Document qakKK1bjojJ7dZeKkaRpBO3Qk

ABD00220715 VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL PART G: PRE-STARTUP SAFETY REVIEW (PSSR) 1.0 SCOPE This policy establishes a Pre-Startup Safety Review (PSSR) procedure for the Aberdeen PVC Plant. A PSSR will be conducted for all new facilities installed and on modifications to existing facilities. Modifications to existing facilities are considered "changes" and are also subject to the provisions of Management of Change (see Aberdeen Plant Management of Change Procedure). Implementation of this policy will fulfill the requirements of OSHA 29 CFR 1910.119/ paragraph (i). 2.0 PURPOSE The purpose of this policy is to ensure that a thorough review of potential hazards has been conducted on new and modified facilities prior to introduction of chemicals into the process or start-up of equipment. The review also ensures documentation exists as required for other elements of OSHA Process Safety. 3.0 DEFINITIONS Facility - A process unit and its associated equipment. Modified Facility - A facility which has undergone modification which resulted in a change to the process safety information. PSSR - Pre-Startup Safety Review PSSR Team - A Team consisting of representatives from appropriate departments such as Safety, Operations, Process Engineering, Project Engineering, Maintenance, and others as needed which has been established to conduct the PSSR. PSSR TEAM LEADER - The PSSR Team Leader will be designated by the Department Head over the "project" or "change". The Team Leader is responsible for providing the necessary documentation for review in the PSSR and for submitting the results of the PSSR to management. DATE OF ISSUE: 8/05/92 1 ABD00220716 VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL PART G: PRE-STARTUP SAFETY REVIEW (PSSR) The Project Engineer will normally be designated as PSSR Team Leader for "projects". 4.0 APPLICATION The PSSR policy applies to any new facilities or modifications to existing facilities. It applies to all chemical processes at the Aberdeen Plant (e.g. Compound is included). Modifications to existing facilities are "changes" and subject to the provisions of both Management of Change and PSSR. This includes both capital projects and work order changes. 5.0 PSSR TEAM 5.0.1 Prior to start-up, a PSSR Team shall be formed to conduct the PSSR. Representatives from Operations, Safety, Maintenance, and Engineering, departments should be selected for participation on the PSSR Team as appropriate. The Team make-up should be appropriate for the size and complexity of the PSSR to be conducted. Initiators of the "change" or members of the PHA team for the "project" or "change" should be considered for participation on the PSSR Team. The Department Head over the '^project" or "change" is responsible for defining which Departments need to be represented on the Team. The PSSR may be conducted by an individual on simple "projects" or "changes" with approval from the appropriate Department Head. 5.0.2 A PSSR Team Leader shall be designated for each PSSR by the Department Head over the "project" or "change". On "projects", the Project Engineer will normally be the PSSR Team Leader. The PSSR Team Leader will be responsible for contacting appropriate Department Heads and requesting other members for the PSSR Team. The PSSR Team Leader is responsible for ensuring all documentation (e.g. construction check sheets, etc.) is in-place and ready for review by the PSSR Team. 5.0.3 It is the responsibility of the PSSR Team to conduct the PSSR in accordance with this policy and present the PSSR results to the appropriate Department Superintendent. DATE OF ISSUE: 8/05/92 2 ABD00220717 VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL PART G: PRE-STARTUP SAFETY REVIEW (PSSR) 6.0 PSSR PROCEDURE The documentation requirements listed in items 6.1 through 6.3 below apply to "projects" only. The required documentation for the PSSR for "changes" is filling out Attachment "B", the "PSSR FOR CHANGES CHECKLIST". 6.1 CONSTRUCTION REVIEW The Team will review the construction check sheets to verify all work is complete. During construction and prior to the PSSR, the PSSR Team Leader will document the progress of the construction. Attachment "A" is a sample check sheet to aid in the documentation during construction. The PSSR Team Leader is responsible for adding to or deleting from the sheet as needed, so all critical information is provided to the PSSR Team. 6.2 PHYSICAL HAZARD REVIEW The PSSR Team will identify physical hazards at the construction site. Physical hazards are items such as tripping hazards, sharp objects, head clearances, etc. Attachment "C" is a guideline to be used in this physical hazard review for "projects". The PSSR Team Leader is responsible for adding to or deleting from the list as necessary. 