Document mpRrVQnYb5OaONjJkkn1wY0QO
Vista Chemical Company
Lake Charles VCM Plant VCM Plant Rd., P.O. Box 605
Westlake, Louisiana 70669 Phone (318)494-5000
October 13, 1986
Mr. H. J. Neeld Conoco Inc. P O Box 2197 Houston, TX 77252
Dear Mr. Neeld:
Re: Groundwater Control Capital Projects
Per your request, listed below are the ongoing and
budgeted projects at the Lake Charles VCM Plant which
will
prevent
groundwater
contamination.
Although
groundwater control is
not necessarily
the
sole
justification of all of
these projects, it is
a
significant factor in each of them. As evidenced by this
list, a substantial amount of capital expenditures (over
$3,OOOM) will have been spent in FY 1986 and 1987 on
groundwater control at the VCM Plant.
This amounts to
about 45%
of the projected total
plant
capital
expenditure of $6,911M for those two years.
1) Acid Neutralization Tanks Replacement
$1,906M
The existing
in-ground
brick
lined
concrete
Incinerator Acid Neutralization Tanks (T-981, 982)
and the Wastewater Neutralization Tanks (T-500) will
be replaced with two below grade Furan tanks inside
a concrete containment vault. The new tanks will be
equipped with integral caustic trim neutralization
chambers to replace the existing caustic
trim
neutralization tanks
(also
in-ground).
Also,
included is installation of piping in trenches for
the collection system for the new tanks, and new
piping for the discharges of the new tanks replacing
a portion of the existing underground sewer piping.
The AFE has been., approved and mechanical design is in progress. Project completion is expected in 4th Quarter FY 1987.
2) T-405 (Heavy Ends Storage Tank) Replacement $136M
The on-ground Heavy Ends Storage Tank, T-405, is being replaced with an above ground cone bottom tank installed on an impervious base. In addition, the
CWI-I 000005843
Heavy Ends Loading Pump, P-452, is being relocated near T-405 and provided with impervious containment curbing.
The new tank is nearly completed service in early November per Compliance Order issued by the April 2, 1986.
and will be put requirements of
Louisiana DEQ
in a
on
3) T-450 Bottom Replacement
$75M
The existing bottom of the Dry Crude EDC Storage
Tank, T-450, is being replaced due to a leak which
occurred in January 1986 as a result of soilside
corrosion.
Both the
existing bottom and
the
previous bottom (underneath) have been removed and a
new bottom installed. Removing the old bottoms is
necessary to allow future installation of cathodic
protection in the tank farm, as Cathodic protection
does not function properly on dual bottom tanks.
The project installation is nearly complete and should be completed by the end of October.
4) Closed Process Sewer Underground Piping Replacement
$150M(Capital) $115M(Expense)
The existing underground Closed Process Sewer (CPS)
piping will be replaced with a solid Kynar piping
system installed in the existing plant process
drainage trenches for secondary containment.
Also,
included are the installation of three clearing
lines for use during distillation column washes, and
construction of a Mobile Recovery Pot to be used for
clearing offsites equipment.
The existing
Furan underground
piping
system
cracked and developed leaks under normal operating
stresses such as thermal expansion, and has not been
operational since the beginning of the last VCM
Plant turnaround in August, 1985.
The project has been AFE'd. Repairs of the process
trenches to provide proper containment are
in
progress ($115M expense).
It is targeted
to
complete the project such that the system can be
used during the upcoming turnaround in early 1987.
CUH 000005844
5) Laboratory Sink Drainage System
$18M
This project involved rerouting the
Laboratory-
drainage collection tank pumpout line to T-110, the
Steam Stripper Feed Tank; instead of the previous
routing to the LCCP sanitary sewer system.
This project was completed in the 4th Quarter FY 1986.
6) Storage Tanks Cathodic Protection
$52M
Cathodic protection will be provided for twelve storage tanks to protect against leaks in tank bottoms from soilside corrosion. The four EDC tanks. Light Ends Tank, three caustic tanks, and the four incinerator acid tanks will be included in this system.
This project has been AFE'd recently. installation is 2nd Quarter FY 1987.
Projected
7) Secondary Containment for Pumps
$10M{Expense)
Concrete containment curbing was installed for ten pumps in non-paved areas. Eight of these pumps are located in the tank farm area; two in the T-500/T-2 area. This project was completed in the 4th Quarter FY 1986.
Total Groundwater Control Related FY86 Capital - $2,337M. % of Total FY86 Capital - 72.5%
FY 1987 Budget Projects
1) T-2 Replacement
$155M(Capital) $ 20MCExpense)
The Process Runoff Settling Tank, T-2, will be
replaced with a Furan tank installed inside the
existing in-ground brick lined concrete T-2 which
will be used as a concrete containment vault.
