Document kmjLpOrjpj9YGnY3KrDr0mLO0
CHEVRON U.S.A. INC. ENGINEERING & MAINTENANCE DEPARTMENT
SPECIFICATION NO. EP-289-N FEBRUARY 10,' 1977 Page 1 of 1
SPECIFICATION NO. EP-289-N ' REPAIR DAMAGED AND REPLACE MISSING
INSULATION IN ALL PLANTS ' '
1.0 SCOPE
This specification covers the repair and replacement of insulation and weathercoating on various sizes of pipe and fittings throughout the refinery per the attached work list.
2.0 DETAILS OF THE WORK ^
2.1 Contractor will -.repair or replace insulation per Standard Drawings GA-N99783-3 and GB-N99993-0 and as directed by our Company Representative.
2.2 Contractor will clean up and dispose of daily^ all debris-' and trash created by the work being done.
3 - 0 GENERAL PROVISIONS
3.1 Contractor shall--comply with the attached Refinery Instruction No. 1404 and ascertain the pertinent Refinery Safety Regulations fromzCompany's Field Representative before commencing work._
3.2 Contractor shall_obtain permission daily from Unit Operator before starting -to work in any plant.
4.0 MATERIALS
^
4.1 All insulation specified in Standard Drawings GA-N99783-3 and GB-N99993-0 shall be asbestos free.
4.2 Aluminum jacketing shall be epoxy coated.
5.0 FURNISHED BY COMPANY
.
Company will provide -if site within the refinery for trash disposal.
6.0 FURNISHED BY CONTRACTOR
Contractor shall furnish all labor, tools, equipment, expendable materials and service^necessary to complete the work set forth in this specification.
CHEV BB 012446