Document n96XEaV9OXNL9xeoO4qBoQX2G
Interoffice Communication
To R. J. Reusch, Chemicals Research, Ponca City
From M H* Lewis
ot Subiact
January 18, 1980
i
PREMATURE FAILURE OF PVC REACTOR RELIEF SYSTEMS
In the past, several of the safety relief systems on Conoco PVC reactors have failed prematurely, resulting in VCM emission to the atmosphere. Of the two configurations presently used, the double rupture disc ar rangement was found to be less effective in preventing premature releases of VCM as compared to the rupture disc/relief valve setup. However, neither arrangement has proven to be 100 percent reliable in controlling VCM emission upon premature failure of the primary rupture disc. Discus sions earlier in the year with BS&B Safety Systems, Inc. generated several ideas for preventive measures which were later carried out in the plants. In November 1979, consideration was given to the idea of changing all double disc setups to rupture disc/relief valve arrangements. The idea was accepted in December. Two experimental test programs were then drawn up to determine the configuration and optimum spacing required between the rupture disc and relief valve to contain the VCM upon premature failure of the primary disc. One of the tests was designed for BS&B and the other for Conoco R&D. The following report summarizes the progress made in December 1979.
Experimental Test Program
A joint meeting dealing with the premature failure of PVC reactor relief systems was held December 4, 1979, with Process Engineering Department personnel. In that meeting, the decision to change all double rupture disc setups to rupture disc/relief valve arrangements was confirmed. Also, an experimental test program for BS&B Safety Systems, Inc. was reviewed. The test program, which was drawn up by R&D, proposed two basic rupture disc/relief valve arrangements to prevent the premature release of VCM from Conoco's PVC reactors. Initially, testing of a 6" or 8" relief system was considered, but because of the limited size of BS&B's test facility (120-gallon vessel), a 3" rupture disc/3Mx5" relief valve system was decided upon. Although the ability to scale up to larqer sizes from the results obtained from the 3" relief system is questionable, the data collected should provide a good starting point for further worfc.
On December 10, 1979, the attached experimental test program was pre sented to BS&B at their Tulsa office.
BS&B not only agreed to carry out the experimental test program at no cost but also agreed to provide rupture discs and safety holders for additional testing by Conoco at no cost. In addition, BS&B volunteered to perform another series of tests based upon the results of the first.
WHI14-M H'll'HtHI II......... 111-1 n 111111+H11MI-I1-ITM1 hM rl 11 hH l+h| I .. ............ ..................................... hi |i |i Hrr
I : 11 r< r< 11 ii 11 ii m n m 11111 m 1111111 n i-i 1111 111111111 |i 11 i^ri i 11 i i 11 i i i | 11 ii ............- ( 11
I 111 11 ! 11 11 i i U4-II Mil i i-i |-fjn |
*
i-
VAB.0001132231
.............................................................................................................................................. ..
1.4*1 hH HM< I** H U44*4W
M **+ i iHUl-h .^l-UW+J+H M+h hi I.................. .. .. ... lnl
.... .
11 I......... I"'M 'rMUI-IMI'll'|NHIM"l'JMm-l'l|llllll- IIII
1111 iH Irhi I II I .........I........................Ill".................................hill-.............
ii' ! i:.11 ih^M|r-p*:ihiNI14* I I
B-20
R. J. Reuseh
Page 2 January 18, 1980
A meeting between 8S&B, Consolidated Valve, and Conoco was held on December 18, 1979, in Tulsa to finalize plans for the experimental test program. Consolidated Valve personnel were present and were willing to provide (at no cost) pressure gauges and relief valves for the experimental tests. The test program should begin January 22, 1980, with the following people present: George Lowrey (DresserConsolidated), Bob Lowrey (Dresser-Consolidated), John Strelow (BS&B), and Max Lewis (Conoco). The data from these tests should give Conoco a better understanding of the effects of the following variables on premature failures: (1) the space allotted between the rupture disc and relief valve, (2) a tee/elbow arrangement be tween the rupture disc and relief valve, and (3) the annle of the
relief valve.
Premature Disc Failure
The reason for premature disc failure is still under investigation. During the past month, six 6-inch and seven 8-inch rupture discs, which which were taken out of service a couple of months ago, were tested by BSSB for their burst pressure. Although PVC buildup was found on several of the 6-inch discs, all broke within disc specifica tion. However, of the seven 8-inch discs tested, four broke below the 5 percent tolerance limit. Further investigation showed that two of these discs that failed prematurely were from a double disc arrange ment on the D-301 reactor, and the other two were from a double disc arrangement on the D-302 reactor. This may indicate that the premature failure of the four 8-inch rupture discs should be attributed to disc installation or setup, rather than to faulty disc manufacture. According
to BS&B, crown damage is the most probable cause of premature disc failure. However, the alignment and weight of exhaust piping on the relief system can cause uneven stressing of the disc and also result in premature failure. The valve vendors were likewise concerned about the effect of exhaust piping on the relief valve.
