Kaiser Engineers Weekly Field Activity Report
March 26, 1968 0. A. Finsand
'j
Middletown Construction 7100
Transmitted herewith is the subject report for the week ending March 26, 1968.
QAF/sec
Distribution
Armco D. C. Osborne C. G. Kramer F. W. Barnes T. R. Folqjr P. R. Smith D. Cox J. S. Lots R. L. Brannaman
Kaiser R. J. Wolf (Oakland) W. F. Bort (Oakland) D. A. Daly F. X. Kast S. Ustel V. L. Frankson A. L. Gordon H. C. Boucher
cc: Central File Kaiser Reading File Armco Reading File
1
iI
KEN 004397
KAISER ENGINEERS WEEKLY FIELD ACTIVITY REPORT Weak Ending March 26, 1968
WEATHER: Approximately 10 inches of snow fell on March 22nd. The remainder of the period was fair and clear.
TEMPERATURE: Minimum - 27 degrees Maximum - 65 degrees
CLIENT:
Armco Steal Corporation
LOCATION: Middletown, Ohio
JOB NUMBER: 6471
JOB VISITORS none
Management General Supervision Field Engineering Warehs. & Mtl. Control Survey Office Srv. St Repro. Clerical Craft *
TOTAL
SUMMARY FORCE REPORT
Kaiser Engineers
Foothill
Exeornt Non-Exenmt Subcontractors Electric Total
44 18 1 42 14
37 1 14 15
--m
69 849
18 12
3
15 m
992
19 5 42 14 82 1 11
18 6
16 31 621
658 2,563
* Average for week of men on payroll.
Average for week of Crafts is as follows:
Kaiser Engineers Subcontractors Foothill Electric
736 904 577
Total Crafts Working
2,217
KEN 004398
WBjjKLT FIELD ACTIVITY REPORT Week Ending March 26, 1968
PROJECT PROGRESS
1. 71ii8 - HOT STRIP MILL
1.3 Structural and Miscellaneous Steel; An average work force of twentyfour ironworkers was maintained in the hot strip mill during the period. In the furnace area, progress continued on the installation of the valve access platforms at the 193 foot elevation for the 16 inch steamline. Installation of the scale shield under the extractors was completed. Progress was recorded on the installation of safety handrails at the skip hoist, dry scale and the slab reject car. In the finisher area, the descale hoods at finishers 1 and 3 were being reworked. In the runout ' area, progress continued on the installation of safety floor plates. At scale pits 1 and 2, handrail was installed in the flume at the inlet structure. An average work force of nine sheetmetal workers was main tained during the period. In the rougher area, the roof wa3 installed. on the pump control room located inside the small parts maintenance shop. In the downcoiler area, diffusers were installed on the downcoiler maintenance unit heaters.
1.5 Heating and Ventilating; Progress continued on the completion of itass for the final inspection of bag houses. Bags were installed in the #12 bag house. General clean-up operations were in progress around the bag houses.
1.6 Mechanicals During the period, Eichleay Corporation maintained an aver age work force of fourteen men in the hot strip mill on support of Westinghcmse testing requirements and remaining mechanical installation. In the finishing mill area, modification requirements involving redowelling for the turn tables continued throughout the period. In the downcoiler and conveyor areas, remaining mechanical equipment which included the downcoiler8, conveyors, downenders and hydraulic systems 17, 18 and 19, lube oil system 10 and the downcoiler air were taken over by Armco oper ations on Monday, March 25th. In the scale pit 3 area, tests were com pleted for the drag systaa and the scale pit mechanical equipment was released to Armco operations. In the furnace area, testing continued on the dry scale removal system. Modifications for the skip hoist sys tem were completed this period. These modifications involved installing a rectifier in order that the existing D.C. brake system could function properly- as well as grinding a 1/4 inch off the skip hoist wheels which was completed in the Armco Machine Shop. Final test of this system is expected next period. In the roll shop, erection of the third roll grinder is underway. The support frame was set in place and grouted during the period* All mechanical equipment between the reheating fur naces through to the coil conveyors are now being checked out and tested by Armco operations. It is anticipated that the first coil through the hot strip mill will be made during the first week in April. The bearings on the bull gear in the Worthington speed reducer, which is between the Worthington turbine and #2 F.D. fan, were inspected and found bad. New bearings are being obtained through Worthington after their field repre sentative inspected the bearings.
