Document omKv7a3ROZD5QmbVKR4GRXRoo
To
From Date Subject
J. D. Burns
J. D. Minott
October 6, 1971
Environmental Health Report Continental VCM Plant
A. Status of Active Budget Items
1. Primary Treatment System Revisions
It has been decided to build an arched acid brick roof in the T-252 pit to repair it. The material has been ordered and forming work is underway on the required concrete changes. Completion of repairs should be during November 1971 and the system will be started up immediately upon completion. The top of the steam stripper tower was inspected during the month and no damage or corrosion was noted. Piping for the stripper bottoms cooler has been ordered and the cooler has been set. It will be operational when the steam stripper system is started up in November.
2730 gallons of slop EOC were hauled from the plant this month.
2. Secondary Waste Treatment System
Excavation and underground piping are still about 85% complete due to extensive rain this month. The clarifier floor and walls have been poured and also the instrument shed floor. Electrical work is about 15% complete and the main power feed has been brought into the site area. The in-plant neutralization system is 60% complete with only electrical and instrument work remaining. Completion of this project still appears to be in late December.
3. C-500 Venturi Scrubber
The system was put in operation on August 27 and on August 30 the spray nozzle of the scrubber failed and blew into the C-500 tower. The system is still operating (at part efficiency) since some scrub bing occurs even with a solid water jet instead of a cone spray. The nozzle vendor is redesigning the spray nozzle so that a new unit can be installed during the next plant shutdown. The pH of the T-2 pit water has dropped to 1.3 compared to about a 2.5 pH seen before the scrubber was installed. This would calculate out to 242 Ibs/hr. of HCl removed from the C-500 vent stream .(about 49%). A single test for organic removal showed 12% of the EDC and 2.3% of the ethyl chlo ride in C-500 were also scrubbed out. All of these efficiencies should improve when the new spray nozzle is installed early in 1972.
CCR 000060362
4. Copper Removal System
The copper removal system (used during catalyst turnarounds only) trenches and mixing basin are complete* New double size filter bags have been ordered for the filter system. The only remaining work is some minor piping work which should be done during October, This system is essentially operable now if required. Some process engi neering work is continuing on methods of improving the Cu(0H)2 sludge filterability, such as filter aids or polyelectrolytes.
B. Current Developments
1 Analytical Work
The last of the special tests on the plant effluent and well waters have been completed by Ponca City R & D. The data showed less than 1 ppb mercury, under 1 ppm cyanide, 1.0 ppm lead, and about 3 ppm oil and grease. Plant analysis has shown that all of the sulfide, magnesium, aluminum, manganese, and most of the iron and copper in the plant effluent come from the well water feed. Cobalt, nickel, zinc, chromium, calcium, sodium and cadmium are being added by plant operation. Additional well water COD tests have confirmed a COD of around 5 ppm for the well water system. Phenol levels are higher than originally expected, (about 1.0 ppm) and apparently come from the plant operations.
Daily effluent samples were taken during September for 25 out of 30 days and checked for organics. The EDC content averaged 1673 ppm with a range from 831 to 3373 ppm. At an estimated 200 gpm flow rate, this would be about 4000 Ibs/day of EDC in the effluent water.
2. 1899 Refuse Act - part B
The completed supplemental form was mailed to Dr. Sharrah on Septem ber 10 and was received by the Corps of Engineers on September 23, 1971. On September 6, 1971 another form was received from the EPA requesting special data on capital costs, labor requirements, and operating costs on all pollution equipment from 1966 thru 1976. Work on this new form (reply to this form is voluntary) should be completed by the end of October 1971.
John DD. Minott Senior process Engineer
jb CC: LNV-DOP-RDG-RHG-PLF-GDJ
CCR 000060363
Date
0500 VENT STACK ANALYSIS September 1971
EDC
VCM
IN PPM BY VOLUME
Other Et Cl Organics
ci2
HCl Oxidants
C2
IN VOLUME %
Plow in
CO
2
ch4
c2H4 C2H6
scfh
9/1/71 9/3/71 9/4/71 9/5/71 9/6/71 9/7/71 9/8/71 9/15/71 9/29/71
4017 12,200
5687 4957 2568 3708 4620 2435 3528
362 420 750 719 2600 800 1500 332 540
3685 3500 3365 3426 3800 3500 3500 2890 5520
12,800 5584 4503 6100 9400
12,500 8691 515
6 3704 3 217
17 5728 20 15,012
- 5061 - 12,666 15 1234 - 5673
30 4765
2765 Nil
2790 11,111
1432 2049 ( 1975 4444 5925
1.7 1.06 1.82 1.65 2.00 2.50 2.20 1.32 1.19
1.0 0.20 0.12
Nil 0.10 1.80 1.50 0.25 0.26
2.0 8.04
2.20 1.80 2.23 2.80 2.70 1.60 1.92
Nil 0.50 0.12 0.13
0.10 0.32 0.36 0.13 0.11
0.6 6.17 0.74 0.73 1.40 1.20 1.20 0.81 0.21
Nil Nil Nil Nil Nil 0.03 Nil Nil Nil
624,800
o o
30
o o o o O' 0 UJ O01'
ater Sampling
r Samp1ing
rimary Water Treatment
;condary Waste Treatment
-500 prescrubber
?pper Removal System
jw Pressure Con densate Collection System
ry Crude Tank Fume Scrubber
jLop Caustic Collec tion System
romate Removal System
iw Exchanger for C-101
99C090000 ^500
ENVIRONMENTAL HEALTH PROJECTS - VCM PLAN*
January 1st Quarter
January to December April
_________ 2nd Quarter
1971
July 3rd Quarter
Process Engineering and Laboratory
October 4th Quarter
Process Engineering and Laboratory
^ Rebuild of Steam Stripper
Install Oil Skimmer^
n,i. i
...........M.i 11 -I--
- - ~'y
!. CED Design Work
iin--n-- -
' fc M i i1 -
' * ^
: '--~ `~~Furceasing
Purchasing
. Startup
Construction
-------------
Construction
_ inmiwi
i~r--;--m~
Repair Damage
,, Purchasing.
Finish Construction ,'H --|>*Cpip^mnia--
Construction^ ^ Tie-ins
Rebuild Roof
Startup
->
Replace: Spray Nozzle
Purchasing
Construction
Purchasing t:
Engineering
Construction it Testing
Startup
Estimate
ta-------------
Purchase ..
Mechanical Engineerin
Construction
"TM--r-r