Document npypXROmL4Zp2VrenLzk16n1a
Central* Engineering
l||piP^jE^RA'Ripl^NT-j`'
CEA NO.
1430
PRODUCT
PROGRESS REPORT
AR NO.
date
#
-- Nov. 17.
19fi7
TITLE
Aroclors
~
:------------------------
Increase Aroclor Capacity
DISTRIBUTION CED SECTION MANAGER
ced project manager
R. P* SteVenS R. W. Peterson
DIVISION
Organic
PLANT
Anniston
Dl vision representative
W. F. Taffee
J. M. Depp
.
M. Dmytryszyn
R. E. Emling
F. W. Enoch
F. J. Holzapfel
R. W. Kaltenrieder
F. P. LaBelle
R. E. Lenz
Russell L. Miller
E. Negro
C. L. Parish
A. B. Terry
(2)
ORGANIC DIVISION
a.H. C. Carder ,Cresce'*5 R. J. Stratmeyer H. L. Williams
W. J. Burkett R. R. Cook/J. R. Fullgraf R. E. Howard
SCOPE
Aroclor production facilities at Anniston will be expanded by the addition of tankage for storage and for the preparation of blends, drumming facilities in a new building (to be expanded on another project, CEA 1452, into a product warehouse), new and larger flakers for solid Aroclors and for biphenyl in the same building, and packaging equipment for flaked products. Tank truck loading and a new track spur with tank car loading and unloading facili ties are included.
DSW 200671
' w. C O N F I O E N T 1 A L . I N F O R M A T I O N
THIS DOCUMENT IS THE PROPERTY OF MONSANTO COMPANY AND THE RECIPIENT IS RESPONSIBLE FOR ITS SAFEKEEPING AND DIS POSITION. IT CONTAINS CONFIDENTIAL INFORMATION WHICH MUST NOT BE REPRODUCED. REVEALED TO UNAUTHORIZED PERSONS OR SENT OUTSIDE THE COMPANY WITHOUT PROPER AUTHORIZATION.
CE- 14
STLCOPCB4058735
Product
Aroclors______________________________
Location______ Anniston
Title_______ Increase Aroclor Capacity______________________________________________
Data Tabulated As Of October 31 , 1967
CEA No
1430
AR No.
Appropriation Current Estimate Date of Estimate Expended & Committed Spent This Month Scheduled Completion On Schedule?
M J To the bd for approval.
MS 1,400
Process Design, % Complete
September 14, 1967
Mechanical Design, % Complete
MS 124.3
Construction, % Complete
MS 21.3
% Expended & Committed
October 1, 1968
Design Manpower
See Below
Construction Manpower
--
Last Month 60 7
--
2 1 --
This Mo. 65 20
--
9 3 --
SUMMARY:
The tank farm portion is ready for firm design. We are just be ginning the flaking-packaging area, which is to be coordinated with warehouse project CEA 1452. Some design momentum was lost due to the illness of the Project Manager. We will reevaluate our schedule, position by next report.
Tank Farm
This area is fairly well defined, A study model was made and comments were received from the plant representative. These items are mostly reconciled and work on the finished model is underway except for the blending area. Top product quality and non-contamination between pro ducts are imperative for Aroclors. A number of details toward this end are under study.
The tanks are on order. Pumps and filters are nearly ready.
Flaking-Packaqing
0
Layout of this area has begun. A number of points on how this area can be coordinated with the adjacent warehouse project (CEA 1452) have been proposed to the3plant. Definition of the flaking and filling area has been delayed by the illness of the Project Manager and the need to re lease the tank farm for firm design.
The Aroclor flaker is on order.
Production Area Tie-in
Due to urgency of the above item, we will defer this area for two months. We expect to use photo drafting for much of this.
Site Preparation
'
A sanitary lift station has been ordered and construction of its force main authorized.
The Division has been informed that resolution of an area sewer problem
(36" sewer failure) not on this project may limit our ability to do
field work on the warehouse-packaging building.
.
4-
R. W. Peterson Acting Project Manager vo
DSW 200672
STLCOPCB4058736