KEN 004399
WEEKLY FIELD ACTIVUY REPORT Week Ending March 26, 1968
lo7 Piping: During the period, the remaining 30 feet of pipe was installed for the grease piping in scale pit 3- Total pipe installed to date is 342,702 feet. Kaiser pipefitters were working with Richardson Chemical Cleaning Company during the period when the pickling of the first of four sections of the oxygen piping was started. The sump pump tinder test in the hot strip mill has been accepted and the new seals will now be in stalled in the remaining sump pumps. An average work force of fortytwo men was maintained on hot strip mill piping during the period.
1.8 Electrical: During the period. Foothill Electric Corporation maintained an average work force of one hundred and sixty men on lighting, grounding, communications and miscellaneous building requirements throughout the hot strip mill. During the period, 6,700 lbs. of exposed conduit was installed for a total to date of 1,560,500 lbs. or 99^ complete. 3,600 feet of low voltage cable was installed for a total to date of 1,965,000 feet or 99% complete. 50 low voltage cable terminations were made for a total to date of 33,500. 2,000 feet of control cable was installed for a total to date of 2,069,500 or 99% complete. 50 control cable terminations were made for a total to date of 62,650 or 99% complete. 1,600 lbs. of lighting conduit and 1,100 feet of wire was installed. 500 feet of communications and TV cable was installed. 190 lbs. of structure grounding was installed foe a total to date of 147,100 lbs. or 99^ complete.
1.9 Miscellaneous Subcontracts: Owens Corning Fiberglas Company maintained an average work force of thirty-one men on insulation during the period. Insulation was being removed from the condensate lines in the bag houses as required for the rework on these lines. In the boiler house, work continued on the insulation of piping for the #2 and 3 units.
Delta Pipeline Constructors continued installation of the 10 inch and 4 inch well water drops during the period with 135 feet installed. Pipe remaining to be installed is approximately 200 feet each of 2 inch and 4 inch well water on C line. During the period, the testing on the plant air piping was completed and preparations for pickling of the oxygen sys tem continued. A work force of twenty-eight men was maintained during the period.
Salem-Brosius completed the repairs to the #3 roof refractories and continued^witb installation of plastics in the soak zone hearth. This is scheduled for completion next period. The repairs to the #2 charge end refractories will be initiated during next period. The repair work on the #3 F.D. fan shaft has been completed and a new bearing has been in stalled.
Stuart Painting Company maintained an average work force of sixteen men in the hot strip mill during the period. Progress was maintained on the painting of service piping and miscellaneous steel at the finishers, downcoilers and oil cellars. This subcontractor worked through Saturday, March 16th, on the downcoilers and the various piping systems on the finishing mills.
KEN 004400
- 5-
WEJsKLT FIELD ACTIVITY BEPQBT Week Ending March 26, 1968
2. 71/,A - SLAB MTT.T.
2.1 .excavation and Backfill: 2,000 cubic yards of excavation was completed this period for a total to date of 230,641 cubic yards. This excavation was accomplished between column line A and B in the slab storage area for the slab spray cooling system.
2.2 Concrete} 357 cubic yards of concrete was placed during the period for a total to date of 49,189 cubic yards. Period concrete consisted mainly of the completion for the gantry rail support slab and some fill concrete in the oil cellar between column 14*5 and 15*5* Approximately 200 cubic yards of concrete remain to be poured in the slab mill project.
2.3 Structural and Miscellaneous Steel: During the period, twenty-seven iron workers continued with miscellaneous iron installation and erection of the scale pit gantry crane. The gantry crane is now erected in place and remaining bolt-up and installation of access platforms are in progress. Progress was also evident on the installation of gutter grating in the motor room basement> the dust shields around the shear drive together with dust shields at the main mill, installation of grating at the trans fer car landing table sumps was completed as well. Thirty sheetmetal workers continued throughout the period on renaining duct installation for the five bag houses. Three of these bag houses were completed at the close of this period. The fan motors in bag houses 3 and 4 were bumped for rotation and installation of bags for these units will be accomplished next period*
2.6 Mechanical; Eichleay Corporation maintained an average work force of fifty-three men on mechanical installation in the slab mill. In the main mill aisle, progress continued on installation of motor couplings together with motor brakes and indicating devices. Installation of the dry scale skip hoist cables, dry scale drag scrapers, bottom spindle carriers, roll tliters, and 2 slab pusher motor bases were also in pro gress * In the main mill area, the rotor for the upper horizontal mill was installed. The bottom stator section and the rotor was also installed for the vertical mill. Progress in this area consisted mainly of dowelling on the lower horizontal mill motors and cleaning and setting of bearings. The cable idlers for the ingot buggy drives were installed and reeving of the cable& for this system is now in progress. At the fume elimination systo;oa the east side of the hot strip mill, sheetmetal workers con tinued-with inlet ductwork to the separator. Equipment grouted during the period included the lower mill main drive motor out-board bearing, bottom spindle carrier support, the roll change sled, the #1 slab pusher drive motor base, and the turn-sheave for the ingot buggy system.
