INTER-OFFICE MEMO
TENNECO
CHEMICALS,
INC
To
from
Subject
H. H. Duhamel g. W. Leach
AT Burlington at Burlington
MVC Samples Project 70-001
Date February 14, 1969
copy to
H B Carr
F. W. Kanzler
N. or. Quiet
File
I would like to request that your operators, in the Copolymer plant, take MVC samples at three specified points in the monomer inlet system (please see attached sketch). The samples should be taken as close (timewise) to each other as possible. The samples are to be taken at*
1. Cuno filter of virgin MVC 2. Cuno filter of recovered MVC 3. Sample tap, discharge of MVC charge pump. It is important that these samples be taken at 7t00 a.m. on Tuesday, February 18, so that a G.C. analysis can be run on all three samples that day. Mr. Fred Kanzler and myself will be observing the sampling to insure that we have good samples. Three evacuated sample bombs will be furnished.
I have written a maintenance order to install perman ent sampling points at the Cuno filters on the virgin and recovered MVC inlet lines. These should be completed on Monday, February 17.
If you have any questions, please feel free to ask. Thank you.