Document omKv7a3ROZD5QmbVKR4GRXRoo

To From Date Subject J. D. Burns J. D. Minott October 6, 1971 Environmental Health Report Continental VCM Plant A. Status of Active Budget Items 1. Primary Treatment System Revisions It has been decided to build an arched acid brick roof in the T-252 pit to repair it. The material has been ordered and forming work is underway on the required concrete changes. Completion of repairs should be during November 1971 and the system will be started up immediately upon completion. The top of the steam stripper tower was inspected during the month and no damage or corrosion was noted. Piping for the stripper bottoms cooler has been ordered and the cooler has been set. It will be operational when the steam stripper system is started up in November. 2730 gallons of slop EOC were hauled from the plant this month. 2. Secondary Waste Treatment System Excavation and underground piping are still about 85% complete due to extensive rain this month. The clarifier floor and walls have been poured and also the instrument shed floor. Electrical work is about 15% complete and the main power feed has been brought into the site area. The in-plant neutralization system is 60% complete with only electrical and instrument work remaining. Completion of this project still appears to be in late December. 3. C-500 Venturi Scrubber The system was put in operation on August 27 and on August 30 the spray nozzle of the scrubber failed and blew into the C-500 tower. The system is still operating (at part efficiency) since some scrub bing occurs even with a solid water jet instead of a cone spray. The nozzle vendor is redesigning the spray nozzle so that a new unit can be installed during the next plant shutdown. The pH of the T-2 pit water has dropped to 1.3 compared to about a 2.5 pH seen before the scrubber was installed. This would calculate out to 242 Ibs/hr. of HCl removed from the C-500 vent stream .(about 49%). A single test for organic removal showed 12% of the EDC and 2.3% of the ethyl chlo ride in C-500 were also scrubbed out. All of these efficiencies should improve when the new spray nozzle is installed early in 1972. CCR 000060362 4. Copper Removal System The copper removal system (used during catalyst turnarounds only) trenches and mixing basin are complete* New double size filter bags have been ordered for the filter system. The only remaining work is some minor piping work which should be done during October, This system is essentially operable now if required. Some process engi neering work is continuing on methods of improving the Cu(0H)2 sludge filterability, such as filter aids or polyelectrolytes. B. Current Developments 1 Analytical Work The last of the special tests on the plant effluent and well waters have been completed by Ponca City R & D. The data showed less than 1 ppb mercury, under 1 ppm cyanide, 1.0 ppm lead, and about 3 ppm oil and grease. Plant analysis has shown that all of the sulfide, magnesium, aluminum, manganese, and most of the iron and copper in the plant effluent come from the well water feed. Cobalt, nickel, zinc, chromium, calcium, sodium and cadmium are being added by plant operation. Additional well water COD tests have confirmed a COD of around 5 ppm for the well water system. Phenol levels are higher than originally expected, (about 1.0 ppm) and apparently come from the plant operations. Daily effluent samples were taken during September for 25 out of 30 days and checked for organics. The EDC content averaged 1673 ppm with a range from 831 to 3373 ppm. At an estimated 200 gpm flow rate, this would be about 4000 Ibs/day of EDC in the effluent water. 2. 1899 Refuse Act - part B The completed supplemental form was mailed to Dr. Sharrah on Septem ber 10 and was received by the Corps of Engineers on September 23, 1971. On September 6, 1971 another form was received from the EPA requesting special data on capital costs, labor requirements, and operating costs on all pollution equipment from 1966 thru 1976. Work on this new form (reply to this form is voluntary) should be completed by the end of October 1971. John DD. Minott Senior process Engineer jb CC: LNV-DOP-RDG-RHG-PLF-GDJ CCR 000060363 Date 0500 VENT STACK ANALYSIS September 1971 EDC VCM IN PPM BY VOLUME Other Et Cl Organics ci2 HCl Oxidants C2 IN VOLUME % Plow in CO 2 ch4 c2H4 C2H6 scfh 9/1/71 9/3/71 9/4/71 9/5/71 9/6/71 9/7/71 9/8/71 9/15/71 9/29/71 4017 12,200 5687 4957 2568 3708 4620 2435 3528 362 420 750 719 2600 800 1500 332 540 3685 3500 3365 3426 3800 3500 3500 2890 5520 12,800 5584 4503 6100 9400 12,500 8691 515 6 3704 3 217 17 5728 20 15,012 - 5061 - 12,666 15 1234 - 5673 30 4765 2765 Nil 2790 11,111 1432 2049 ( 1975 4444 5925 1.7 1.06 1.82 1.65 2.00 2.50 2.20 1.32 1.19 1.0 0.20 0.12 Nil 0.10 1.80 1.50 0.25 0.26 2.0 8.04 2.20 1.80 2.23 2.80 2.70 1.60 1.92 Nil 0.50 0.12 0.13 0.10 0.32 0.36 0.13 0.11 0.6 6.17 0.74 0.73 1.40 1.20 1.20 0.81 0.21 Nil Nil Nil Nil Nil 0.03 Nil Nil Nil 624,800 o o 30 o o o o O' 0 UJ O01' ater Sampling r Samp1ing rimary Water Treatment ;condary Waste Treatment -500 prescrubber ?pper Removal System jw Pressure Con densate Collection System ry Crude Tank Fume Scrubber jLop Caustic Collec tion System romate Removal System iw Exchanger for C-101 99C090000 ^500 ENVIRONMENTAL HEALTH PROJECTS - VCM PLAN* January 1st Quarter January to December April _________ 2nd Quarter 1971 July 3rd Quarter Process Engineering and Laboratory October 4th Quarter Process Engineering and Laboratory ^ Rebuild of Steam Stripper Install Oil Skimmer^ n,i. i ...........M.i 11 -I-- - - ~'y !. CED Design Work iin--n-- - ' fc M i i1 - ' * ^ : '--~ `~~Furceasing Purchasing . Startup Construction ------------- Construction _ inmiwi i~r--;--m~ Repair Damage ,, Purchasing. Finish Construction ,'H --|>*Cpip^mnia-- Construction^ ^ Tie-ins Rebuild Roof Startup -> Replace: Spray Nozzle Purchasing Construction Purchasing t: Engineering Construction it Testing Startup Estimate ta------------- Purchase .. Mechanical Engineerin Construction "TM--r-r