86 20 TIMING 1986 - $50M 1987 - $100M TANKCAR LOAD RACK CONTAINMENT 1986 - $75M 1987 - $125M 1986 1987 TANKCAR/TRUCK LOADING CONTAINMENT CAUSTIC TANK CONTAINMENT (5) TO COMPLETE BLOCK CONTAINMENT TANKCAR CONTAINMENT TIMING 1986 1986 OIL AND SPC CONTAINMENT (EXTENSIVE) OIL AND SPC CONTAINMENT DO 074634 CONFTOFNTTAt