The rupturing of four 8-inch rupture discs desionated for Conoco PVC plants was witnessed while in Tulsa on December 18, 1979. The discs were rated for 206 psi at 72F. The four discs burst at 204, 204, 198, and 202 psi--all within the 5 percent tolerance limit.
*
Recommendations
If desired in the future, BS&0 will provide rupture discs that neet the ASME code. They will also provide strip chart recordings of the temperature and pressure experienced during the tests conducted to meet the ASME code. It is recommended that Conoco should purchase only ASME coded discs from BS&B. Although the quality of the ASME
r
I
I I I I
II
I i
I
i
i.
I I
I
r
r
i
f
i. '
i i
r p E
t
r
i
i I i
I
l I i i i i i i i i i
i
i
I I I I I I
I I
VAB.0001132232
- 1,1
4
4 **
B-20
R. J. Reusch Page 3 January 18, 1980
coded disc would not necessarily be superior to the disc now purchased, the presence of coded discs on the PVC reactors would be to Conoco's advantage if court action resulted from a premature failure. It is also recommended that all safety relief valves on PVC reactors be oriented vertically to assure proper functioning of the valve and that the feasability of altering the exhaust pipe be considered.
Heat Up
In documenting the premature failure of rupture discs on PVC reactors, Duane Lewis found that most premature failures occurred during heat-up (IOC of September 24, 1979). By viewing the polymerization reaction in the 50-gallon reactor during heat-up, it was found that the vapor space disappeared. As the contents of the reactor were heated, the vapor above the mixture became entrained into the liquid, the vortex disappeared, and the whole liquid surface rose inside the reactor. Also during heat-up, the torque on the agitator blades decreased as a result of the vapor entrainment. Whether or not this same phenomenon occurs in the large commercial reactors is not known. However, if it does, the presence of a liquid in the reactor dome would help to explain why the relief valve opens and then fails to close upon premature disc failure.
M. Lewis
\
Ennineer *
Engineering Research Section
vie Enc cc: FK DJR JF CM
AJL WF OH-
w
BSmB TEST PROGRAM
j
I RUPTURE DISC/RELIEF VALVE SYSTEM
PRESSURE -200 PS I TEMPERATURE -50OF
Basic Configurations
i I
i
I. Spacing between disc and valve
Configuration 1
i
|
Space (Pipe Disc Rating (Psi) Test Diameters) Valve Rating (Psi) Mo.
2 0.70
1
2 0.80
O 4-
2 0.90
3
7 0.70
4
7 0.80
5
7 0.90
6
4 0.70
7
4 0.80
8
4 0.90
9
6 0.70 10
6 0.80 11
6 0.90 12
/
j ,
-
'
9
B-20
' Tt**| 11 KM H l H rN 11111111' |-n IIJIHII fWI I l-l I utltfrf+l cl II HIti pr>hf| 111' M*-1 H rl 11 --m I LI 11
*
l|.Tl
1111r*i>i 11 .................
. 11M1' 11 lJlJi+Ihi H !
11 11 i -I * pi I -
I - i-i ................................... ................... I
h ' -I .-*1 rl N*H-I l+4-| JM1111 r< '' f
i
4-
I i I I
I I I
I I I
i.
i
i i
i. i
i
ji;
i
i i i:
V
I I
I I
r
T
i
i
i
11
i i. i i i
i
I
I
I i
I I
i,
.(
I I I
'L i
T|
I
* j;
f\'-
r
j;
r \
n'l
i,
r
ij
k. i-
r
I
I I1 .
IH
I n.
I j:
I?
I I
S'
if.
I
I
ia I
\
I
i
L1.
c.
r r
i
cv-.
i i
i.
i!
f
t r
i
VAB.0001132234
h iuiii
* 'im1 m *i
................ 4iiniiHWi*>i"H*<*fr>Hi*liWMPH*4MllnpHWTW^TW
B-20
Space Past Elbow (Pipe
Diameter)
0 0 0 3 3 3 2 2 2
Disc Rating (Psi) Valve Rating (Psi)
0.70 0.80 0.90 0.70 0.00 0.90 0.70 0.80 0.90
Test Mo.
13 14 15 16 17 18 19 20 21
II. Angle of Relief Valve
Use the pipe diameter spacing that successfully contained the rupture in Phase 1, Configuration 1.
Spacing (Pipe Diameters)
Angle
Disc Rating (Psi) Test Valve Rating (PsiT No.
To be determined 30 0.70 22
To be determined 30 0.80 23 To be determined 30 0.90 24
.... ...................................................................................................... ........ ..
*
111-1 |j I 11111 M ri 11111 M 111-1111 11 11111 11 hi 11111 hi I pi | |tI 111 h*1111 * |1
i r>1111111111'
................
11 -11.1 I .. - I: . IIII 1-11*1 hi H |1 An 111 I ht: i 'll
I I
I
I
i Ji
i
4
I
j,
i!
i
4 I
i
I
'l l!
I
I
i
r
i
I
i
i
r
h
1
4
I1
I
I
t-
I
I
I I I
I
I I
I
I I
T|
l l
i i
i
l i
i
i
VAB.0001132235