Document mm1xxxOj5jdM66nngjRjOXxDO
v-UiVK-A.NY (JONFfDENTTAL
t Monsanto
Anniston Plant
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Anni ston
Summary
C. K. A. G. L. C. J. C. G. W.
W. B. W. F. H. L.
Eastman Hill
Lahman
Landwehr Miller
j |
Papageorge I
Taffee Williams
Month
September, 1969
Cost Improvement Results
Est. Act. $63,120
Target $66,285
% of Target 95.27.
General Offices
YTD
$430,976
$438,570
98.37.
H. S. Bergen H. C. Carder D. Danna (5) P. B. Hodges D. B. Hosmer (2) W. A. Kuhn J. A. Morgan W. R. Robirds J. E. Smith J. A. Stephens R. J. Stratmeyer H. S. Trail
OTHER LOCATIONS
A. H. Forsten Alvin, Texas
D. W. Jackson WGK
T. M. Patrick So. 2nd St.
Organic Division
The Solid Aroclor 5460 yield increase instrumentation has been installed. Calibration and start-up will begin when 5460 is produced in early October.
The Sandvik belt test on Montar 5 was successfully completed. Installation costa will be estimated in October.
Muriatic Acid - MIP was reviewed in plant on 9/10. Necessary revisions to be completed during October.
Agricultural Division
The Acetone Recovery project was verbally approved 9/29 for $32,125 capital and $28,600 expense. Expected savings are $40,000/yr.
C.E.D. has suspended scoping and estimating activities on original Sulfur Recovery Project and will evaluate alternates to obtain the major yield savings at a lower capital cost.
Niran - Tentative Process Amendments are being prepared for plant trials of Freon-21 replacing Freon-11 as chlorinator coolant and HC1 replacing nitrogen as chlorination sparge gas.
DSU 014862
-N - 30
COMPANY CONFIDENTIAL INFORMATION
"This document contains confidential information which is the property of Monsanto Company. Only those portions of the document relevant to a duly authorized individual's need to know may be exerpted for him. The report must not be sent outside the Company without written approval and the recipient is accountable for its safe keeping, exerpting or otherwise disclosing of its contents and for its proper disposal."
STLCOPCB4003238
Company Confidential 2.
Utilities Evaluation of Central Air Compressor system started, with December report target.
Design & Drafting Data being gathered for electrical protective device study which will lead to recommendations to improve reliability of overload protective devices in important feeders. Construction drawings forwarded for Biphenyl Pilot Unit building and Parathion emergency generators.
Pollution Control HC1 neutralization pit continues to successfully treat all waste acid. Construction 95% complete on test unit for removal of solids in Waste Treatment Plant effluent. Start-up targeted for early October.
Quality Control The Plant Quality Score was 86.1, down 7.6 from August with a YTD score of 88.1 against a 1969 target of 95.0 minimum. Unfavorable trends continue in Aroclor 5460 solubility, Aroclor 1242 low dis tillation and TC Chlorides. Raw material benzol remain at low distillation level, with Intermittent high toluene.
. C. Landwehr :kd
OSH 014863
STLCOPCB4003239
) ORGANIC DIVISION
1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR APR KAY JUN JUL AUG SEP OCT NOV DEC
Sol.Aro.Level TAR
Ind.< -Still SpG ESI
AFE 3015
ACT
Solid Aro.
TAR
Lower 5060
EST.
Soft. Point
ACT
2250 2250 2250 2250 2250 2250 2250 2250 2250
--
--
"
--
"-
-
2600 ?6oo 2600 26oo ?6oo 2600 2600 ?600 2600 1500 5490 4390 215 C 467 C aooc 4230 iiyr 3475 1500 5490 48 90 2150 467 C 80oc 4<ou 77 30
-
--
Sol.Aro.-Still Coolant temp.
AFE 5015
TAR EST. ACT
160 170 160 170 160 170 160 1.70 160
--
-
-`
*
Sol .Aro. -Chlortcc TAR
Batch End
EST.
