Document qakKK1bjojJ7dZeKkaRpBO3Qk
ABD00220715
VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL
PART G: PRE-STARTUP SAFETY REVIEW (PSSR)
1.0 SCOPE
This policy establishes a Pre-Startup Safety Review (PSSR) procedure for the Aberdeen PVC Plant. A PSSR will be conducted for all new facilities installed and on modifications to existing facilities. Modifications to existing facilities are considered "changes" and are also subject to the provisions of Management of Change (see Aberdeen Plant Management of Change Procedure). Implementation of this policy will fulfill the requirements of OSHA 29 CFR 1910.119/ paragraph (i).
2.0 PURPOSE
The purpose of this policy is to ensure that a thorough review of
potential hazards has been conducted on new and modified facilities
prior to introduction of chemicals into the process or start-up of
equipment.
The review also ensures documentation exists as
required for other elements of OSHA Process Safety.
3.0 DEFINITIONS
Facility - A process unit and its associated equipment.
Modified Facility - A facility which has undergone modification which resulted in a change to the process safety information.
PSSR - Pre-Startup Safety Review
PSSR Team - A Team consisting of representatives from appropriate departments such as Safety, Operations, Process Engineering, Project Engineering, Maintenance, and others as needed which has been established to conduct the PSSR.
PSSR TEAM LEADER - The PSSR Team Leader will be designated by the Department Head over the "project" or "change". The Team Leader is responsible for providing the necessary documentation for review in the PSSR and for submitting the results of the PSSR to management.
DATE OF ISSUE: 8/05/92
1
ABD00220716
VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL
PART G: PRE-STARTUP SAFETY REVIEW (PSSR)
The Project Engineer will normally be designated as PSSR Team Leader for "projects".
4.0 APPLICATION
The PSSR policy applies to any new facilities or modifications to existing facilities. It applies to all chemical processes at the Aberdeen Plant (e.g. Compound is included). Modifications to existing facilities are "changes" and subject to the provisions of both Management of Change and PSSR. This includes both capital projects and work order changes.
5.0 PSSR TEAM
5.0.1 Prior to start-up, a PSSR Team shall be formed to conduct
the PSSR. Representatives from Operations, Safety, Maintenance,
and Engineering, departments should be selected for participation on
the PSSR Team as appropriate.
The Team make-up should be
appropriate for the size and complexity of the PSSR to be
conducted. Initiators of the "change" or members of the PHA team
for the "project" or "change" should be considered for
participation on the PSSR Team. The Department Head over the
'^project" or "change" is responsible for defining which Departments
need to be represented on the Team. The PSSR may be conducted by
an individual on simple "projects" or "changes" with approval from
the appropriate Department Head.
5.0.2 A PSSR Team Leader shall be designated for each PSSR by the Department Head over the "project" or "change". On "projects", the Project Engineer will normally be the PSSR Team Leader. The PSSR Team Leader will be responsible for contacting appropriate Department Heads and requesting other members for the PSSR Team. The PSSR Team Leader is responsible for ensuring all documentation (e.g. construction check sheets, etc.) is in-place and ready for review by the PSSR Team.
5.0.3 It is the responsibility of the PSSR Team to conduct the PSSR in accordance with this policy and present the PSSR results to the appropriate Department Superintendent.
DATE OF ISSUE: 8/05/92
2
ABD00220717
VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL
PART G: PRE-STARTUP SAFETY REVIEW (PSSR)
6.0 PSSR PROCEDURE
The documentation requirements listed in items 6.1 through 6.3 below apply to "projects" only. The required documentation for the PSSR for "changes" is filling out Attachment "B", the "PSSR FOR CHANGES CHECKLIST".
6.1 CONSTRUCTION REVIEW
The Team will review the construction check sheets to verify all work is complete. During construction and prior to the PSSR, the PSSR Team Leader will document the progress of the construction. Attachment "A" is a sample check sheet to aid in the documentation during construction. The PSSR Team Leader is responsible for adding to or deleting from the sheet as needed, so all critical information is provided to the PSSR Team.
