(conoco) Interoffice Communication To L. N. Vernon ^1 r I 11 r*r> ! ^ From Date August 15, 1975 subject VCM Plant Environmental Health Report - July 1975 1. STATE AND FEDERAL AGENCY ACTION A. Environmental Protection Agency 1) VCM Emission Control Plant personnel visited Ponca City on July 31 to attend an R & D and PED review of control technology and the status of R & D research on carbon adsorption and catalytic oxidation. A Capital Budget item was prepared for control of VCM containing vent streams. This included incineration of all vents except the oxychlorination vent and carbon adsorption of the oxy vent. B. Louisiana Air Control Commission 1) Hydrocarbon Compliance Plan Status Mr. Gus VonBodungen of the LACC technical staff visited the VCM Plant during July to determine if a "good faith" effort was being made by Conoco to complete it's compliance plan projects. He concluded the VCM Plant was making such an effort and would convey his findings to the EPA. The oxychlorination cleanup reactor, R-305, was completed by July 15 and an attempt was made to startup the reactor. As oxy started up the catalyst bed temperatures began to rise before the addition of chlorine. Oxychlorination was then shutdown as the R-305 outlet temperature approached the teflon piping temperature limit of 205C and R-305 was bypassed. The Louisiana Air Control Commission was notified in July of the completion of R-305 and the unsuccessful initial startup attempt. On August 6, the reactor was successfully started up. The LACC will be notified of the successful R-305 startup. The vent return pipeline is expected to be complete and ready for plant tie-in by the end of August. Delivery of the vent refrigeration system is still scheduled for the end of August. CCR 000060750 2. SECONDARY TREATING SYSTEM A. NPDES Permit Compliance - July Results As indicated below, all effluent parameters remained within permit limitations. Effluent CharacteriStic Average Maximum 1 bs/da.y 1 bs/da.y Permit tci 7-1-77 Average Maximum 1 bs/da.y 1 bs/da.y After 7-1-77 Average Maximum 1 bs/da.y 1 bs/da.y COD 614.7 1469 8000 27000 4177 9398 BOD 211.1 538 4000 9000 600 1350 TSS 350 666 2000 4700 558 1256 Ammonia-N 59.3 142 110 330 30 68 Chromium 6.73 17.08 20 60 0.5 mg/1* 1 .0 mg/1* Chlorinated Hydrocarbons Not analyzed pH Remained in the required 6-9 range * In the cooling Tower Blowdown Effluent water averaged 400 gpm during the July sampling periods. The secondary .system operated well during July, with only the ammonia limitation exceeding the after 7-1-77 conditions. The high ammonia discharges could have been caused by an overfeed of urea or by displacement of septic water from the sludge wasting basin. B. Optimization Program 1) Operator training seminars were held during July to stress the im portance of effective secondary system operation. The seminar covered all major operating points including safety, sampling requirements, EPA requirements and emergency repairs. Revised laboratory and operator log sheets were issued to improve communication on the systems operation. 2) Dilution water is being added to the feed to the secondary system to determine the effect of lower chloride concentration and lower COD feed concentration on system operation and clarifier solids carryover. If dilution proves effective in improving system operation, a design will be prepared to use LCCP treated effluent water as the dilution stream. CCR 000060751 3) Mon-chromate Cooling Water Test The plant began using the United Chemical non-chromate treatment during July. This treatment replaced the Betz Chemical treatment which proved unsatisfactory due to corrosion (pitting) and heavy scale formation. High suspended solids were initially experienced indicating an effective cleanup