AFE 5015
ACT
390 390 390 390 390 390 390 390 390
----
'
" "
Sol.Aro. Yield TAR
SW/R Composition EST
AFE 5016
ACT
2750 2750 2750 2750 2750 2750 ?750 2750 "
--
Solid Aro. Montar 5 Flake AFE 2949
TAR EST
ACT
1080 1080 1080 1080 1080 1030 1080 1080 --
Sol.Aro. Blend 4465
TAR EST
ACT
25 Q0 2500 2500 2500 2500 25QO 2500 2590 2500 2500 2500 2500
1690 1920 1630 1490 710 1690 1920 1680 149C 710
1180 990
use 990
229 220
-
Sol.Aro.-Verti- TAR
cal Still Cond. EST'
AFE 2524
ACT
70 80 70 80 70 70 90 90 9 0 90 -
-
"
70 90 90 90 90 -
Sol.Aro.Cl2 T/C Dock AFE 2542
TAR EST ACT
940 940 950 0-0"
Sol.Aro.-New Cl2 TAR
Unload - No Delay F.ST
CED 1851
ACT
950 940 950 940 950 940 950
900 900
2330 2050 2320 1650 2?5 I2050 2320
Solid Aro.-Flake TAR
& Drum
EST.
CED 1450
ACT
Liq.Aro.
TAR
3000 3000 5000 5000 5000 5000 5000 5000 5000 5000 5000 5000 0 0 IfloTT 2000 2000 2000 300C 3000 3000 0 0 1000 2000 200C 3000 30C1 3000
3000 3000 - - - - - - - - - -
48-53 M #/yr. AFE 2545
EST ACT
0 550c 0 550c
-
*
Liq.Aro.'No.2 TAR
3000 3000
Still Entrain Sep. EST.-
AFE 5095
ACT
Liq.Aro.-Montar TAR
Disposal
EST
AFE 2952
ACT
Warehouse
TAR
Reduce Manpower EST.
CEA 1452
ACT
Liq.Aro.New
TAR
Burners #3 Still EST
ACT
1080 1080 1080 1080 1080 1080 1080 1080 1080 1080
0 00
00 0 -
0 00
00
-
2000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 2000 2000 200C 3000 3000 3000 3000 3009 300C 2000 200C 20CC 3000 3000 3000 300C 3OOC
1500 1500 1500 1500 1500 1500 1500 1500 1500 1500
0
0 1500 3000 900 0
-
0 0 1500 3000 900 -
Biphenyl Relocate TAR
No. 1 Preheat EST
CEA 1892
ACT
HB-40
TAR
2nd Autoclave AFE 3102
EST ACT
500 500 500 500 500 500 500 500 500 500 500 500
1500 0 1560 1870 0
0 TFUt 0
-
150C 0 6 10 137 0 0
0 150C
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 5000-
2230 2530 0 3490 24 2 C 0
600 9 (JOG 6000 560 c ZT2GD 5 99
600 10,40C 8600 /4 DU 6950
1
DSW 014864
STLCOPCB4003240
) ORGANIC DIVISION
1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR APR MY JUN JUL AUG . SEP OCT NOV DEC
BiO Improve Tower Treat. AFE 5155 Improve Pit. Power Factor
TAR
EST ACT TAR EST ACT
450 450 450 450 430 450 450 450
0u
0 584 645
00
0 585
900 900 900 900 900 900 900 900 0 500 900 -ffir 900 0 500 83O 990
Central Air System
TAR EST
1000 1000 1000 1000
-
ACT
Optimize Rx Time PNP
TAR EST ACT
3? 00 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
0 5420 0
0 0 2940 i2ur 0
0 5420 0
0 0 2940 2370
Reduce Mole Ratio NaOH/PNCB PNP
TAR EST ACT
4000 4000 4000 4000 4000 4000 4000 4000 4000
0
00
00 0
0 00 0 0
New Wash Water Pump * PNP AFE 2998 Automatic pH
TAR EST ACT TAR
50 50 50 50 50 50 50 50 25 50 50 50 50 50 50 50 25 $n 50 50 50 50 50
500 500 500
Control
EST
PNP ACT
HC1 Filter Pump
TAR ^0 330 540 EST 330 33O 340 ACT 330 3 30 340
New Blow Tank HC1
TAR 200 200 200 200 200 200 EST 200 200 200 200 500 200 ACT 200 200 200 200 200 200
150,000 Gal.-HCl Storage Tank AFE 2468
TAR EST ACT
17$0 1760 1780 1760 1760 1780 1760 1760 1780
-
u -.
