Subject: 3 liter.lab release, board of review
The GEON CompanyOne Geon Center
Board of incident Review Vinyl Chloride Monomer Release Building 413, 3 Liter Laboratory
12/5/96
Summary of the Incident At approximately 3pm on December 5, 1996 the Resin R&D 3 liter pilot
operations experienced a clamp failure on reactor #1. Approximately 1 hour into the reaction the reactor retaining clamp failed which allowed the reactor to separate at its mating flange. Upon separation a combination of polyvinyl chloride resin and vinyl chloride monomer was released to the atmosphere in the room. It was calculated that approximately 2.1 pounds of vinyl monomer was released. There were no injuries and no exposures over the OSHA reporting criteria.
Board of Review A Board of Review was convened on Thursday the 5th of December 1996 at
4:15 PM with the following in attendance:
Jerry Bialko Bob Tebbutt Al Kalzewski
Kevin Maggioli
Dale Wahl Shane Ryan Jason Barnes
Facility Manager Director R&D Resin & Intermediates R&D Senior Process Specialist Resin Pilot Plant Lead Operator Resin Pilot Plant Engineer Resin Pilot Plant, 3 Liter Operator Research Technician, Resin R&D Maintenance Supervisor Maintenance Supervisor Environmental, Health & Safety Engineer,
OGC
Narrative The discussion began with a review of the incident and the circumstances
leading up to it. '
3 liter operator, had prepared reactor #1
according to standard operating procedures. As part of the preparation,
pressure and vacuum tests were performed on reactor #1 prior to charging. The
reactor held pressure and vacuum within specified limits and he began the
experimental charge. Approximately 1 hour into this process
observed that
the charge was beginning to solidify instead of normal polymerization, he then
redacted
"NGC *3601
began to cool the reactor down as per procedure. 2 to 5 minutes after the
1
cooling began, " ` `
suspension resin technician were discussing *
the reaction characteristics by the computer control console in the lab when
they heard and felt a pressure concussion. Both men observed that the reactor had failed, they immediately left the laboratory. The VCM warning alarm lights activated at the 1 and 5ppm levels almost immediately with the lOOppm warning
alarm horn sounding approximately 20 seconds later.
Phil Bak a resin scientist who was standing outside the lab when the
reactor failed, immediately went to the fire alarm pull station and pulled the
alarm to evacuate the building as per emergency protocol. However, the alarm
did not function. Phil then proceeded to begin a manual evacuation of the
building. E,H&S personnel and the Facility Manager were contacted by radio and
immediately responded to the scene. The Emergency Response Team (ERT) was also
activated via radio. The operators involved were checked for injuries by ERT
personnel and the areas outside the laboratory were monitored for VCM. No VCM
was detected outside of the 3 liter lab. Building personnel were then allowed back into the building. After determining that over 1 pound of VCM had been
released we immediately began the emergency notification protocols as outlined
in site environment policies E-101 through 103. All notifications were made
within the required time frames.
were sent to the dispensary
for medical evaluation for potential chemical exposure, no problems were found.
Once the VCM levels in the lab were below 1 ppm, personnel were allowed
to re-enter the room to begin the investigation. Upon investigating, it was determined that the reactor had failed at approximately 196 psi of internal
pressure, which is well below the vessel pressure rating of 300 psi. Normal
operating pressures vary from 160 to 230 PSI. The reaction was a typical
reaction performed in the 3 liter pilot plant.
The investigation revealed that the bottom portion of the vessel had
blown down and slightly back bending the support structure and hydraulic system
as well as tearing the cooling water outlet line from the vessel. A more
detailed inspection showed that the cooling jacket had been fractured as well.
3 pieces of the vessel retaining clamp, the T bolt assembly and the clamp ring
(in 2 pieces) were found near the failed reactor.
Upon examination it was determined that the flexible banding steel on
the clamp had fatigued directly along a spot weld which lead to the clamp
failure. Normal procedure is to visual inspect the clamp prior to securing the vessel. The T bolt was examined, the threads were intact and the bolt assembly
was found to be within specification. The age of the clamp is not known. It
appears when the clamp burst that one of the pieces flew towards the computer
console striking it with enough force to snap several pieces off of its casing.
The Avon Lake fire department came to the scene to inspect the damage
and assess if any remaining hazards existed.
Systems Investigation: The fire alarm system did not function properly.
Upon investigating it was determined that the mechanical reset switch on the master control box did not engage fully the last time the system was reset. This has been remedied.
The VCM detection and lab ventilation systems functioned as designed.
Cause
The cause of the incident was determined to be mechanical fatigue failure of Che reactor retaining clamp flexible banding ring.
NGC 13602
Corrective Actions:
1) Remove all present clamps from service and inspect them for evidence of
wear.
Bialko 12/6/96 Complete
2) Replace all present clamps with new clamps. Maggioli 12/10/96 Complete
3) Replace present flexible, T bolt locking clamp design with a 2 piece dual
locking clamp for all 3 liter reactors.
Maggioli 1/10/97
4) Assess ways of preventing clamps from becoming projectiles should failure ever happen again, i.e. shielding, tethering ect. Maggioli 12/20/96
5) Assess damage and repair costs to 3 liter reactor #1. Maggioli 12/20/96
6) Check and repair faulty fire alarm system. Ryan/Wahl/Barnes 12/5/96 Complete
7) Check and replace damaged computer control monitor in 3 liter lab. Kalzewski 12/6/96 Complete
8) Clean lab of all resin particles.
12/6/96 Complete
9) 3 liter laboratory operations are to be suspended until replacement clamps
are received.
Bialko 12/5 Complete
Facts Surrounding the Incident
There were no injuries The notifications to all outside agencies were made as required Internal management notifications were made as required The laboratory ventilation system worked well The VCM monitoring system worked well OGC sustained a reportable release of vinyl chloride The operator has been an employee of Geon for 8 years The operator followed all procedures as required
Conclusion
It was the conclusion of the board that the environmental release was result of mechanical failure of the reactor retaining clamp and no operator error or recipe related factors contributed to the release. The 3 liter operations are suspended until such time that new clamps can be secured.
a
Jason E. Barnes Environmental, Health & Safety Engineer,
OGC
NGC 13603