6.2 PHYSICAL HAZARD REVIEW
The PSSR Team will identify physical hazards at the construction site. Physical hazards are items such as tripping hazards, sharp objects, head clearances, etc. Attachment "C" is a guideline to be used in this physical hazard review for "projects". The PSSR Team Leader is responsible for adding to or deleting from the list as necessary.
6.3 ADMINISTRATIVE CHECKLIST
Attachment "D", the "Administrative Checklist"; should be filled out to document the following for "projects":
6.3.1 OPERATING, MAINTENANCE AND EMERGENCY PROCEDURES
The PSSR Team shall verify the following procedures are in place prior to startup of the facility:
6.3.1.1
Operating procedures as required in the
Aberdeen Plant Operating Procedure Development and
Control Policy.
6.3.1.2
Maintenance procedures including both
-preventative and routine maintenance as appropriate for
equipment in the facility.
DATE OF ISSUE: 8/05/92
3
ABDQ0220718
VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL
PART G: PRE-STARTUP SAFETY REVIEW (PSSR)
6.3.1.4 Emergency response procedures as applicable.
6.3.2 PROCESS HAZARDS ANALYSIS AND MANAGEMENT OF CHANGE
The PSSR Team shall ensure that a Process Hazards Analysis (PHA) has been conducted and that all recommendations resulting from the PHA have been addressed. The Team shall also verify that the modifications have been made in accordance with Management of Change provisions.
6.3.3 TRAINING
The team shall verify that appropriate training has been conducted for operations personnel associated with the facility. Documentation of training shall be available which certifies that operations personnel understood the training received.
6.4 PSSR CHECKLIST FOR CHANGES
Attachment "B11 is the "PSSR Checklist for Changes". The checklist shall be filled out for all "changes" as defined in the Aberdeen Plant Management of Change Procedure. This list encompasses the requirements listed in sections 6.1 through 6.3 above in an abbreviated format.
6.5 RECOMMENDATIONS
After completion of the PSSR, a list of recommended actions shall be generated by the PSSR Team. The list of recommendations shall be generated for all PSSRs ("projects" and "changes'*) . Each recommendation will be classified as either "critical" (C) or "noncritical" (N) . All "critical" items must be corrected prior to start-up of the facility.
7.0 REPORTING
A PSSR Report shall be submitted to the appropriate Department Superintendent for approval upon completion of the PSSR. The report shall be filled out for all PSSRs ("projects and "changes") and should document that a PSSR has been completed for the facility
DATE OF ISSUE: 8/05/92
4
ABD00220719
VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL
PART G: PRE-STARTUP SAFETY REVIEW (PSSR)
in accordance with this policy. The PSSR Team Leader has the responsibility for writing and issuing the report. The report should include the following information:
7.1 A list of recommendations.
7.2
Assignment of priority (either MC" or "N") for each
recommendation.
7.3 A reference to the appropriate code, policy, etc. (if applicable) for each recommendation.
7.4
Assignment of individual responsibilities for each
recommendation.
7.5 Target completion dates for each Mc" item and scheduled completion dates for all nN" items.
7.6 Non-critical items may be accepted without correction with written approval from the appropriate Department Superintendent.
The appropriate Department Superintendent and the Safety Director have the authority for approval of the PSSR report. Attachment UE" is an example PSSR Report form.
8.0 STARTUP AUTHORIZATION
Prior to startup, a Startup Authorization Statement shall be prepared by the PSSR Team Leader which certifies that all critical items have been corrected. The Startup Authorization Statement shall be completed for all PSSRs ("projects" and "changes"). Approval for. start-up will be authorized by the appropriate Department Superintendent. Attachment "F" is an example Startup Authorization Statement Form.