0 2640 3290 2990 0 2830 343
Produce Staley Grade Acid AFE '>076
TAR EST ACT
799 799 799 780 780 790
--
-
Cla Plt. Shutdown TAR
EST
CEA 1851
ACT
8??0 8880 8880 8880 8880 8880 8880 3380 6655 42335 19900 *i99a 223C do55 v2355 19900
Hg Recover from Residue
TAR 250 g50 250 ?50
EST 3910 0
00
ACT ^910 0 0 0
Hg Wash Tank
AFE 2802 Biphenyl Productivity
TAR EST
ACT
TAR EST
ACT
250 250 250 230
00 00
0u 00
5600 5600 5600 5600 5600 5600 TSoo 5600 5600 5600 5600 5600
0 9u0u 15,OCX 0 0 0 3(3733; 2700 0
1800 5900 13530 0 0
0 3078C 2700
Total Organic By Month M $
Total Organic YTD M $
TAR
EST ACT TAR
EST ACT
23.; 26.3 29.3 37.5 42. ? 51.1 51.6 51.6 51.6 52.7 5j-AJCLgj
27.1 30.2 11.5 56.3 39.165 107.4 53344 49.410 16.5 23.3 27.3 11.4 25.75 45.9 1102E 258J6 >
25- 3 50.1 79.4 116.9 159 .2 210.3 2ZTJ
417.8 471.-1521.9
46.9 78.8 79.6 11519 144.4 253.5 315J3L 368.86 2
16.5 40.3 68.1 79.5 105.2 151.1(361.35 131945 2
_
** $27,780 adjustment included for months January thru June.
DSW 014865
STLCOPCB4003241
> AG DIVISION
1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Cooling Tower Rep iping AFE 2598 Optimize N2 & Cl2 Levels
TAR
EST -ACT
TAR EST ACT
420 420 410 410 420 420 410 420 420
0 00 0 00
00 00
0
6600 6700 67 00 6600 6700 67 00
0 00 0 00
00 00
0
Increase Waste Acid Sales
TAR EST ACT
400 500 500 400 500 3OO 400 500 300 00 0 0 00 00 0 0 0
Chlorinator R.I.
AFE 2244 EVOP Condensation
TAR EST ACT TAR
750 750 500
250 250 250 250' 250 250
00
0
00
500 750 750
Rx. EST 0 0 12,615 ACT 0 0 32,615
Cl2 Unloading
CEA 1851 Recycle Wash Water AFE 2960 Parathion Recovery
TAR EST ACT TAR EST ACT TAR
5000 5000 5000 2000 2000 2000
0 0 1580 00
290 290 290 290 290 290
00
0
00
580015800 5800
EST
AFE 2655 Reduce Acetone
ACT. TAR
4500 4300 4300
Losses
EST
Formulations
AFE 2897 Change Cooling HsO Item 7J7 AFE 5067 Well H-O to Jets
ACT TAR EST ACT TAR EST ACT TAR EST
1600 1600 1600 1600 1600 1600 3000 6600 10,001 4570 2000 3950 5300 10,400 9235 4570 1205
125 125 125 125 125 125 125 125 125 120 130 155 272 333 310 120 180 171 272 333
500 500 500
ACT
Ag. Division by Month
TAR 750 750 50C 9145 9145 91 *5 14^75 .146.8 5 1464?. ,14575, 1 443 s 14485-^ EST 12615)3,12 t 6,750 10,155 4842 4033 13,7 k ACT 0 0 12^15 1,420 10,580 9459 484 l 6488
Ag. Division
TAR
YTD EST
ACT
Ag. Division
TAR
untargeted-R.M.
EST
Charges ODtimizatiJ rACT
TAR
Untargeted - HC1 EST Catch Tank& Coale: eXCT
Ag Div.-Untargeted TAR
750 1500 9000 11145 P029C 9<342> 441 nr 53785 75470 83045 1025 5 117015
12,635
%315 37,770 41,93c 45,949 63114
0 0 12^15t/,035 27615 57.074 41,936 48,404
0
17 0C 3690
1700
0 00 0 5000 6250 596C 4690 1330c
0 9?5C 6317 4920
l
1
EST - 4180
^3 Cl2 change out ACT
3250
DSW 014866
STLCOPCB4003242
>
AROCLOR
Company confidential 3.
