Document npZyqZNJQ5zXvKm1eOGn3wEVX

St. louls Organic Research Department March 28, 1962 VAPOR PRESSURE AND THE: STABILITY APPARATUS FO: ORGANIC RESEARCH - 2 You will recall that at the laBt project review on thermoflulds the time estimates for the construction and testing of the vapor pressure and thermal stability apparatus were uncertain. Since that time, a preliminary design conference has been held and the following tentative echedule was developed. Detailed design of Instrument by Dr. W. N. Trump March 25 to April 15 Ordering of components with , critical delivery dates April 1 Delivery of all components completed May 25 Construction of Instrument completed June 22 Testing of instrument completed July 6 Training of analytical lab representative completed and instrument operating In plant control lab July 27 These target dateB are compatible with other commitments of the Oeneral Physical Chemistry and Instrumentation Groups. W. E. Koemer dm HARTOLDMONOOQ4763