9.0 DOCUMENTATION
The approved PSSR Report and Startup Authorization Statement shall be maintained in the PSM files for the life of the facility. The PSSR Team Leader is responsible for filing this report in the PSM Files.
DATE OF ISSUE: 8/05/92
5
ABD00220720
Pre-Startup Safety Review
Attachment "A"
Issue Date: 08/05/92
CONSTRUCTION CHECKLIST
PROJECT TITLE:___________________________________________ AFE #:__ WO#: PROJECT ENGINEER:________________' "________ !_________ PROCESS ENGINEER:______________________________________
TASK MASTER P&ID'S UPDATED: PROJECT ENGINEER PROCESS ENGINEER
PIPING SYSTEMS: LINE NUMBER:
PRESSURE TEST PIPE: MEDIUM:_________________ @ FOR
NO. X-RAYS REQ'D:
(ATTACH RESULTS)
PIPE FLUSHED/TREATED: TREATED WITH: __________
DATE
PERFORMED BY:
UNDERGROUND PIPE JEEPED: # CATHODES INSTALLED:. : INSULATING FLANGES INSTALLED:
SERVICE TEST STEAM TRACING: MEDIUM: @ FOR
VINYL UNIT ONLY:
ANY BLEEDER INSTALLED ON A LINE OR VESSEL
CONTAINING VCM WILL BE REPORTED TO THE
. ABERDEEN ENVIRONMENTAL COORDINATOR FOR NESHAPS
LIST.
NO. OF VALVES REPORTED:
DATE OF ISSUE: 8/05/92
6
ABD00220721
Pre-Startup Safety Review
Attachment "A"
Issue Date: 08/05/92
SAFETY SYSTEMS:
RELIEF VALVE: EQUIPMENT NUMBER RELIEF COLOR CODED FOR PM: (CIRCLE ONE USED)
1992 1993 1994
1996
(1997) (1998) (1999) (2000) (2001)
SET PRESSURE___________ GREEN YELLOW RED ORANGE BLUE
DOCUMENTATION ON FILE-AVAILABLE FOR REVIEW IN EQUIPMENT FILE.
RUPTURE DISC BURST PRESSURE: LOT NUMBER:_________________
UNIT PROTECTED ALARM SYSTEM TESTED:
FIRE PROTECTION SYSTEM TESTED: TYPE: _
TEST DESCRIPTION:
DATE
PERFORMED BY:
APPROVALS AND WITNESSES:
DATE OF ISSUE: 8/05/92
8
ABD00220722
Pre-Startup Safety Review
Attachment "A"
ATMOSPHERIC AND PRESSURE VESSELS :
EQUIPMENT
DATE
EQUIPMENT NUMBER DESCRIPTION:______
SHOP VESSEL INSPECTION REQ'D: YES/NO/NA
____________
VESSEL DOCUMENTATION: (BY MANUF.) AVAILABLE FOR REVIEW IN EQUIPMENT FILES:
CALCULATIONS WELDER QUALIFICATION VERIFIED CERTIFIED DWGS ASME FORM (U, R, OR A) X-RAYS PROVIDED PER CODE MTL DATA SHEETS LINING OR PAINT SPECIFICATIONS STRESS RELIEVING
YES/NO/NA YES/NO YES/NO/NA
YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA
IF NO TO ANY ABOVE, WHY?.