E. E. Bowles, C. R. Mcllwain, J. W. Mattern, (V. R. Haupt)
Evaluate Quaterphenyl-
Polyphenyl Effects on
1969 Savings $63,200
Solid Aroclor YieldsNFC$14.000B - 8(a)
TSD Objective
Radioactive source for level alarm installed. Representative from Ohmart Corp. conducted radiation survey and instrument checkout. Start up delayed because of department downtime and producing Solid Arodors other than 5460. Expect to start mid October.
Montar Use and Disposal
Savings $13,000
Project 2952NFC
$10.000B - 8(g)
TSD Objective
Request to change route of piping to avoid going through the Chlorine plant has delayed installation of project. Necessary equipment delivery date is estimated at 4-6 weeks.
Sandvik Belt Cooler for Montar 5 Solidification
Solid Aroclor Expansion Evaluation
TSD Objective B - 8(1)
The Pilot Unit Testing has been successfully completed with good results. Price and size estimations have not been finalized, however, preliminary "ball park" figures show that a belt to handle 8000#/hr. requires a cooling width of 4 ft. x 55 ft. long. The purchase price of this size unit is in the 35 M dollar range.
Porocel Columns
Assist
CEP 2152ProductionTSD Job No. 950
North Porocel columns to treat chlorobenzenes were started up on September 19, 1969. Results of first trial were inconclusive. Further quality improvement tests are planned.
The start-up of the South columns has been delayed by the Aroclor fire. Start-up is now planned for the week of October 6, 1969.
BIPHENYL-SANTOWAX
W. G. Niemeyer, D. A. Self, J. M. Jones, (V. R. Eaupt)
Debottleneck Biphenyl-
Santowax Distillation Area
Capacity
TSD Objective
to 87,6 M lba./vr. BiphenylIncreaseB - 7(a)
Installation of by-pass loops with blow-out connections for the two Santowax C flow meters was scheduled foT 9/10/69. However, only about one fourth of the planned work was completed. The problem was that the operators were not able to unplug the recycle line and it was not safe to cut and weld on the line. Maintenance is now scheduled to unplug the line. A capacity/performance test run will be conducted on the Santowax distillation column after the meters are re-installed and calibrated.
DSW 01486?
STLCOPCB4003243
BIPHENYL-SANTOWAX - (continued)
Company confidential 4.
Low Biphenyl Santowax for FDA 5460
Sale* Support
TSD Objective B - 7(b)
A tower water loop study is in progress to try to increase the cooling water flow to the Biphenyl/Santowax distillation area. Increased cool ing water flow to the distillation area is required to produce low biphenyl Santowax.
Prediction and Control of Dust Explosion Potential in Biphenyl Flaker Packaging System
Safety
TSD Job No. 951
At our last plant meeting on this problem, we decided to convert the biphenyl packer from fluidizing with air to fluidizing with nitrogen. However, the estimated operating expense for nitrogen is much higher than originally thought. The estimated operating cost for nitrogen will be $13,000 to $14,000 per year compared to $1500 that was originally esti mated. We plan to proceed with this conversion, in spite of the high cost, to eliminate a hazardous situation. Inert gas generation equipment will be evaluated to compare operating costs and most economical method used long term.
Designed Experiment Run on No. 1 Biphenvl Furnace
Process Study
TSD Objective B - 7(e)
All the samples have been analyzed. Preparation of a progress report is in progress. Test results will be used to update math model of this process.
Install Knockout Tank on Santowax Jet Vent
Safety
TSD Job No. 862
Complete design package was transmitted to Maintenance for construction on September 9, 1969.
Natural Gas Safety Shut-off Interlock Switch
Safety
TSD Job No, 948
Complete design package was transmitted to Maintenance for construction on September 25, 1969.
DSW 014868 STLCOPCB4003244
Company confidential
5. HC1 G. L. Moore, L. 0. Chambers, K. G. Hale, (A. G. McCarty)
Production of Staley Grade
New Earnings $288 M
TSD Objective
Acid - AFE-^076Potential Savings $71,000B - 10(c)
Savings of $13,300 resulted from the Coalescer and Catch Tank project during September. Spare elements of a modified design are being completed by the vendor.
