Document p2RNxVLyY3jaqE9YM9Q0ymDbk

SPECIALTY CHEMICALS DIVISION SOUTH CHARLESTON PLANT ENGINEERING November 7, 1986 RECEIVED NOVI 0f&6 maintenance dept. TO: D. A. Gosselin R. G. Link S. Rossi M. J. Shoger E. D. Southard 0. L. Worstell CC: hi. 0. Bradbury SUBJECT: South Charleston Plant Insulation Upgrade Outline of Project Gentlemen: The Insulation Upgrade Outline of Project (0/P) is attached for your review. This plantwide Insulation Asbestos Upgrade Project is a high-priority Safety/Health Program. The total cost is $3.3W Capital and $1.4MM 838 Expense. Please note that the required Health, Safety, and Environmental review by the Engineering, Manufacturing, and Technology Services Department has been completed and is incorporated into the 0/P. Please return any comments directly to me by November 13. The finalized 0/P will then be transmitted by the Director of Engineering to the functional Vice-Presidents for approval. Please call if you have any questions. \ JFD/wdm Ext. 3469 Attachment 2301G >seph F. Dodd UCC 006704 SOUTH CHARLESTON PLANT ENGINEERING SPECIALTY CHEMICALS DIVISION OUTLINE OF PROJECT SOUTH CHARLESTON PLANT INSULATION UPGRADE SOUTH CHARLESTON, WV November 7, 1986 UCC 006705 OUTLINE OF PROJECT SOUTH CHARLESTON PLANT INSULATION UPGRADE TABLE OF CONTENTS I. 11. III. IV. V. VI. VII. VIII. IX. X. XI. PAGE INTRODUCTION SUMMARY SPONSOR'S OBJECTIVES FACILITIES ENVIRONMENTAL PROTECTION/OCCUPATIONAL HEALTH AND SAFETY CONSIDERATIONS SUPPORTING FACILITIES FROJECT PLAN SCHEDULE COST ESTIMATE A. Summary B. Basis for Estimate C. Cash Flow COST ALLOCATIONS TO DIVISIONS APPENDIX o Health, Safety, and Environmental Review by Engineering, Manufacturing, and Technology Services Department o Division/Profit Center Cost Allocations Summary 1 1 1 2 3 3 4 4 4 5 6 UCC 006706 I. INTRODUCTION Much of the insulation in the South Charleston Plant is asbestos and is in poor condition. Exposed asbestos presents a safety and health hazard associated with airborne particulate asbestos. II. SUMMARY The asbestos insulation throughout the South Charleston must be upgraded to conply with the Occupational Safety and Health Administration (OSHA) standards. The project is estimated to cost $4.7MM over a three-year period: $3.3MM capital and $1.4MM removals 838 expense. The plan is to remove asbestos from idle equipment, replace damaged insulation with an approved type, and seal all remaining asbestos insulation. This project will be implemented over a three-year period with completion in 1989. The justification of this project is Occupational Health. The present OSHA Asbestos Standard, 1910.1001, now specifies 0.2 fibers/cc as the maximum allowable exposure over an eight-hour period. The figure refers to fibers greater than five micrometers in length. III. SPONSOR'S OBJECTIVE The basic objective of this project is to upgrade the asbestos insulation throughout the South Charleston Plant to comply with OSHA Standards. Completion All insulation upgrade to be complete by December 1989. Project is high priority and must be executed on a continuous basis over the three-year period with only curtailment during the bitter cold winter months. Safety/Health All Division Safety/Health Guidelines must be following during asbestos removal/disposal, repair, and covering. UCC 006707 2- - Government Regulations Plant will be in compliance with all applicable OSHA and U.S. Environmental Protection Agency (EPA) Regulations at project completion. IV. FACILITIES The asbestos insulation upgrade encompasses the following units and the work schedule on a priority basis follows: Phase 1 No. 2 Steam Plant Portion Water Treating Unit Phase 2 (Manufacturing Units) Chemical Mixing Upper Island Mainland PVA Resins Solvent Vinyls Polyols Specialty Catalyst Specialty Chemicals Middle Island Oxide Adducts Phase 3 Complete Water Treating Unit Utility Distribution Distribution Bulk Terminal Maintenance Some of the work has already been authorized for removing asbestos insulation from idle equipment and lines; the work is not part of this major capital project. These projects are listed below: Project Approval Cost Status No. 2 Powerhouse Solvent Vinyl Resins Specialty Chemicals Division Units Upper Island Chemical Complex Oxide Adducts 10/85 1/86 1/86 Total $111,000 17,000 182,000 Complete Complete On-going 26,000 