Issue Date: 08/05/92
PERFORMED BY:
MARK ITEM TESTED:
(EXCHANGER SHELL SIDE, PRESSURE TEST: MEDIUM: @ FOR
VESSEL)
_____
FLUSHED/TREATED:
_____
(EXCHANGER TUBE PRESSURE TEST: MEDIUM: @ FOR
SIDE,
VESSEL JACKET) _____
VESSEL FLUSHED/TREATED:-
___
DATE OF ISSUE: 8/05/92
7
ABD00220723
Pre-Startup Safety Review
Attachment "A"
Issue Date: 08/05/92
MECHANICAL EQUIPMENT:
EQUIPMENT EQUIPMENT NUMBER: DESCRIPTION:_______
DATE
PERFORMED BY:
ALIGNMENT:__________ LUBRICATION USED:
CORRECT ROTATION: SEAL FLUID USED:
VIBRATION CHECK: _________________ BUILDING PRESSURIZATION CHECK: (ATTACH TEST WITH WITNESSES)
______________ ______________
OVERHEAD CRANE HOIST:
ATTACH CERTIFICATION AND IDENTIFY FOR MONTHLY TESTING WITH
TOOL ROOM MECHANIC. ATTACH COPY OF CERTIFICATION AND TOOL
ROOM IDENTIFICATION NUMBER FOR FUTURE REFERENCE.
YES/NO/NA
CIVIL/STRUCTURAL:
ATTACH REFERENCE FOR SOIL TESTS PERFORMED (FILED WITH CONTRACT SUPERVISOR)
UNDERGROUND DRAWINGS UPDATED DESIGN OF CONCRETE/STEEL IN PROJECT FILE MONORAILS ARE TO BE ENTERED INTO VMS SYSTEM AND
CALCULATIONS FILED IN DRAWING ROOM.
BUILDINGS:
YES/NO/NA
YES/NO/NA YES/NO/NA
YES/NO/NA
DOORS AND WINDOWS HUNG TO AVOID PROJECTING INTO OR BLOCKING WALKWAYS OR EXITS
ELEVATORS EQUIPPEDWITH SHAFT-WAY DOOR INTERLOCKS YES/NO/NA
AND CAR GATES CONTACTS ELECTRICAL:
POSITIVE ELECTRICAL POWER DISCONNECTS INSTALLED AND CHECKED FOR LOCKOUT PURPOSES
RED CONCRETE FOR UNDERGROUND ELECTRICAL ELECTRICAL CLASSIFICATION OF UNIT UNDER CONSTRUCTION
MOTORS:_______________________________________________________ __ INSTRUMENTATION:_________________________________________ ___ OTHER:
YES/NO/NA
YES/NO/NA YES/NO/NA
DATE OF ISSUE: 8/05/92
9
ABD00220724
Pre-Startup Safety Review
Attachment "A"
Issue Date: 08/05/92
INSTRUMENTATION & ELECTRICAL:
INSTRUMENTATION CALIBRATION, CHECK OUT AND OTHER ACTIVITIES THAT APPLY TO CONSTRUCTION, INSTALLATION AND PRE-START UP CHECKS WILL BE RECORDED ON THE LOOP DIAGRAM SHEET. STAMPS WILL BE AVAILABLE IN THE DESIGN DEPARTMENT SIGNALLING NECESSARY CHECKS. THE PARTY RESPONSIBLE FOR CONSTRUCTION WILL GENERATE THE LOOP DIAGRAM LIST. AFFECTED IN ANY WAY BY THE CHANGE. THE PSSR TEAM WILL VERIFY LOOP CHECK OUT SIGNATURES ON LOOP DRAWINGS FOR COMPLETENESS. ELECTRIC TRACING WILL BE CHECKED IN THE SAME MANNER PRIOR TO INSULATION.
DRAWING NUMBERLOOP NUMBERGENERATORPSSR TEAM
DATE OF ISSUE: 8/05/92
10
ABD00220725
Pre-Startup Safety Review
Attachment "B"
Issue date: 8/05/92
PSSR CHECKLIST FOR CHANGES
1. Is the equipment installed properly?
2. Is the area of the change free of physical hazards (e.g. head clearance, sharp edges, etc.)?
3. Has a Process Hazard Analysis been performed and all identified hazards addressed?
4. Has a MOCA form been filled out and all the requirements of the MOCA met?
5. Are operating, maintenance, and emergency procedures in place?
6. Is operator training complete and documented for the change?
YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA
DATE OF ISSUE: 8/05/92
11