Document jy1KGj3KVx4oJd5Lm6xe25NQ2
ASARCO INCORPORATED CENTRAL ENGINEERING DEPARTMENT FIELD CONSTRUCTION
GAS HANDLING, CLEANING 6 ACID PLT EL PASO, TEXAS JANUARY 22, 1979
Mr. Julio Serra-Jones Monsanto Envlro-Chem Systems, Corporate Square Office Park
Box 145^7 St. Louis, Missouri 63178
Inc.
RE: EA-26-EP, N.Y. 395*f, Pit 623 Gas Handling, Cleaning and Acid Plant
^-file - 8.3.2 Monsanto (Proposal) Release of Fee Payments - Pit Acceptance
Dear Julio:
Your letter of December 27, 1978, regarding the release of the remaining
fee payments has been signed. A qualification has been added which is initialed by me. If you have no objection, please initial and return a copy for our contract
file.
Your Invoices No. 533^1-ifO-LC and No. 53248-AO-LC for the June and July 1978 fee payment have been approved for payment. This should clear up all outstanding payments relating to engineering and fees under the contract.
Yours truly.
Senior Construction Engineer
RHH:bo Ends. - As Stated
E. S. Godsey's Acceptance Test Report
cc: W. T. Sweat, w/letter W. A. Bennis, w/letter W. R. Mahoney, w/letter W. R. Kelly, w/letter C. Glaser, w/attachments 623-FC-4A8
ASARCO ELP 0007978
Monsanto Enviro-Chem
Monsanto Enviro-Chom Systems Inc. Corporate Square Office Park Box 14547 St. Louis, Missouri 63178 Phone: (314) 694-1000
December 27, 1978
3
Mr. R. H. Hunt ASARCO, Incoruorated P. 0. Box 1111 El Paso, Texas 79999
Reference: ASARCO Order No. 17H 0711
Subject : EA-26-EP, NY-3954 Pit. 623 MEC Letter No. 2102-231 PLANT ACCEPTANCE ASARCO File No. 8.3
Dear Rod:
This is a confirmation of our meeting of December 15 concern ing plant demonstration and acceptance.
In accordance with Article 6, I, "Performance Guarantees" of the contract, a performance demonstration run was made during the period of December 12 through December 15, 1978 and the plant was tested according to the provisions of Exhibit A, "Performance Guarantees and Tests".
The results of these tests, performed by Mr. E. Godsey from ASARCO Central Engineering Department, indicate that the plant has met the performance guarantees. Consequently, our obliga tions with respect to Article 6, I, "Performance Guarantees" have been fulfilled. We, therefore, request that you release the remaining fee payments as our agreement of last April.
I would like to re-iterate that although the performance guarantees have been met, we acknowledge that there exists a potential design and worfcnanship guarantee obligation concern ing the fiber-bed mist eliminators in the interpass tower.
ASARCO ELP 0007979
Mr. R. H. Hunt
2- -
JLS-J
12/27/78
Our Engineering Department is evaluating the situation and any corrective actions required will be handled under the provisions of Article 6, III, of the contract.
If you are in agreement with the foregoing, please sign one copy of this letter and return to me at your earliest convenience.
Sincerely,
MONSANTO ENVIRO-CHEM SYSTEMS INC.
jkb
c -*r. 1
Julio Serra-Jones Estimating 5c Control Director
AGREED BY: R. H. Hunt
DATE:
/
'- /
Qua! if ication j-. tS
The above letter has been agreed to and the remaining fee payments released as per items U and 5 of contract Amendment No. 1, dated April 17, 1978.
However, as stated in the conclusions of the acceptance test signed by Mr. E. S. Godsey, the conditions during the test were not up to the design capacity
From Godsey's Acceptance Test Report, January 17, 1979
"CONCLUSIONS"
"Based on the face value of the tests conducted the plant appears to meet the contract guarantee values. However, it must be noted that only during one of the three tests did the feed gas SO2 grade reach the design range. It should be further noted that during all tests the plant was operated at a flow rate well below the design capacity."
When the intended source of gas to plant is established (i.e. lead sintering and copper roaster plants), another acceptance test will be performed and witnessed by Monsanto. The performance and other guarantees referenced in Article 6 of the contract will apply./'Js" / y
ASARCO ELP 0007980