Document oDqX5qMNvx4qKa3Y5j8YR3xL3
720
CHAPTER 68
1962 Guide And Data Book
blast coding. This method of cooling aggregates has been com ing into greater use as time goes by, due to several assumed advantages over the other precooling systems. One of the advantages is that it does not require any particular changes to the materials handling set-up or additional tanks for in undation. The actual aggregate cooling is accomplished by blowing cold air through the aggregate in the batching bins. Also by introducing heating means, the air cycle used in cooling can be used in heating aggregates during the cold weather. Other apparent advantages are the fact that cooling effect is not limited by the quantity of mix-water specified. Cooling ia applied at the final stage of handling aggregates and does not increase the moisture content of aggregates. However, the inundation method provides a positive means' of keeping moisture content always relatively constant.
Cement and Sand Cooling
As specifications continued to require lower and lower pour temperatures, it became more apparent that direct methods for cooling sand and cement (which cannot be cooled by either the air blast or inundation and spray methods) would . be of great help in obtaining the overall system heat removal required. On several recent installations, attempts have been made to accomplish this cooling by the use of hollow flight screw conveyors in which chilled water is used to cool the hollow flights. As yet, not enough experience has been ob tained in this method of cooling to determine its effectiveness and economy. In any event, it does not seem likely that too much heat removal could be accomplished by this method, . since cooling of either of these components below the wet-bulb temperature could result in condensation and serious handling problems. Condensation bringing excess moisture into the sand would undoubtedly cause it to clog in the screw con veyor; but condensation talcing place in the dry cement be fore it was introduced into the mixer could be a very serious and dangerous problem, resulting possibly in the actual cementing up of the conveyor.
Vacuum Cooling
A fourth development in the technique of precooling ag gregates is a proprietary system which uses a vacuum system to evaporate the surface moisture on the aggregate and there by reduce the temperature of the aggregate.
DESIGN CRITERIA FOR REFRIGERATION SYSTEMS FOR CONCRETE PLACEMENT
As indicated above, there are a number of different sys tems from which a selection could be made in deciding upon the type of cooling which could be used on any particular installation. As a matter of fact, where the total yardage of concrete is relatively small and where mechanical installations cannot economically be set up in connection with the miring plant, ice manufactured by existing commercial ice plants has been used satisfactorily on a number of occasions. For larger installations, plant selection is dependent on a number of factors, including the following:
(a) Normal pouring rate--cu yd per hr. (b) Maximum pouring rate--cu yd per day. (c) Total allowable mixing water in lb per cu yd. (d) The required concrete placement temperature. (e) Concrete temperature when coming from the mixer.
Hie difference between this and (d) is the estimated rate of gain of heat by radiation during transporting from mixer to final placement. . (f) Average ambient temperature during period of maxi-
mum placement. Generally speaking, the period of maximum rate of placement will be during the summer month* of June, July, August and possibly September, because in most tem perate zones this is when the best progress can be made on construction work. The average temperature of the aggregates will assume the mean ambient temperature of the air (this includes night and day), during tire period of maximum placement and for an estimated period dependent on the amount of aggregate storage specified or available. It is cus tomary on the larger dams for the agency writing the speci fications to specify the-minimum amount of storage capacity to be provided. Basically, the minimum requirement b stipulated to insure continuity of concrete placement hoiild there be any interruption in the supply of the aggregates from whatever source it is being furnished.
However, if the minimum live storage specified is, for instance, 100,000 tons of aggregates; and the pouring rate is 2000 cu yd per day, this would mean the consumption of approximately 3800 tons of aggregates per day. If the job b working a 6 day week, this would provide 26 days of actual storage in place, or approximately one month's live storage. Under these conditions, we can assume that the temperature of the rock when delivered into the reclaiming tunnel will be equal to the average ambient temperature for the mouth preceding that particular day on which the aggregate is trans ferred from the storage piles to the reclaiming utnnnl,
GENERAL CONSIDERATIONS FOR
SELECTING A SYSTEM
In the light of recent developments in various types of installations, it is obvious that considerable analysis and study is necessary to determine the most satisfactory method for each particular condition and specification. Initial cost, satisfactory operation, and degree and flexibility of control must be considered in deciding whether to use the inundation system, plus the use of ice in the mix (such as was used on the Buggs Island Dam), or the use of the air blast cooling plus the use of chilled mix water, and the addition of ice when necessary in the mix.
Where the aggregate cooling range from initial to final temperature of the mix is relatively small (15 to 20 F deg at the most) or where the required pour temperature ia rela tively high (65 F or more), chilled water plus ice in the mix, or chilled water plus air blast on the larger aggregates, may be able to take* care of the entire cooling load. When the overall temperature reduction is greater than this, or lower pour temperatures are specified, such as 50 F or less, it is almost certain that a combination of all three types of cool ing will be required because only a limited amount of heat removal can be obtained by one of these methods alone. Cool ing by ice and chilled water is limited by the amount of mix water specified- Cooling by air blast alone is limited by the entering air temperature, which must be maintained high enough to prevent coil frosting. Cooling by inundation, al though it involves the necessity of relatively large inundation tanks does offer the most positive and sure method of cooling, plus a positive degree of control of surface water on the coarse aggregates. By the addition of ice into the mix to take the remainder of the heat balance, there is a very satisfactory degree of control of the aggregates mwnfnr as Mending in the mix is concerned and of the exact amount of water introduced by the inundation and the ice.