2c7 Piping; Hunter Corporation maintained an average work force of fiftyfive men on slab mill piping this period. Major piping systems worked on during the period were; hydraulic system 2, lube oil systems 3, 9 and 10, grease piping, natural gas and clarified water. 1,155 feet of piping was installed this period for a total to date of 33,933 feet. Circulation of permanent oil for lube oil system 6 was continued through out the period and permanent oil was placed in lube oil systems 5 and 7. Lube oil system 11 was pickled and flushed and is now ready for permanent oil. The main plant air loop in the mill aisle was put into service this period.
KEN 004401
-f JUPJgigW
WEEKL7 FIELD ACTIVITr REPORT Week Ending March 26, 1966
2.8 Electrical: Foothill Electric maintained an average work force of two hundred and sixty men in the slab mill during the period. The auxiliary MG sets 1 through 6 were energised and mechanically tested this period. Check out of the adjustable voltage and constant potential voltage panels is now in progress. During the period. Foothill installed 8,900 lbs. of exposed conduit for a total to date of 160,200 lbs. or 91$ complete. 200 lbs. of structure grounding was installed for a total to date of 30,900 lbs. or 62$ complete. 49,000 feet of low voltage cable was in stalled for a total to date of 283,000 feet or 57$ complete. 600 low voltage terminations were made for a total to date of 3,400 or 50$ com plete. 19,000 feet of control cable was installed for a total to date of 108,000 feet or 46$ complete. 371 control cable terminations were made for a total to date of 1,400 or 14$ complete. 6,400 feet of computer cable was installed for a total to date of 29,000 feet or 41$ complete. 600 computer terminations were made for a total to date of 3,600 or 64$ complete. 80 lbs. of lighting conduit and 230 feet of wire was installed. 2,240 feet of communication cable was installed and 21 terminations were made during the period.
3. 7143 - SOAKING PITS
3.3 Structural and MlsceTinneous Steel: Ironworkers completed the guard rail tubing north of 7 line together with the door seals and jambs at the west end of the soaking pit building.
3.6 Mechanical: Loftus Engineering maintained an average work force of one hundred and eighteen men on battery installation during the period. At battery 6, a safety inspection was completed and a punch list developed. The items on this punch list are now being accomplished. The final course of refractory installation was started in pits 23 and 24. Test ing and checking of electrical equipment for battery 6 continued through out the period. The basic back-up brick for all pits was completed this period* Cover carriages have been set in place over these pits with the exception of pits 1 through 4* The first cover has been set in the re lining rack and cover refractory is scheduled to begin next period.
3.7 Piping: Delta Pipeline Constructors maintained an average work force of thirty^rtwo men on service piping in the soaking pit area. The compressed air, siftnrai gas, and coke oven gas piping is essentially completed. Periocfeiprogreas consisted mainly of oil piping, steam piping, water, and instrumentation. 886 feet of piping was installed for a total to date of 17,227 linear feet. Pressure testing was accomplished on the 10 inch natural gas header. Testing of the 3 inch natural gas header pipe is in progress.
3.6 Electrical: Foothill ELectric installed 1,200 lbs. of exposed conduit for a total to date of 93,500 lbs. or 67$ complete. 300 lbs. of lighting conduit was installed during the period.
KEN 004402
mm
wmgm
iffggy
- 7-
WEcXLI FIELD ACTIVITY REPORT Week iinding March 26, 1966
ear
4. 7128 - BASIC OXYGEN SHOP AND MOLD YARD
4.1 Excavation said Backfill; 1,759 cubic yards of excavation was accomplished this period for a total to date of 215,916 cubic yards. 1,448 cubic yards of backfill was completed for a total to date of 274,667 cubic yards. Ex cavation included electric manhole 6, the west wall footing for the elec tric control room and electrical duct runs.
4.2 Concrete: 140 cubic yards of concrete was placed during the period for a total to date of 20,629 cubic yards. This concrete included the service floor from column 22 to 25, the electric manhole 6 base slab and the clarifier sludge tunnel base slab. In the mold yard, the concrete was placed for the canteen floor slab. This completed all concrete in the mold yard.