Plant pilot carbon treatment studies are scheduled to be run in November. The objectives are; 1) Accumulate design data necessary to expand the carbon treatment area, and 2) determine the carbon treatment and condi tions necessary to produce "Staley" acid. An experimental project for pilot test facilities is being issued ($700 experimental expense).
TSD Objective Issue HC1 MIPPlanningB - 1(b)
Plant review was held on 9/10/69. Revisions are being made to several sections as a result of plant review. Revised copies will be submitted for final review by 10/31.
Reduce High Free Cla in Muriatic Acid
QualityTSD Job No. 950
An expense project is being issued to install necessary piping to air blow a second storage tank and provide a temporary air supply until the cause and/or cure to the high Cla problem can be found.
PNP L. 0. Chambers, K. G. Hale, (A. G. McCarty)
Debottleneck to 1.8 M $27.500B - 9(a)
Capacity Savings
TSD Objective
Process changes targeted at reducing PNCB usage resulted in let-down problems during September. No savings resulted in September. Additional changes will be made and monitored by P. & Q.A. to attempt PNCB usage optimization.
NIRAN
K. G. Hale, D. W. Dudley, T. W. Lawrence, (A. G. McCarty)
Demonstrate Parathion Recovery
Savings $17,400 10-1571 Reduced COD
TSD Objective B - 5(a)
No change in status. Construction in progress on test facilities.
DSW 014869 STLCOPCB4003245
)
NIRAN - (continued)
Company confidential 6.
Acetone Recovery201 Reduced COD
Savings $12,900
TSD Objective B - 5(i)
Recovery tests on #3 condensation reactor indicate a 307. reduction in acetone loss. Gross savings (ethyl and methyl) from increasing acetone recovery is $40,000 per year plus a 201 reduction in COD load. Project 3340 was verbally approved 9/29 for $32,125 capital and $28,600 expense. Manpower evaluations are presently underway to determine what parts of the project will be installed during the '69 fall turn-around.
Central Chlorine Unloading for Nlran.
Savings $21,000
TSD Objective B - 6(a)
Evaluation of rebuilding 12 year old compressor vs. purchasing new com pressor favors the new compressor. Compressor will not be purchased or installed until late winter to prove worth of air pad on "cold chlorine cars" during winter.
Sulfur Recovery
$271,000/yr. Net Savings
from Residue531 Reduction in SOoB - 5(d)
TSD Objective
C.E D. has suspended work on the Sulfur Recovery scope and will evaluate alternates to obtain yield savings at a lower capital cost.
The new objective would be to remove sulfur and recycle organics, but not clean-up sulfur for re-use.
Improve Chlorinator Cooling System
Profit New Sales and Productivity Savings $48,000/mo. per 0.5 Hour TSD Objective Reduction in Chlorination TimeB - 5(g)
A Tentative Process Amendment is being prepared to cover plant trial of Freon-21. If approval is given, expect to begin trial approximately one month prior to the end of the 1969-1970 Ethyl run and extend approximately one month into the 1970 Methyl run.
Improve Intermediate Distillation Capacity
Capacity
TSD Job No. 972
Possibilities are remote for obtaining significant increases in inter mediate distillation capacity with existing equipment. It is felt that thin-film or wipad-fllm equipment may be suitable for processing this type of material rapidly. Contacts will be made with thin-film vendors to explore the possibility of application to this problem.
DSW 014870
STLCOPCB4003246
)
NIRAN - (continued)
Company confidential 7.
Replace Nitrogen with HC1 for Chlorinatiop SpargeSaving* $60.000TSD Job No. 60^
Anniston PR&D has shown that HC1 sparge produces no adverse effects during chlorination compared to nitrogen sparge. Since HC1 is produced during chlorination, it could possible be recovered for use as sparge gas replacing nitrogen. A tentative Process Amendment will be prepared covering a plant trial of sparging with cylinder HC1.
PROCESS AND QUALITY ANALYSIS
J. L. Murphree, Allen Hale, (W. B. Dunlap)
Process Surveillance
An 18 month downward trend in distillation level of raw material benzol was revealed, culminating in 6 tank cars out of specifications. Toluene in benzol was found to be out of spec. These factors may be related to a documented increase in Aroclor 1242 TC Chlorides over the last 5 months.