program. The first set of United Chemical test exchanger tubes will be examined during August. bw CC: REL-JAD-JEC-JHM-GGD-PLF-DAK-RLH-RDG-CLM-RFT OBM-BDR CC 000060752 VCM EFFLUENT WATER ANALYSTS 1/ i\ CM ro -:r m ir a g t 0 O' r X > 5" 0 0 LO cr- SO Mf LO CO 0> O r-- y i' > |n 1 C-) r> O fc C vC fi CM 0 O M O f O' >C c O P-- <n C; CM *r r~ * tx. O -si O 0 Oc\ c X) "K 1 ro CM cn CO CM1 IT) r~~ LO r-1 CTv 1 r- LO LO LO 5 CO LO LO LO r-. r- CM LO 1 -. i-s r-. LO C: ro r--* LT. r- r^. CC p-- LO LO 0 Ol co C- LO CO CO LO LO LO LO 00 LO O LO LO LC 1 C5Mt- CM CM LO v4> >s "O c < 0 0 LO 2 O O to1 U LO r-~ 1 LOj 0 O r*. co CO cc <sf N LO O CO r*. N O cf CM cr co LO 1-- CO a, 1 &; 0 (3-1 i 0 r- u. s -p R O O TJ Cl tu a; <y E Wp0 fi R > -L 5./ E r-l 0: O I: <L> n: O C-1) p Cl o'! * (V C'1 -J O 1 1 tfl ra4 H 3 w R O g aj O 0>! X) B cn > T0ZJ XJ Q) XI XJ Si rH 1 8(L> M fH-` *rt 0 x3 '-V 0 H e^t O C' r-1l r 0p r-l H 1 Cl H fH 0 .c: L'-l O rHI u 3 < > >--1 cl ci JU P tO-4 .1--01 TJ Li) S a R ai O u 3 \ > O rH a "rl c. 0 ii * 4, t> LI; lO l> CO O r*t f-l rH VO LU M E T otal A c id As HCl ' *t X O' U y-- Z LU MD uX a; CM uj D UJ 5X Z) U O > CM O Z O O CM O U v eu rs ___1. a _2 U CM u V) L. C CJ 0 ~c o) 06 0 UJ Cl. zu > u a LU a) 0 a CM LO r- O LO ro CM LO O OO O O' or h-- I Of 1-- r^ ' a-> co CM CO 0 0O 0 CO LO co cr CM LO CO CM ^3- LO cr, 0 O ro rs. 0c CO cO LO CM 0 LO c o-v CTi CO r- CM LO LO ro CO LO 0 1 10 0 1 CTk LO CO CM CO r^. CM O d- 0=d- co r^- CM LO O LO Ocr> O<31 O ro CM O O OO O LO LO rs CO co <X cr> O 0 O0 O O CM ro ro 1-- CO 0 O O0 ^- CO C<TOt CO CM ro CM LO LO lo 10 r-- r-. r- r- j 1 1 ? r- M- T~" co 1 1 CM CO1 r>- r-'- - O r> O 0 0 O' 0 -g .ji w HYDROCARBON COMPLIANCE PLAN STATUS I. R-305 Progress Increment Date As LACC Approved. 1. System Design 2. Eval. and Cost Est. 11/30/73 01/13/74 3. AFE 02/01/74 4. Equipment and Mat1!. Purchase a. Reactor b. Preheater 05/15/74 5. Delivery a. Reactor b. Preheater c. Structure d. Teflon Pipe '* e. Catalyst 03/15/75 6. Installation Modify plant piping Foundations Modify R-305 Install. R-305 05/01/75 7. Startup and Operation II. VINYL VENT RECOVERY SYSTEM 1. System Design 07/15/7F* 03/01/74 2. Eval. and Cost Est. 05/01/74 3. AFE 05/15/74 4. Equipment and Mat'!. Purchase a. Refrig. Unit 08/01/74 5. Delivery a. Refrig. Unit 03/01/75 6. Installation Stack Const. 'Refrig. Unit 11/15/75* 7. Startup and Operation 12/01/75* Projected Comp!etion 03/27/75 03/75 08/25/75 12/01/75 12/01/75' Actual Completion 11/30/73 02/07/74 03/05/74 03/20/74 04/17/74 06/21/74 05/24/74 04/04/75 05/06/74 12/02/74 07/15/75 07/15/75 03/19/74 05/07/74 06/17/74 06/17/74 02/26/75 CCR 00060754 III. VENT RETURN PIPELINE Proqress Increment Date As LACC Approved 1. System Design 06/07/74 ' 2. Eval. and Cost Est. 08/02/74 3. AFE 10/01/74 4. Equipment and Mat'l. Purchase 10/21/74 a. Pipe b. Stanchions & fittings 5. Delivery 01/31/75 a. Pipe b. Stanchions & fittings 6. Installation (Started 3-17- 75*) 12/01/75* 7. Startup and Operation 12/01/75** Projected Completion --- -- 08/75 08/75 Actual Compl etion 06/07/74 08/02/74 10/01/74 05/30/74 61/10/75 05/30/74 01/10/75 - *.Revised LACC 5/20/75 ** This date was revised by the LACC on 5/20/75 to correspond with startup of the vent refrigeration system's startup. oooo*>155 CO* Figure I VCM Plant Effluent Water Analysis From Secondary System Outlet Flow in GPM COQ lb s /d a y Suspended S olids Ibs/day ( BOD^ Ibs/day ----------- After 7-1-77 Permit Limitation 000060756 CCR Temperature Figure II VCM Plant Effluent Water Analysis From Secondary System Outlet CCR 000060757 PPM Dissolved 0o Figure III VCM Plant Effluent Air Analysis From C-500 Vent vl SCO CCR 000060758 46 3093 -vr? ij m o n i h s 'r 9000 : Figure IV VCM Plant Effluent Air Analysis From C-500 CC 000060759