Document mmOvgXX1wz5YzBBk05VwBvB4Z
Monsanto
R. S. Yates - General Offices
September 18, 1967
Additional Tests from the Continuous Absorber System
CEA 1800 - Aroclor Expansion-WGK
TO \J. MacPherson ANNISTON
J. G. Bryant H. C. Carder V. R. Haupt R. P. Stevens H. L. Williams
During the development of the scope for building new aroclor facilities at WGK the question was raised as to why we have to install an absorber on each aroclor stream that we process. A separate unit may be desirable for 1242 and 1254 but the other streams might be processed through one unit. To determine if this is possible, I suggest you set up a test of changing from Aroclor 1242 to another Aroclor and determining what contamination problems present themselves. The present unit could be drained and may be blown free of Aroclor 1242 before the test is started.
Can we have your comments in this regard? We would like this information by mid-October if possible.
R. Yates
0285369
TOWOLDMONOQ45594