Document n6Y3Vbe5Kk7D74gNnvLRjrZz
UNITED STATES
Clean Air Act Compliance Inspection Report
AGENCY
United States Environmental Protection Agency
ONMENTALPROTECTION Region 10 Seattle, WA
Partial Compliance Evaluation
Kinder Morgan
Willbridge and Linnton Terminals
5880 NW Saint Helens Road,11400 NW Saint Helens Road,
Portland, OR 97210Portland, OR 97231
Inspection Date: December 5, 2024
Digitally signed by ZACHARY HEDGPETH
ZACHARY HEDGPETH
Date: 2025.02.13 07: 51: 46-08'00 '
Report Author SignatureDate
Zach Hedgpeth, PE
Environmental Engineer
EPA Region 10
BRENDAN
WHYTE DigitalDlatye : s2i02g5n.0e2d.1 3b 0y8 :B 2R6E: N0D0-A0N8' 0W0 H'Y
TE
Peer Review SignatureDate
Brendan Whyte
CAA Inspector
EPA Region 10
Digitally signed by ELIZABETH WALTERS
ELIZABETH WALTERS
Date: 2025.02.13 11: 40: 50-08'00 '
Manager SignatureDate
Elly Walters
Supervisor, Air Enforcement Section
EPA Region 10
Table of Contents
1. Basic Facility and Inspection Information......3
2. Introduction4
3. Inspection Elements and Field Observations - December 5, 20244
4. Closing Conference - December 5, 2024.....6
Attachments
Attachment 1 ..Photo and Video Log
Attachment 2.............. EPA Region 10 FLIR GF320 SOP
2
1. Basic Facility and Inspection Information
Facility:Kinder Morgan Willbridge Terminal Kinder Morgan Linnton Terminal
5880 NW Saint Helens Road,11400 NW Saint Helens Road,
Portland, OR 97210Portland, OR 97231
AFS / FRS Number:AFS: OR0000004105102028FRS: 110048840735
Permit Number:26-2028-TV-01
Facility Contacts:Lane Karabaic
Area Manager
Kinder Morgan
lane karabaic@kindermorgan.com
Donny Homer
Air Specialist
Kinder Morgan
donny homer@kindermorgan.com
Agency Inspectors:Zach Hedgpeth, PE-EPA Region 10
206-553-1217, hedgpeth.zach@epa.gov
Brendan Whyte - EPA Region 10
(b) (6) whyte.brendan@epa.gov
Trey Peterson - EPA Region 10
Alex Liebert - EPA Region 10
Boris Barrera - Oregon DEQ
Inspection Date:December 5, 2024
Inspection Notice:Limited notice
Disclaimer
This report is a summary of observations and information gathered from the facility at the time
of the inspection. The information provided does not constitute a final decision regarding
compliance with the Clean Air Act (CAA) and applicable regulations or permits, nor is it meant
to be a comprehensive report of all activities and processes conducted at the facility.
3
2. Introduction
a) This was a Clean Air Act (CAA) compliance inspection by the Environmental Protection
Agency (EPA). The purpose of this inspection was to conduct a partial compliance
evaluation (PCE) inspection of the facility. The inspection included general discussion of
facility operations and a visual walk - through including observations using FLIR GF320
and Gx620 infrared gas imaging cameras in addition to the observations of the
inspectors.
b) Limited notice of this inspection was provided to the facility.
3. Inspection Elements and Field Observations - December 5, 2024
a) Around 08:15 I called Donny Homer and provided notice of the inspection.
b) The EPA inspectors arrived onsite at the Linnton facility location at approximately 09:10.
We met with Lane Karabaic, Area Manager, and Sean Gray, Operations Supervisor, in
the facility parking lot.
c) Opening Conference
1. A brief opening conference was held in the facility entrance with the four EPA
staff, Mr. Karabaic, and Mr. Gray. Donny Homer arrived shortly after our arrival.
The EPA inspectors presented our credentials to facility staff at this time. Mr.
Karabaic explained that he and Mr. Homer would serve as EPA's points of
contact for the inspection.