WOR To Dan 10/9/86 100,000 WOR to Dan by 11/13/86 $436,000 UCC 006708 -3- V. ENVIRONMENTAL PROTECTION/OCCUPATIONAL HEALTH AND SAFETY CONSIDERATIONS This project will correct an Occupational Health concern by replacing or sealing exposed asbestos insulation throughout the Plant. When the insulation is being replaced or removed, Safety and Health Guidelines will be followed which includes: installing rope barricades and clearing the area of plant personnel, posting of warning signs, proper bagging and disposal of insulation, and monitoring of surrounding work areas. In addition, assuring that contractor personnel adhere to guidelines such as: wet clean-up, wearing of appropriate respirators, wearing and disposal of proper protective clothing, etc. This project will be in compliance with all applicable OSHA and EPA Regulations. The EPA will be notified that the removal of asbestos insulation could occur at the South Charleston Plant. The required Health, Safety, and Environmental review of the project was completed on October 30, 1986, by the Engineering, Manufacturing, and Technology Services Department; the project is endorsed contingent upon the following: 1. Maintenance Procedure XVIII Provisions for Asbestos Material Removal and Disposal Safety will be revised to be in compliance with the latest OSHA Standard 29 CFR 1910.1001. 2. Procedure XVIII will be revised in accordance with the environmental concerns listed in the review. A copy of the complete review is attached in the Appendix section. VI. SUPPORTING FACILITIES A. Distribution The project will have no effect on Distribution facilities. B. Energy Systems The project will have no effect on Energy Systems requirements. However, Energy Conservation will be improved with this insulation upgrade. C. Safety and Environmental Considerations See Section V above. UCC 006709 -4- VH. PROJECT PLAN The project survey, or scope, was prepared by the Maintenance Department over the last year. The priority of work is shown in the Facilities Section on page 3. Insulation specification consultation will be supplied by Engineering. Field construction by an outside contractor or the Central Engineering Construction Group, will be supervised by the Maintenance Department. Project Management, including cost control and reporting, will be provided by Plant Engineering. The project organization follows: Steering Committee Assistant Plant Manager Maintenance Superintendent General Project Manager Project Team Maintenance Coordinator/Supervisor Project Manager S. Rossi J. R. Dement J. F. Dodd L. B. Hewitt J. R. Maier VIII. SCHEDULE Key dates are: Outline of Project Approval C8P Approval Mechanical Completion December 1986 February 1987 December 1989 IX. COST ESTIMATE A. Summary o Labor o Materials o Engineering/Maintenance* o Contingency Total Capital $1,950,000 860,000 160,000 330,000 $3,300,000 838 Expense $1,140,000 50.000 70.000 140,000 $1,400,000 * Insulation specification consultation, project management and field coordinator of contractor. UCC 006710 -5- B. Basis for Estimate The estimate for the Phase I work is based on a detailed scope and budget pricing obtained from a local insulation contractor. The remaining work is based on an insulation survey of each operating unit and estimating the associated man-hours and materials required. The total man-hour estimate is 101,000 hours of work. C. Cash Flow Capital 838 Expense 1987 1988 1989 $1,100,000 ,1,100,000 1 100,000 $ 466,000 466.000 468.000 Total $3,300,000 $1,400,000 X. COST ALLOCATIONS TO DIVISIONS The project costs are allocated to tenant divisions based on the 1987 plant period cost allocations furnished by the Plant Controller. For example, costs for insulation work on steam lines in the Energy Systems area would be allocated plantwide to those profit centers on a steam usage basis. The overall project allocations to divisions follows: Division Percent ______ Costs Capital Expense Specialty Chemicals Solvents & Coatings Industrial Chemicals 75.12 21.80 3.08 $2,479,000 720.000 101.000 $1,052,000 305,000 43,000 Total 100.00 $3,300,000 $1,400,000 These costs are spread equally over three years (1987, 1988, and 1989). The individual profit center cost breakdown for each division is shown in the Appendix section. JFD 11/07/86 2301G UCC 006711 6- XI. APPENDIX UCC 006712