PNP-Identlfication of
Potential Savings
Critical Variables$60.000TSD Job No. 839
TSD Objective C - 3
A final report on yield study was written. Reactor settings will be ad justed and controlled experimentally to verify the statistical prediction of the study.
Potential Savings Niran Still Control$79.000TSD Job No. 964
An AFE was approved to obtain and install control equipment. Design and drafting is scheduled for the 4th quarter. Installation EDC is 3/1/70.
ENGINEERING DESIGN AND SERVICES
Mechanical/Electrical/Inatrument Design and Drafting '
J. C. Price, J. A. Veazey, J. 0. House, G. W. Richey, B. D. Morgan, R. V. Carlisle, R. L. Brewer, J. K. Rennie, (W. F. Taffee)
Design was completed on Project 3161 - $3*8 M, Automatic Temperature Control of Thio Acid Reactors #1 & 2. Review drawings were transmitted with con
struction drawings to follow in October.
Design is in progress on Project 3H8 - $9.7`M, Modify Agitator Interlocks on all critical vessels in the Niran department. Transmittal is expected in October.
DSW 014871
STLCOPCB4003247
ENGINEERING DESIGN AND SERVICES - (continued)
Company confidential 8.
The following project safety reviews were held or attended: Fire Pump Capacity Check Equipment (AFE 3227 - $4.1 M), Install Pressure Control Valves in Fire Protection System (AFE 3211 - $5.7 M), Biphenyl Pilot Unit (AFE 3297 - $13 M).
A program is underway to gather data necessary for preparation of a short circuit coordination study of the electrical portion of the Niran department. The results of this study will lead to the compilation of a program for testing switches, circuit breakers, protective relays and, in general, all major electrical equipment that could cause prolonged downtime due to its failure.
Training and supervisory time remained at a high level this month because of time necessary due to three recent manpower additions to the department. One E & I Technician is on loan to the Maintenance department to instruct maintenance employes in an electrical instrument course.
Premises were prepared and forwarded for the following projects: Niran Intermediate Tank-Car Cleaning, Building 27 Dismantling, Eliminate "Head Knocker" at Aroclor.
Drafting
Review drawings were completed for the following projects:
Install 4" Heat Exchanger in Biphenyl (AFE 3282 - $1.4 M), Final Wash TankPNP (AFE 3342 - $2.0 M), Automatic Temperature Control of Thio Acid Reactors (AFE 3161 - $3.8 M), Dual Chlorine Relief Valves - Niran (AFE 3310 - $3.5 M), Acetone Recovery (Electrical) (AFE 3340 ~ $50.7 M).
Construction drawings were completed for the following projects:
Replacement of Water Loop-HCl (AFE 3240 - $8.4 M), Biphenyl Pilot Unit (AFE 3297 - $13 M), Debottleneck Solid Aroclor (AFE 2897 - $20 M), Replace Niran Generators (AFE 3305 - $41.9 M), Install Nash Compressor at Eimco Filter-Waste Treatment (AFE 2820 - $4.6 M), Acetone Recovery - (Piping) (AFE 3340 - $50.7 M).
UTILITIES ENGINEERING
J. C. Price, J. 0. House, M. L. Marcum, (W. F. Taffee)
Transmitted review drawings for Test Heat Exchanger (AFE 3282 - $1.4M) on Biphenyl Cooling Water. The design package will be transmitted in October. Started preparation of Utilities Improvement Items for inclusion in the Aroclor MIP. Started evaluations of projects to replace existing air com pressors with a Central Plant Air Compressor (estimated gross savings $12.0 M 16.0 M per year) and to Improve Plant Power Factor (estimated gross savings $5.0 M - $9.0 M). The premise for the power factor project la expected to be forwarded in October and for the compressor project in late November or early December. Continued work on Steam Plant MIP with completion scheduled for December 15.
0$W 014872
STLCOPCB4003248
PLANT IMPROVEMENT
Company confidential 9.
G. C. Goodwin, (W. F. Taffee)
A premiae was prepared and forwarded for Renovating Niran Control Room and Lunchroom. Design package was forwarded for: Up-grading Fire Pro tection System (AFE 3293 - $7.1 M).
