Document pGvY93e6dE5BEzdORyrwrqNE
NJ3AC0MPANY CORRESPONDENCE
!-98 (Ry. :-68)
ROM:
T O:
J. F. Farrell - Baton Rouse P. L. Patty - Baton Rouge
PLAINTIFFS EXHIBIT
RMC-460
1
; O P Y:
DATE & SUBJECT:
Messrs: T. M. McCracken, J. A. Williams, F. C. Priest Progress Report - Job 7727 - W/E 5-4-74
May 6. 1974
Barnard & Burk personnel on site - 50
Betz personnel on site
-3
No. time lost to bad weather or labor problems.
Facility 24.0 Started placement o rebar steel and anchor bolts for stack
foundation. Started stripping of forms on combustion chamber retaining wall. Kiln pier "B" footing poured. Started form work for pier "B" walls.
Facllty 35.0
Continued excavation for cooler foundations. Started relocation of existing drainage trench.
Facility 40.0
Installed remaining underground conduit necessary for plant electrical changeover.
Facility 65.0
6" transite water line from deep well pump .completed. Temporary electrical feed to pump completed. Pump energized, well pump out and flow test made.
JFF/gw Attachment - Dally Construction Report
F. Farrell
RMC3300020000014
Facility Y.O Grading and drainage work on construction parting and work areas
completed. Road being built to refractory atoraga area with excess excavated dirt and concrete*
Facility 24.0 Stack bell bottom footings completed. Start foundation 80% complete.
Combustion chamber retaining wall poured* Combustion chamber foundation 65% complete. Kiln pier nB" foundation paused* Off loaded and stored rotary cooler.
Facility 35.0 Excavations started for cooler piers* Relocation of existing drainage
trench begun.
Facility 40.0 Switchgear installed and energlsdd* I4h nafa office and maintenance
building hooked op to new switchgear* Underground cantalt runs for complete electrical plant changeover SOX complete* X&stsllatioa of 1107 power and lighting In switchhoosw complete*
Facility 63*0 6" Transits water line from deep well pump completed and tied into
existing plant main.
FORECASTED WORK FDR MOgg OF KAY
Facility T* 0 8" firewater line will be completed*
Facility 24.0 Stack and combustion Chamber foundation wUl be completed. Complete
kiln pier "Bn. Start kiln pier **An.
Facility 26A.0 Start control house footings*
Facility 35.0 Complete cooler foundations* Partially rtTOOta eodtetlng drainage
trench.
Facility 40.0 Complete changeover of pleat electrical system to new swfttrthouse.
Facility 65.0 Complete this facility and turn over to plant*
R MC3300020000015