4.3 Structural and Miscellaneous Steel: 491 tons of structural steel was erected at the main B.O.F. facility for a total to date of 8,055 tons, (excluding 328 tons of anchor bolts and base plates). At the sold yard, 7 tons of structural steel was erected on the spray cleaning station. % The erection of structural steel at the mold yard is now completed. -1 At the main B.O.F. building, no work was done on March 22nd due to a | heavy snow storm.
4*4 Roofing and Siding: At the main B.O.F. plant, roofing continued between column 17 and 20 from D to E line. Siding installation continued on the freight elevator shaft where 881 square feet of siding was installed.
4.6 Mechanicals The following equipment was received for the fume control system during the period: 10 tons of platform grating, two quencher pumps with 200 horsepower motors and one vent system fan and housing. The lower tier subcontractor. Combustion Engineering, moved on site on March 25th.
4.7 Pining* At the mold yard, installation and testing of the service piping systems continued during the period. At the main B.O.F. building, pro gress continued on the installation of the roof drain piping frcm column 17 to 20 between D and E lines. Work progressed on the installation of the Island grease systems for cranes 501 and 506.
4*6 ElectrifyAt the main B.O.F. building, progress continued on the wiring of the charging aisle crane 501 together with the erection of the crane rail brackets for this crane. Laying of conduit Was continued between electric manholes 6 and 7. Embedded conduit was set in the. pump building basement slab. At the mold yard, electrical work continued in the rectifier building together with wiring of crane 521.
KEN 004403
mmm
* s
WEhXLY FIELD ACTIVIT! REPORT Week Ending March 26, 1966
>N
-se**'
4.9 w ar-wil yteous Subcontracts i McGraw Construction Company continued work on the floor slabs and decks for the office and lab building. Underground piping continued for this building and the sanitary system has now been tested and approved between columns A and B. The slab on the first floor between columns 1 and 4 is scheduled to be placed during next period and a start is also- scheduled for the installation of the Steelox siding.
DBS Corporation has installed the new spur track to the 8.O.F. teeming area* This was completed on March 26th.
Stuart Fainting Company has now completed painting at the mold yard building apart from a small quantity of miscellaneous steel and column base plates. At the main B.O.F., painting continued with several further areas now released for painting.
5* 7145 - STRIPPER BUILDING
252 square feet of roofing was installed during the period for a total to date of 22,500 square feet. Electrical work continued in the rectifier building. The testing and check out of crane 354 continued during the & period and the reeving of both the main column and the auxiliary hoist was completed on March 26th. The collector rail and braokete for crane 356* (crane repair hoist) are now completed. This crane was also reeved during the period. Wiring of the heating and ventilating system in the rectifier building continued during the period and is scheduled for completion fay the end of March.
6. 7150. 7156 and 7159 - PICKLE AREA
6.2 Concrete: 356 cubic yards of concrete was placed on pickle line 4 during the period for a total to date of 12,543 cubic yards. Major concrete pours included the floor slab between columns 29 and 32, the fume scrubber baae slab and the base slab for the hydraulic power unit for hydraulic 17. Various conduit runs were-encased in concrete in the delivery motor room for #4 pickle line and at the wet loop pits at #5 line. On pickle line #5, 35 cubic yards of concrete was placed for a total to date of 7,114 cubic yards. Forming for the second lift of the concrete for catenary pit 2 Ojfcp&ckla line #5 continued with concrete scheduled for the next p8riod|||lh the green coil storage building, placing of the slag floor conbinuil^and is now approximately 90$ complete. The section between column-^lihes 12 and 16 will not be completed until the coil buggy system is constructed.
6.3 Structural and Miscellaneous Steel: In the green coil storage area, Ohio Valley continued work on the punch list items for final completion. In the pickled coil storage building, bolt-up of roof sections and installing of purlin spaces continued during the period.
KEN 004404
WEEKL3T FIELD ACTIV3TT SHOOT Week Ending March 26, 1968
^dr -
6.4 Hoofinland Siding: In the green coil storage building, progress coo* tinuecfcon the erection of the roof vents. These are scheduled for com pletion during next period. In the pickle line building, installation of Steelar siding continued over the vent doors in the south lean-to. In the pickled coil storage building, 5,094 square feet of roofing was installed during the period for a total to date of 23,700 square feet.
6.5 Heating mr>A Ventilating: During the period, Kaiser forces completed the installation of the heating and ventilation ducting in the maintenance aisle offices. This is now ready for the installation of the insulation.
