INTEROFFICE COMMUNICATION Westlake, Louisiana November 25, 1969 TO: subject: Mr. R. L. Hyberger HCI-EDC Pipeline Enclosed are the process description, equipment specifications, and P&l diagram for the EDC-HCl pipeline. As an HCI pipeline this line has a capacity of 30 tons per day. Changing the control valve and orifice run will increase the capacity to 100 tons per day. As an EDC line we will have a maximum rundown rate of 100 gallons per minute. RWC-MC cc: LNV RHC5 JDM^ DKP WOM WRB RAJ Each w/enclosure R. W. Churns Process Engineer VCM Plant CCR 000034119 Process Description HCl-EDC Line VCM Plant This pipeline is designed to carry HCl to Ancon at an initial flow rate of 1 to 10 tons per day. At 20 tons per day the orifice and control valve must be changed. To go to the maximum rate of 100 tons per day the control valve trim must be changed and the orifice run must be increased from 2 inches to 3 inches. This pipeline can later be used to fill tank T-415 at the docks. Tie-ins will be made connecting the east end of this line with the cyclohexane rundown line and connecting the west end with the EDC tank car loading line. This line can transfer 100 gallons per minute of EDC from either the pure EDC storage tank or the sales EDC storage tank to the dock tank. CCR 000034-120 Temperature Recorder Specifications EDC-HCl Pipeline VCM Plant Instrument No. Service Inst. Type Location Range, F Element Type Location Temperature, F Pressure, psig * TR-1 HCI vapor to Ancon Temperature Recorder Ancon control room 0) -25 to +125 Foxboro Model 12-A 4" line upstream of FR 60 50-115 On two pen recorder with PR-1 CCR 000034121 Pressure Recorder Specifications HCI-EDC Pipeline VCM Plant Inst. No. Service Inst. Type Location Range (psig) Element Type Location Temperature Pressure PR-1 HCI vapor to Ancon Pressure Recorder Ancon Control Panel (1) 0-150 Foxboro Model 44 Upstream of Orifice Ambient 50-115 psig (1) On two pen recorder with TR-l CCR 000034122 Pressure Gauge Specifications HCI-EDC Pipeline VCM Plant Instrument Number Range, psig Location Operating pressure, psig Service Type Pl- 0-160 On strainer bypass 110 Strainer differential Bourdon tube CCR 000034123 Flow Controller and Recorder Specifications HCl-EDC Pipeline VCM Plant Instrument No. Service Instrument Type Location Range, " H2O Max. chart, sq. rt. Element Type Orifice size, in. Pipe size, in. Valve Type Location Valve body size Valve Trim Size Maximum pressure drop Air failure position Steam through valve Temperature Pressure, psig MW Wt. Percent Vapor In-Out Rate, Maximum tony'day FRC-1 HCl Vapor to Ancon Flow Recording Controller Ancon Control Room 50 200 10 10 Orifice 0.778 2.067 Orifice 1.289 2,067 Microflute 0) Ancon Battery Limit 3/4" 2" 1/2" 1-5/16" (2) 125 psi 125 psi closed closed HCl vapor Ambient 115 36.5 100-100 10 103 100-100 60 (1) Fisher type 667 EC, equal percentage (2) Can be changed to 2-5/16" trim for 100 T/D CCR 00003*12* Type Service Size Material Particle Size Screen material Filter Specifications HCl-EDC Pipeline VCM Plant Armored Knight Bucket Strainer HCI vapor to Ancon , 4> Carbon Steel Body 100 micron 304 SS 0003tUs Remote Operated Valve Specifications HC1-EDC Pipeline VCM Plant Operator Type Action Control Supply Air Solenoid Valve Tufline No. 7020 Closes on air and/or electrical failure. Electrically operated pushbutton More than 80 psig 110 VAC-60 cycle explosion proof 3" bail. CCR 000034126 Work List HCI-EDC Pipeline VCM Plant1 1. Run the 4" pipeline from the VCM Plant battery limits to the Methyl Chloride Plant battery limits. 2. Tie this line to the existing 3" vapor return line for the liquid HCl loading system. 3. Tie the 3M vapor return line to the high point bleed in 8" CVC-1208. (Make permanent tie-in on next oxy shutdown.) 4. Run lead wires to a pushbutton for the Tufline operator. 5. Tie the 2" line into the HCl feed line in the Methyl Chloride Plant. 6. Install PR-1 and TR-1 and FRC-1 in the Ancon control room. 7. install a line from the cyclohexane line to the docks to the easternmost point on the HCl line. Blind both ends. 8. Install a line from the EDC tank car loading spot to the HCl ine at the VCM Plant battery limit. On the next oxy shutdown: 9. Connect the western end of the HCl line to 8" CVC-1208. To convert to EDC service; 1. Depressure the entire line and blow clear with nitrogen. * 2. Blind the junction between the HCl vapor return line and the new EDC-HCI pipeline, 3. Connect the EDC line to the tank car loading line. Connect the EDC line to the HCl line. CCR 000034127 4. Tie in the HCI I in to the cyclohexane line. 5. Connect the cyclohexane rundown line to the suction line of the EDC loading pump. (CCR 000034128