Messrs. K. B. Davis and J. Harrison of the Alabama State Highway Depart ment visited the plant on September 26, to discuss the relocation of Highway 202 across Monsanto property. They presented two schemes for the connection of old Highway 202 to the new 202 on the southeast side of the plant.
POLLUTION CONTROL
E. G. Wright, (W. F. Taffee)
Air & Ha0 Pollution Complaints
Conmunity and Governmental Relations
TSD Objective B-P
No air or water pollution complaints were received at the Anniston Plant during September.
P.C.B. in Choccolocco Creek
Pollution Abatement
TSD Objective F-^
The first set of samples taken from Choccolocco Creek show levels of P.C.B. from 2 to 8 PPB. These levels will be checked at periodic inter vals beginning in October with another set of samples from the creek.
TSD Objective HC. Neutralization PitProduction AssistanceF - 4
The pit continued to neutralize all of the acid sewered this month. No un-neutralized HC1 has left the plant since August 8. The pit is showing no signs of reaching a break-through point at the present time. Plans are to continue to extensively monitor the pit until it has reached the break-through point.
Choccolocco Creek
TSD Objective
Wildlife StudiesPollution AbatementF - 4
Requested Drs. Gunning and Suttkus to do another study of Choccolocco during the fall season. This study will probably be conducted during late October. Samples of the fish and other wildlife from the creek will be collected, frozen, apd sent to Organic Research for P.C.B. analysis. This will provide some base data for evaluating the magnitude of the P.C.B. problem in Choccolocco.
DSW 014873 STLCOPCB4003249
POLLUTION CONTROL - (continued)
Company confidential 10.
Eimco Filter at Waste Treatment
Production Assistance
TSD Objective F - 4 TSD Job No. 808
Construction is 957. complete. Start-up is scheduled for the first or second week in October.
Waste Treatment
All wastes were effectively treated during September. High solids continue to be a problem. Successful operation of the Eimco filter should eliminate the problem. Average daily values for Monsanto's effluent are as follows:
PNP COD Parathion BOD
Average daily 1.0 PPM
123 .17 PPM
4 PPM
Specifications 5 PPM
<C200 PPM *=^-1.0 PPM (max.)
<.200 PPM
DSW 014874 STLCOPCB4003250
)
PLANT LABORATORIES G. W. Miller
Company confidential 11.
PROCESS RESEARCH AND DEVELOPMENT J. T. Bell
Of the 105 PR&D mandays available in September, 63 were expended on projects outlined in the 1969 PR&D Program. The use of the remaining mandays were divided among vacation, supervision, illness, and miscellaneous.
Blend Scavenger
Improved Aroclor
Refinement (Aroclor)Electrical PropertiesJ . L. Brown
Evaluation of Type 4A Molecular Sieve as an absorbant for column refinement of Aroclor-Scavenger mixes was begun on 9/24 with completion targeted for 10/15/69.
HB-40 Process Studies
Determine Process Variables
W. H. Howard
Equipment failure has temporarily suspended attempts to prepare HB-40 via a continuous process. This aspect of the study is to be continued on 10/3. The effect of quaterphenyl level on reaction times and catalyst requirements has been determined by a batch process. Santowax C has been hydrogenated to HB-40 with an extended reaction period.
Biphenyl Tubular
Obtain Desired
Pilot StudiesBlohenvl/Terphenvl RatioJ. L. Brown
Plans for the Biphenyl Pilot Laboratory were completed on 9/9 and trans mitted to maintenance. The plans were issued for bids on 9/10. A delay of 15 days caused by failure of contractors to bid promptly has been encountered with construction now targeted to begin on 10/15.
Low Color Aroclor 5460
Develop Alternate ProcessG. L. Arnett
The distillation of Aroclor 5060 and 5460 over a combination of lime and NaOH is effective in reducing color. DTA studies indicate thermal stability of the combination of Aroclor 5060, NaOH, and lime up to 400C. Samples have been forwarded to St. Louis for corrosion studies. A PR&D report is being prepared.
Parathion Isomer Reduction
Increased Yields
G. L. Arnett
This project has been delayed by illness but will resume by 10/6.
DSW 014875
STLCOPCB4003251
PLANT LABORATORIES -(Cont'd)
Company confidential 12.