DESIGN. CONDITIONS
In order to illustrate the principles involved in the selec tion of a refrigeration plant and the mathematics involved
in working out its application, the following is based on an
Concrete Dams, Sub-Surface Soils and Foundations
721
arbitrary set of conditions which were set up as a typical me^inm sized installation. The assumed conditions set forth hiow involve a system with a high enough cooling range and a low enough pour temperature to require a combination of at least three basie systems, such as inundation, or air blast and chilled water, plus ice. The source of these design conditions is a combination of ambient conditions (Weather Bureau), rate of pour (Contractor) and ultimate result specified (Using
Agency):
aggregate from 90 F, using 35 F water, to the temperatures indicated was as tabulated below.
Assumed Typical Conditions
1. Normal pour rate, based on three 4 cu yd mixers with 3 min to the batch giving a rate of 240 cu yd per hr.
2. Maximum pour rates (in cu yd per day); 4800 cu yd per day (20 work hr per day).
3. Total mix water allowing 8 gal per sack, three sacks to the eu yd: 24 gal or 200 lb of water per cu yd.
4. Concrete placement temperature, 55 F. 5. Concrete temperature from mixer, 50 F. An arbitrary allowance of 5 F deg was made for rise in temperature after the concrete leaves the mixer until its time of final placement, litis temperature difference will vary somewhat dependent upon the tinv> of emptying of the mixer and placement of the concrete in the forms. The actual amount of radiation can be accurately com puted but a rise of 5 F deg is an adequately safe allowance under normal conditions. Under ideal conditions it will probably be somewhat less than 3 F degrise. 6. Average ambient temperature and aggregate temperature during period of maximum rate of placement, 80 F. 7. Additional cooling load, if any (such as cooling pipes in monolith, etc.).
For purposes of illustration, it is assumed here that tire engineers may want 500 gpm cooled from 65 F (assumed river, temperature) to 40 F and pumped through the thin wall tubing in the monoliths, giving:
500 X 8.33 (65 - 40) = 520 tons
200
The first step in computing the loads for which to design the refrigeration plant is to draw up a table listing the various ingredients in the mix and calculating the total beat to be re moved.
The next step in planning the refrigeration plant is deter mination of the size and type of bins in which the aggregate ia to be cooled.
inundation Tanks
With the inundation system for precooling aggregates, generally the three largest sizes of aggregates are placed in large cylindrical tanks. It has been felt practicable to have two complete sets for each of the three sizes, making six tanks in all. The proposed cooling tanks, loaders, unloaders, chutes, screens and conveyor systems from the tank* into the concrete plant should be enclosed and cooled to 40 or 45 F by air-conditioning units with blowers placed at appropriate
points in the housing around the tanka and conveyors. The Bull Shoals job, being the first to use the inundation method for. precooling aggregates, posed a new problem which (although it had been theoretically solved before) had never
*chxally been solved in practical experience. V. L. Peugh, to gether with Ivan Tyler, at Morris Dam wrote a paper ein LUed Mathematical Theory of Cooling Concrete Aggregates. The original studies were made in 1934, and mathematically
efennined by spherical calculus the problem length of time Pessary to cool various sizes of rock to the core of the rock
on temperature to another. The calculations were borne ut to a remarkable degree of accuracy in pilot tests con ducted for the Bull Shoals Dam. The calculations by Peugh
"Cheated that the time required to cool the various sizes of:.
This study indicates that an immersion period of 25 min
will bring even the cobbles down to an average temperature
of 45 F. Theoretically, the smaller sizes can be brought to a
much lower temperature in less time. Practical considerations,
such as the rate at which cooling water nan be pumped, make
it unlikely that a cooling period less than 30 min should be
considered. Any excess cooling will provide a needed factor
of safety.
Pilot tests conducted by Royal McShea for the Bull Shoals
Contractors brought out the graphical corroboration of
Mr. Peugh's computations (Fig. 1).
However, the limiting factor on the overall cycle, as there
had to be a very definite proportion between the various
at all times, was the cooling time for the largest size aggre
gate, which implied a cooling period of nearly 45
plus
about 15 min for loading and unloading.
Tabulated actual pilot test results compared with V. L.
Peugh's theoretical computations for cooling time*? of cobbles
indicate the following (using 35 F cooling water):
Time (minutes)
0 5 10 20 30 40 50 60
Measured Temp, F
103 101 91 64 51 44 40 37
Theoretical Temp, F
a* = 0.07
a* - 0.08
102 102
101 101 96 94
76 73 56 51 45 41 39 36 .
36 34
Note that a* it the diffusivity constant of. the material under consideration,- and is equal to conductivity/(specific heat)' (density). To determine the value of this constant for a typical piece ofaggregate, a cobble of8A in. diameter, as nearly spherical as could be found, was selected and a small resistance thermome ter placed in the center by drilling a small hole infrom one side, filling the hole with mortar after the thermometer was in place. The cobble teas brought to a uniform temperature by immersion in warm water, and teas then placed in an ice bath in a home- made calorimeter. During its cooling period the temperature was read at five minute intervals.
BIN SELECTION AND CRITERIA FOR
AIR BLAST COOLING
The size of the compartmented bins (octagonal bins) above the concrete mixers is usually determined by having an ampin factor of safety from a materials handling standpoint so that if there were aoy supply breakdowns, the concrete mixing plant would not be shut down before a particular pour could