The
new vessel will be equipped with pumps, piping, and
instrumentation necessary to transfer the collected runoff to the steam stripper feed system.
The project is budgeted for 1st Quarter FY 1987 with installation projected for 4th Quarter FY 1987. Expeditious replacement of T-2 and/or taking the existing T-2 out of service is part of a commitment made with the Louisiana DEQ.
CWH 00000
2) Heavy Ends Containment
$ 125M
Containment for the EDC Tars Still Area, the Vinyl
Chloride Tars Still Area, the Incinerator By-product
Liquid Feed Pumps (P-902 A&B) Area, and the Tars
Trailer Loading Area will be provided by installing
6in.x6in. curbs around each area.
A chemical
resistant coating will be applied to the concrete,
and a resistant material will be used to replace
existing expansion joints in the concrete.
This project is budgeted for 1st Quarter FY 1987 with installation projected for April 1987.
3) T-450 Conversion
$ SOM
The Dry EDC Crude storage Tank, T-450, will be modified to spare the Wet EDC Crude Storage Tank, T-453, and the Pure EDC Crude Storage Tank, T-451.
This project will
reduce the
potential
for
groundwater contamination by allowing more frequent
inspection of the EDC Storage Tanks.
Currently, neither T-451 or T-453 can be taken out
of service outside of turnaround. Consequently, the
frequency of inspection is dictated by the run time
between turnarounds.
By modifying T-450 to spare
T-453 and T-451, both tanks can be inspected outside
of turnaround.
This modification will reduce the
potential
for
groundwater
contamination
from
undetected tank bottom leaks
and reduce
the
turnaround workload. By having a spare for T-451
and T-453, sudden unexpected repairs can be made
without a plant shutdown.
Furthermore, reduced
repair costs and increased operating flexibility are
expected.
This project will be submitted for AFE approval in the First Quarter Fiscal Year 1987 with project completion expected two months after AFE approval. The timing is dictated partially by the turnaround which is tentatively scheduled for January 1987, as some of the work can only be done during the
turnaround. Also, expeditious installation of this project is required to allow T-451 and T-453 to be inspected as soon as possible.
000os04*
4) Heavy End Storage Tank, T-452, Base and Bottom Replacement
$ 27 0M
The soil base of the existing T-452 will be replaced
with an impervious base.
Also, if inspection in
January 1987 (after the new T-405 is put in service
and T-452 emptied and cleaned) show T-452 bottom to
be leaking, a new bottom or tank will be installed.
If a new bottom or tank is required, secondary
containment for the area surrounding T-452 will also
be required per
the recent
hazardous
waste
regulations promulgated in July 1986.
The project is budgeted for 2nd Quarter FY 1987. The Louisiana DEQ Compliance Order issued in April 1986 for T-405 and T-452 requires the new base to be completed by June 18, 1987. An extension may need to be obtained if secondary containment and a new tank become necessary.
5) Tank Bottoms Replacement - Phase II
$150M
The bottoms of the Pure EDC Storage Tank, T-451, and the Wet EDC Storage Tank, T-453 will be replaced. These tanks presently have two bottoms each due to previous replacements of tank bottoms by installing the new bottom over the old bottom in lieu of removing and replacing the old bottom (similar to T-450). Both bottoms will be removed and a new bottom installed such that the cathodic protection system being installed will be effective for these tanks.
This project is presently budgeted for 2nd Quarter FY 1987 AFE. One tank will probably be done in the 2nd or 3rd Quarter and the other in the 3rd or 4th Quarter.
Total Groundwater Control Related FY87 Capital - $750M % of Total FY87 Capital - 20.3%
It is expected that additional funds will be budgeted in
FY 1988 and 1989 to continue the plant (and Vista)
overall program of inspecting all the plant tank bottoms
over the next few years.
The main ones remaining after
FY 1987 will probably be the Light Ends Tank (T-402), the
Slops Tank (T-460), and the three caustic tanks, T-421,
T-422, and T-423). The four Incinerator acid tanks have
CUH O0n 000sg4?
rubber liners so the metal bottoms cannot be inspected
without removing the liner.
The liners for three of
these tanks were inspected and repaired as needed in FY
1986. The liner for T-960B will be replaced in early FY
1987. At that time, the metal bottom can be inspected
also. After T-960B is placed back in service, the liner
of the remaining acid tank, T-960A, will be inspected.
Besides the
capital and
expense projects
already
mentioned, there are a number of small projects and
administrative measures that have been implemented during
the past year to improve groundwater control.
Sincerely, j, * ^ 7/
.
G. E. Hopkins Chief Process Engineer Vista VCM Plant