6.3 ADMINISTRATIVE CHECKLIST Attachment "D", the "Administrative Checklist"; should be filled out to document the following for "projects": 6.3.1 OPERATING, MAINTENANCE AND EMERGENCY PROCEDURES The PSSR Team shall verify the following procedures are in place prior to startup of the facility: 6.3.1.1 Operating procedures as required in the Aberdeen Plant Operating Procedure Development and Control Policy. 6.3.1.2 Maintenance procedures including both -preventative and routine maintenance as appropriate for equipment in the facility. DATE OF ISSUE: 8/05/92 3 ABDQ0220718 VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL PART G: PRE-STARTUP SAFETY REVIEW (PSSR) 6.3.1.4 Emergency response procedures as applicable. 6.3.2 PROCESS HAZARDS ANALYSIS AND MANAGEMENT OF CHANGE The PSSR Team shall ensure that a Process Hazards Analysis (PHA) has been conducted and that all recommendations resulting from the PHA have been addressed. The Team shall also verify that the modifications have been made in accordance with Management of Change provisions. 6.3.3 TRAINING The team shall verify that appropriate training has been conducted for operations personnel associated with the facility. Documentation of training shall be available which certifies that operations personnel understood the training received. 6.4 PSSR CHECKLIST FOR CHANGES Attachment "B11 is the "PSSR Checklist for Changes". The checklist shall be filled out for all "changes" as defined in the Aberdeen Plant Management of Change Procedure. This list encompasses the requirements listed in sections 6.1 through 6.3 above in an abbreviated format. 6.5 RECOMMENDATIONS After completion of the PSSR, a list of recommended actions shall be generated by the PSSR Team. The list of recommendations shall be generated for all PSSRs ("projects" and "changes'*) . Each recommendation will be classified as either "critical" (C) or "noncritical" (N) . All "critical" items must be corrected prior to start-up of the facility. 7.0 REPORTING A PSSR Report shall be submitted to the appropriate Department Superintendent for approval upon completion of the PSSR. The report shall be filled out for all PSSRs ("projects and "changes") and should document that a PSSR has been completed for the facility DATE OF ISSUE: 8/05/92 4 ABD00220719 VISTA CHEMICAL COMPANY - ABERDEEN PLANT PROCESS SAFETY MANAGEMENT MANUAL PART G: PRE-STARTUP SAFETY REVIEW (PSSR) in accordance with this policy. The PSSR Team Leader has the responsibility for writing and issuing the report. The report should include the following information: 7.1 A list of recommendations. 7.2 Assignment of priority (either MC" or "N") for each recommendation. 7.3 A reference to the appropriate code, policy, etc. (if applicable) for each recommendation. 7.4 Assignment of individual responsibilities for each recommendation. 7.5 Target completion dates for each Mc" item and scheduled completion dates for all nN" items. 7.6 Non-critical items may be accepted without correction with written approval from the appropriate Department Superintendent. The appropriate Department Superintendent and the Safety Director have the authority for approval of the PSSR report. Attachment UE" is an example PSSR Report form. 8.0 STARTUP AUTHORIZATION Prior to startup, a Startup Authorization Statement shall be prepared by the PSSR Team Leader which certifies that all critical items have been corrected. The Startup Authorization Statement shall be completed for all PSSRs ("projects" and "changes"). Approval for. start-up will be authorized by the appropriate Department Superintendent. Attachment "F" is an example Startup Authorization Statement Form. 9.0 DOCUMENTATION The approved PSSR Report and Startup Authorization Statement shall be maintained in the PSM files for the life of the facility. The PSSR Team Leader is responsible for filing this report in the PSM Files. DATE OF ISSUE: 8/05/92 5 ABD00220720 Pre-Startup Safety Review Attachment "A" Issue Date: 08/05/92 CONSTRUCTION CHECKLIST PROJECT TITLE:___________________________________________ AFE #:__ WO#: PROJECT ENGINEER:________________' "________ !