GUIDELINE
PLANT ENVIRONMENTAL ASSESSMENTS
A program of environmental assessments and audits of all plant sites will be maintained in order to assure regulatory compliance and the protection of the surrounding environment.
PROGRAM
1. Environmental assessment documents (information
such as local air and water quality, relationships with
regulatory agencies, and the effects of our presence on
the surrounding environment) will be prepared for
each operating location. Documentation of subsequent
changes or additions to assessment contents will be
filed with assessments at the plant site so that an
update can readily be prepared should the need arise.
Executive summary sections reflecting long-range
plans and highlighting key environmental issues will
be updated annually.
'
2. Compliance audits for large and environmentally sensitive sites will be conducted on a three-year maximum cycle with other sites to be audited at least every five years. Audit follow up plans will be reviewed annually.
3. Groundwater assessments will be performed for all locations with annual reviews to address priority concerns.
4. Each location shall maintain a groundwater protection plan to include inspection, testing and maintenance of facilities with the potential of contaminating groundwater (i.e.; sewers, process lines, sumps, tanks, loading/unloading areas, etc.)
New or replacement facility designs (including sewers and lines) should consider aboveground and/or double containment, improved materials of construction and/ or cathodic protection to provide improved assurance against groundwater contamination.
The above groundwater protection plans and designs shall be commensurate with the risk posed by the specific situation.
STA TUS/OBSER VA TIONS
Environmental Assessments
Initial environmental assessments have been completed at essentially all worldwide sites, certainly at all major sites. Many of the resulting manuals exceeded the three year update target of the previous guideline language, though local records continue to provide up-to-date status.
Compliance Audits
The audit program is essentially on schedule for U.S. locations, with some plants having completed the third audit cycle since inception of the program. Follow-up status on recommendations are variously reviewed on an annual or semi-annual basis.
Auditing of ex-U.S. plants, except Europe/Africa, is just now beginning to fall behind schedule, as audit responsibilities were not reassigned subsequent to the corporate reorganization. This is being addressed.
Groundwater Assessments
All plants have completed initial groundwater assessments. The last major effort on update of these assessments was completed in late 1984. Priority projects and plant corrective action situations have had subsequent reviews. Most groundwater protection plans were put in place by the July 1, 1985 target date. However, some plans have not yet been written and many are in the process of achieving full implementation.
(Revised and Approved: Environmental, Safety & Health Committee June 25, 1987.)
-OSH 117709