6.6 Mechanical; Ohio Valley continued erection of the bolt-49 of the pickle
tank support steel on both #4 and 5 pickle lines. The first pickle tank
section on #4 line were set on March 26th. On #4 pickle line, the #1
and 2 pinch rolls were set in position and additional equipment was off
loaded at the site including the shear entry side guides, the weld de
tector and the looping pit side guides. On pickle line #5, setting of
the strip separator was initiated. In the green coil storage building,
punch list work was accomplished on the grating for the coil conveyor %
trenches.
>
Piping: Delta Pipeline Constructors maintained one crew in the picklef
lines during the period. 720 feet of piping was installed including 160 feet of plant air and 560 feet of oxygen piping for a total to date of 4,980 feet. This piping was installed from the east end of the pickle building along 0 line towards column 34. In the green coil storage building. Bom Woolley continued installation of 2 inch plant air piping and plant air drops.
6.8 Electrical: In the green coil storage building. Lake Erie Electric
continued with the installation of conduit and disconnect switches along B and C lines. Wire has also been pulled in the conduit along C line. The Installation of the high bay lighting feeders from column 1 to 10 between A and B lines is now 95$ complete. In the pickle line building, disconnect switches #5 and 6 in the #4 motor roca are wired and ready for energising. Disconnect switches #4 and 3 are Installed, but cable has cot yet*been<installed. The high bay lighting circuit disconnect * switciMEir# nowfsTftt installed.
6.9 Subcontracts: FBS Builders continued building the masonry entry motor room on E2 and F lines between column 17 and 19*
took walls in the maintenance aisle office have now been cam-
7160 - norn mttj.
During the period, 2,793 cubic yards of excavation was completed for a total to date of 14,163 cubic yards.
KEN 004405
"SW**<teS#*W9r%
- WEEKLY FIELD ACTIVITY HEPOJHT Week Ending March 26, 1968
>*--WfSBBC55B5
7186 - WASTE DISPOSAL FOR THE PICKLE FACILITY
During the period, forming for the aeration and flocculation tanks con tinued with concrete scheduled for the next period. Installation of the roof drains in the waste disposal building continued together with the setting of the acid unloading area drains south of the building. 4$054 square feet of flat deck roofing was set in the waste disposal building. Setting of the stairs inside the building was started during the period. Foothill Electric has completed the conduit in electric manholes 1 and 2 and continued setting the Transite duct bank west of #2 manhole.
UTILITIES
7105 - Water Distribution System: At the elevated water storage tank in the south area, Chicago Bridge and Iron were closing the top of the stor age tank during the period. All items are scheduled for completion by the end of March apart from the painting.
7110 - Power Distribution; In the melt area switching station, the con trol cable connections to the Quindar cabinet were completed during the period. The station batteries and charger were installed and connected but not yet placed on charge. At the cold finish substation, progress^ continued on the relocation of aisleway leaders and relays. This work* is scheduled for completion during a station outage on March 30th.
7111 - Sanitary Sewers: The subcontractor has repaired leaks at several manholes on the trunk line in the steelmaking area and preparations for an inspection are now being completed.
7112 - Drainage and Site Development: 2,800 cubic yards of excavation was completed during the period for a total to date of 798,023 cubic yards. 1,945 cubic yards of backfill was placed for q total to date of 1,048,710 cubic yards. Delta Pipeline Constructors placed 192 feet of 24 inch CMP from manhole 405 to 728 and 53 feet of 24 inch CMP from manholes 728 to 729 in the steelmaking area. This completes the pipe installation on this subcontract, and now remain approximately forty-five manholes to be com pleted in the vicinity of the soaking pits, stripper building, mold yard and B.O.F. Weetinghouse Electric Corporation has now completed seventeen of tha;..eighteen railroad lighting tower foundations. Parking lot tower foundalibn concrete has now been placed and wood poles for roadway light ing aMupresently being distributed..
.3&r` 7113 - Trackwork; DBS Corporation installed 2,114 feet of track and five turnouts in the steelmaking area during the period. This track is located between open hearth #2 and the B.O.F. and gives access to the teeming aisle.
7114 - Locker Rooms; In the steelmaking area locker room, installation of lighting and plumbing fixtures is nearing completion and general clean-up of the area is being continued. When the toilet partition and the exterior painting is completed, work on this facility will be essentially finished.
OAF/LM/sec
KEN 004406
Prepared by 0. A. Finsand
Approved by. G. L. Heberts Construction' Manaeer