Organic Chemicals Division CAPITAL PROJECT SCHEDULE
Project Name and Number: OC 3007 Lead Dust Ventilation and Material Handling Renovation EP 20
Approximate Cost: $275,137
Location: Chicago
Date of Issue: 4/10/78 Supersedes: 10/1/77 Issued By: F. B. Dorf
Description (in c l u d in g a p p r o x ima t e c a p a c it y ): Reduce airborne lead dust by improved material handling and ventilation in Chicago plant.
Objective (in c l u d in g e c o n o mic s ): Redesign and upgrade facilities to meet OSHA require ments for airborne dust abatement.
Distribution:
M,, D. Cover W. A. Fead G. A. Forlenza H. C. Gaffney H. H. Hofmaier G. R. Koehler F. C. Schmelz H. G. Thompson R. L. von Glahn B. G. Witherspoon
Special Considerations:
EPA is setting a standard for lead in the atmosphere. Plans are made to measure lead emitted from the plant vents and stacks after completion to determine if any hygiene problems are posed to the surrounding neighborhood.
Checkpoints Overrun
Mechanical Completion Close Out Job
Responsibility Strategy Board
Gaffney Gaffney
Dates:
Start
End
9/8/77
6/1/78
Remarks:
Additional funds of $59,000 approved for more extensive renovation of old dust collectors and doubling the size of the stack sampling study - 0C 3007-R1.
Compliance schedule with OSHA.
6/30/78
kmc/P 171
This schedule represents available information and judgment estimates at the time issuance. For changes or corrections, notify the issuer (or F. C. Schmelz BB X3777 or W. A. Fead BB X2775).