PROCESS RESEARCH AND DEVELOPMENT -(Cont'd)
Parathion Condensation Reaction Studies
Increased Yields
I, Ransaw
The project work plan has been interrupted to derive a method for determining the actual 7. conversion in the condensation reaction. The reliability of the method is to be determined by 10/3 with the study, as written in the work plan, to resume on 10/6.
Acetone Recovery (Parathion)
Reduce COD Load
G. L. Arnett
Sample analyses have been made to support a plant demonstration of increased acetone removal in the condensation step. This study has been terminated.
ANALYTICAL AND QUALITY CONTROL S. 0. Kemp
Complaint Report
Quality
Number
Material
Customer
12-A-69 13-A-69 14-A-69
Aroclor 5460 HB-40 Aroclor 1268
Swift Addyston Plant Central Solvents
YTD Quality Complaints/100 Shipments 0.24
Reason
Organic Matter Color High Melt Point
Target 0.20
OSW 014876 STLCOPCB4003252
)
Company confidential
COMMUNITY RELATIONS. PERSONNEL, RECRUITING. AND DEVELOPMENT
13-
Community Relations
1. J. C. Landwehr, W. F. Taffee and E. G. Wright attended a talk by Dr. Roy Ledbetter, Alabama State Extension Entomologist, on the positive benefits of DDT at the September meeting of the Decatur, Ala. Kivanis Club, September 11.
Personnel
1. Brode D. Morgan, BSEE from the University of Arkansas, reported to work on September 2 as Electrical-Instrument Engineer I.
2. Ralph Noel, D.O. student, Cobb High School, started to work in ED&S September 18, 1969.
3. G. L. Moore, Co-Op from Ga. Tech, has returned to school to complete studies to obtain degree in Chemical Engineering.
4. All members of TSD attended a seminar on Parathion Poisoning Symptoms conducted by Ishmeal Ransaw, September 16, 1969.
3. All members of TSD attended Job Holders meeting conducted by
W. B. Papageorge, September 24, 1969.
'
Recruiting
1. Summer employes reported to school September 15: P. D. Kinnear to the University of Chicago, M. L. Marcum to the University of Tennessee, J. L. Gaines to Auburn University, and A. I. Hale to the University of Mississippi.
Development
1. J. C. Landwehr participated in Innovation Exchange Program at Bridgeview Plant (Chicago), September 25-26.
2. V. R. Haupt visited the Newport England Plant to assist with Biphenyl problems, September 4-20.
3. G. L. Arnett held a seminar at the Luling Plant, Luling, La., to train decontamination team, September 25.
Visitors
1. Bob McCutchan visited the laboratory September 17 concerning Aroclor.
2. W. A. Kuhn visited September 3-4 and was special guest at the seminar and barbecue for new employes.
3. George Hunt from S&PP section of CED visited the plant on September 30 concerning the electrical failure in the Aroclor department on September 27.
DSW 014877
STLCOPCB4003253
)
PROCESS
IMPROVEMENT
DISTRIBUTION OF TINS BY TECHNICAL SERVICE Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec.
NEW PRODUCTS
PUNT IMPROVEMENT
ASSIST OPERATIONS
SPECIAL ENGINEERING SERVICES
uo ewcuz
TECHNICAL MANPOWER
MISCELLANEOUS ACTIVITIES
AND ABSENCES
---------
DSW 014878 STLCOPCB4003254
)
IN MAINTENANCE
FOR CONSTRUCTION
IN MAINTENANCE COMPLETED
NOT CLOSED
PROJECTS SUBMITTED
FOR APPROVAL
tcod 3
j
oa bo tQZo C<ZO3 o
H z
APPROVED PROJECTS IN TSD
TSD PROJECT SUMMARY
DSW 014879 STLCOPCB4003255
LABORATORY AT!:I*,T5TRATIO.i
60
ANALYTICAL SAMPLES
56 52 48 44 40
2400
2300
2200
ANALYTICAL MANPOWER
2100 2000
1900 1800
1700
0.6 Manpower/sample 0.4
0.2 11.00 10.00
$/Manhours
9.00 8.00 7.00
7. Total Plant Operating Cost
2.0 1.5 1.0 0.5
| 1\
-------1------1
Overtime 7.
7 ^ 3 1
1967
_____________________________
1963 J F M A fi-
J
I |
JA
bo
.'t u
STLCOPCB4003256