_________ PROCESS ENGINEER:______________________________________ TASK MASTER P&ID'S UPDATED: PROJECT ENGINEER PROCESS ENGINEER PIPING SYSTEMS: LINE NUMBER: PRESSURE TEST PIPE: MEDIUM:_________________ @ FOR NO. X-RAYS REQ'D: (ATTACH RESULTS) PIPE FLUSHED/TREATED: TREATED WITH: __________ DATE PERFORMED BY: UNDERGROUND PIPE JEEPED: # CATHODES INSTALLED:. : INSULATING FLANGES INSTALLED: SERVICE TEST STEAM TRACING: MEDIUM: @ FOR VINYL UNIT ONLY: ANY BLEEDER INSTALLED ON A LINE OR VESSEL CONTAINING VCM WILL BE REPORTED TO THE . ABERDEEN ENVIRONMENTAL COORDINATOR FOR NESHAPS LIST. NO. OF VALVES REPORTED: DATE OF ISSUE: 8/05/92 6 ABD00220721 Pre-Startup Safety Review Attachment "A" Issue Date: 08/05/92 SAFETY SYSTEMS: RELIEF VALVE: EQUIPMENT NUMBER RELIEF COLOR CODED FOR PM: (CIRCLE ONE USED) 1992 1993 1994 1996 (1997) (1998) (1999) (2000) (2001) SET PRESSURE___________ GREEN YELLOW RED ORANGE BLUE DOCUMENTATION ON FILE-AVAILABLE FOR REVIEW IN EQUIPMENT FILE. RUPTURE DISC BURST PRESSURE: LOT NUMBER:_________________ UNIT PROTECTED ALARM SYSTEM TESTED: FIRE PROTECTION SYSTEM TESTED: TYPE: _ TEST DESCRIPTION: DATE PERFORMED BY: APPROVALS AND WITNESSES: DATE OF ISSUE: 8/05/92 8 ABD00220722 Pre-Startup Safety Review Attachment "A" ATMOSPHERIC AND PRESSURE VESSELS : EQUIPMENT DATE EQUIPMENT NUMBER DESCRIPTION:______ SHOP VESSEL INSPECTION REQ'D: YES/NO/NA ____________ VESSEL DOCUMENTATION: (BY MANUF.) AVAILABLE FOR REVIEW IN EQUIPMENT FILES: CALCULATIONS WELDER QUALIFICATION VERIFIED CERTIFIED DWGS ASME FORM (U, R, OR A) X-RAYS PROVIDED PER CODE MTL DATA SHEETS LINING OR PAINT SPECIFICATIONS STRESS RELIEVING YES/NO/NA YES/NO YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA IF NO TO ANY ABOVE, WHY?. Issue Date: 08/05/92 PERFORMED BY: MARK ITEM TESTED: (EXCHANGER SHELL SIDE, PRESSURE TEST: MEDIUM: @ FOR VESSEL) _____ FLUSHED/TREATED: _____ (EXCHANGER TUBE PRESSURE TEST: MEDIUM: @ FOR SIDE, VESSEL JACKET) _____ VESSEL FLUSHED/TREATED:- ___ DATE OF ISSUE: 8/05/92 7 ABD00220723 Pre-Startup Safety Review Attachment "A" Issue Date: 08/05/92 MECHANICAL EQUIPMENT: EQUIPMENT EQUIPMENT NUMBER: DESCRIPTION:_______ DATE PERFORMED BY: ALIGNMENT:__________ LUBRICATION USED: CORRECT ROTATION: SEAL FLUID USED: VIBRATION CHECK: _________________ BUILDING PRESSURIZATION CHECK: (ATTACH TEST WITH WITNESSES) ______________ ______________ OVERHEAD CRANE HOIST: ATTACH CERTIFICATION AND IDENTIFY FOR MONTHLY TESTING WITH TOOL ROOM MECHANIC. ATTACH COPY OF CERTIFICATION AND TOOL ROOM IDENTIFICATION NUMBER FOR FUTURE REFERENCE. YES/NO/NA CIVIL/STRUCTURAL: ATTACH REFERENCE FOR SOIL TESTS PERFORMED (FILED WITH CONTRACT SUPERVISOR) UNDERGROUND DRAWINGS UPDATED DESIGN OF CONCRETE/STEEL IN PROJECT FILE MONORAILS ARE TO BE ENTERED INTO VMS SYSTEM AND CALCULATIONS FILED IN DRAWING ROOM. BUILDINGS: YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA DOORS AND WINDOWS HUNG TO AVOID PROJECTING INTO OR BLOCKING WALKWAYS OR EXITS ELEVATORS EQUIPPEDWITH SHAFT-WAY DOOR INTERLOCKS YES/NO/NA AND CAR GATES CONTACTS ELECTRICAL: POSITIVE ELECTRICAL POWER DISCONNECTS INSTALLED AND CHECKED FOR LOCKOUT PURPOSES RED CONCRETE FOR UNDERGROUND ELECTRICAL ELECTRICAL CLASSIFICATION OF UNIT UNDER CONSTRUCTION MOTORS:_______________________________________________________ __ INSTRUMENTATION:_________________________________________ ___ OTHER: YES/NO/NA YES/NO/NA YES/NO/NA DATE OF ISSUE: 8/05/92 9 ABD00220724 Pre-Startup Safety Review Attachment "A" Issue Date: 08/05/92 INSTRUMENTATION & ELECTRICAL: INSTRUMENTATION CALIBRATION, CHECK OUT AND OTHER ACTIVITIES THAT APPLY TO CONSTRUCTION, INSTALLATION AND PRE-START UP CHECKS WILL BE RECORDED ON THE LOOP DIAGRAM SHEET. STAMPS WILL BE AVAILABLE IN THE DESIGN DEPARTMENT SIGNALLING NECESSARY CHECKS. THE PARTY RESPONSIBLE FOR CONSTRUCTION WILL GENERATE THE LOOP DIAGRAM LIST. AFFECTED IN ANY WAY BY THE CHANGE. THE PSSR TEAM WILL VERIFY LOOP CHECK OUT SIGNATURES ON LOOP DRAWINGS FOR COMPLETENESS. ELECTRIC TRACING WILL BE CHECKED IN THE SAME MANNER PRIOR TO INSULATION. DRAWING NUMBERLOOP NUMBERGENERATORPSSR TEAM DATE OF ISSUE: 8/05/92 10 ABD00220725 Pre-Startup Safety Review Attachment "B" Issue date: 8/05/92 PSSR CHECKLIST FOR CHANGES 1. Is the equipment installed properly? 2. Is the area of the change free of physical hazards (e.g. head clearance, sharp edges, etc.)? 3. Has a Process Hazard Analysis been performed and all identified hazards addressed? 4. Has a MOCA form been filled out and all the requirements of the MOCA met? 5. Are operating, maintenance, and emergency procedures in place? 6. Is operator training complete and documented for the change? YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA YES/NO/NA DATE OF ISSUE: 8/05/92 11