2. I began the opening conference by explaining that we (EPA inspectors) were
onsite to conduct an inspection under the Federal Clean Air Act (CAA). The
inspection will be a PCE centering around emissions observations using the FLIR
cameras. I noted that EPA was following up based on data recently collected and
submitted by the facility as part of the fenceline monitoring currently underway
as required by the EPA Information Request.
3. Collection of photos, videos, and FLIR infrared videos were discussed, and facility
personnel expressed their agreement. I also explained that copies of all
recordings collected during the inspection would be transmitted to the facility
along with the inspection report.
4. I noted that some of the EPA equipment is not intrinsically safe, and facility staff
completed the necessary documentation in their hot work permit system.
5. Confidential business information (CBI) was discussed, and the EPA CBI forms
were sent via email to Mr. Karabaic on 12/6/24. Facility personnel did not claim
any information as CBI during the inspection.
6. The opening conference ended, and the group proceeded to the field at
approximately 09:20.
1 Use of the cameras during this inspection followed U.S. EPA Region 10 Office of Environmental Assessment
Standard Operating Procedure OEAFIELDSOP-111 entitled " Optical Gas Imaging with a FLIR GF320 Infrared
Camera ", which is included as Attachment 2.
4
d) Field Observations - Linnton Facility
1. Fieldwork began with a walk - through survey of selected tanks and other areas
using the FLIR cameras. Mr. Karabaic, Mr. Gray, and Mr. Homer accompanied the
inspectors throughout the inspection.
2. Sorbent tube monitoring Station 4 was observed, and I took photos 487-489 (see
Attachment 1) showing the installation of the sorbent tube monitoring
equipment.
3. The groundwater treatment system installed at the facility was observed. The
contractor who maintains the system was onsite at the time of the inspection,
and noted that the carbon was last changed out in September 2024.
4. The oil - water separator at the facility was observed, see photo 491. The facility
staff noted that the unit is rarely used.
5. The facility staff noted that painting was ongoing, and had been initiated on
November 11, 2024. We observed hand painting of piping occurring.
6. Inspector Whyte climbed Tanks T-45028 and T-59029 and observed the tanks
using the FLIR camera. No emissions were visible using the FLIR camera.
7. The group departed the Linnton facility around 10:15 and drove to the Willbridge
facility.
e) Field Observations - Willbridge Facility
1. The inspectors arrived at the Willbridge location around 10:30. We briefly
entered the facility office and met with facility personnel in order to sign - in. We
then proceeded to the field, accompanied by Mr. Karabaic, Mr. Gray and Mr.
Homer.
2. Instead of walking through the facility, the inspectors drove to a gravel area
outside the northwest portion of the site, near the truck scale. The facility staff
opened a gate to allow us access to the facility through the security fence.
3. Sorbent tube monitoring Station 03 and the mobile meteorological station onsite
were observed, and I took photos 492-495 showing the installation of the
sorbent tube monitoring equipment and met station.
4. Mr. Gray explained that the facility truck rack and marine loading vapor
collection are both routed to a bladder tank, which is upstream of the vapor
recovery unit (VRU). The bladder tank was installed in / around 2015.
5. FLIR observations were conducted of Tank WB-123. VOC emissions were
observed from the rim vents using the FLIR cameras, and Inspector Whyte
recorded video 200 (see Attachment 1).
6. The group observed that trucks regularly idle near sorbent tube monitoring
Station 03, as shown in photo 496.
5 10
4. Closing Conference - December 5, 2024
a) The closing conference was held in the field at the Willbridge facility. I led the
discussion, including providing an overview of the EPA Region 10 compliance process.
b) Attendees:
1. Kinder Morgan: Lane Karabaic, Sean Gray, Donny Homer
2. EPA: Zach Hedgpeth, Brendan Whyte, Alex Liebert, Trey Peterson
c) No issues were identified as potential compliance concerns under the CAA. I clarified
that this may not include any additional compliance concerns that are identified post-
inspection.
d) The closing conference ended around 11:00, and the inspectors departed the facility.
6